Chua Chay Lee v Premier Properties: Repudiatory Breach & Contract Termination

In Chua Chay Lee and Others v Premier Properties Pte Ltd, the Court of Appeal of Singapore dismissed the appeal of apartment owners (appellants) who sought to terminate their contract with Premier Properties (respondents) due to construction delays. The appellants claimed anticipatory breach, arguing the respondents could not meet the original deadline. The court, however, found that the delay did not constitute a repudiatory breach, and the appellants were not entitled to terminate the agreement. The court considered the liquidated damages clause and the progress made by the respondents before the termination notice.

1. Case Overview

1.1 Court

Court of Appeal

1.2 Outcome

Appeal dismissed.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Apartment owners claimed anticipatory breach due to construction delays. The court dismissed the appeal, finding no repudiatory breach by the developer.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Chua Chay LeeAppellantIndividualAppeal DismissedLostThio Shen Yi, Priscilla Chang
Premier Properties Pte LtdRespondentCorporationAppeal DismissedWonMohan Pillay, Andre Maniam

3. Judges

Judge NameTitleDelivered Judgment
Chao Hick TinJustice of the Court of AppealYes
Tan Lee MengJudgeNo
Yong Pung HowChief JusticeNo

4. Counsels

Counsel NameOrganization
Thio Shen YiThio Su Mien & Partners
Priscilla ChangThio Su Mien & Partners
Mohan PillayWong Partnership
Andre ManiamWong Partnership

4. Facts

  1. The respondents, property developers, sought to redevelop a site with 24 apartments.
  2. The respondents offered apartment owners the option to exchange their old apartments for new ones to be built on the redeveloped site.
  3. The appellants opted to exchange their old apartments for new ones.
  4. The agreement stipulated a deadline of 33 months for handing over the new apartments.
  5. The agreement included a liquidated damages clause for delays at a rate of 10% per annum on $2,805,000.
  6. The respondents acquired additional land, expanding the housing project.
  7. The appellants terminated the agreement due to concerns about delays and the respondents' financial difficulties.

5. Formal Citations

  1. Chua Chay Lee and Others v Premier Properties Pte Ltd, CA 182/1999, [2000] SGCA 34

6. Timeline

DateEvent
Agreement for en-bloc transfer of apartments signed.
Preview of the working model of the project.
Business Times quoted the respondents' representative as saying that the respondents would sell their St Martins' land if the price was right.
Respondents invited the appellants to select their new apartments on 8 May 1999.
Date the appellants were invited to select their new apartments.
Appellants' solicitors wrote to the respondents' solicitors to terminate the agreement.
Appellants' solicitors wrote to the bank to demand the payment of $2,762,603.84 under the performance guarantee.
Respondents' solicitors replied that their clients considered the termination by the appellants of the agreement as wrongful.
Respondents' solicitors wrote to the appellants' solicitors to point out that the appellants had already been verbally informed that the date for completion for their apartments was set back by only about a year.
Appellants' solicitors responded to the respondents' solicitors' letter of 18 May 1999.
Respondents took out an originating summons to determine whether the appellants' demands under the performance guarantees were valid.
Decision Date

7. Legal Issues

  1. Repudiatory Breach
    • Outcome: The court held that the delay in construction did not constitute a repudiatory breach of contract.
    • Category: Substantive
    • Sub-Issues:
      • Anticipatory breach
      • Delay in performance
    • Related Cases:
      • [1949] Ch 649
      • [1957] 2 QB 401
      • [1962] 2 QB 26
      • [1980] AC 827
      • [1983] 1 All ER 449
      • [1979] AC 757
      • [1971] 1 WLR 361
      • [1967] 1 AC 361
      • [1989] 166 CLR 623
      • [1940] 3 All ER 60
  2. Contract Termination
    • Outcome: The court held that the apartment owners were not entitled to terminate the agreement.
    • Category: Substantive

8. Remedies Sought

  1. Termination of Contract
  2. Damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Litigation
  • Construction Law

11. Industries

  • Construction
  • Real Estate

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Thorpe v FaseyHigh Court of JusticeYes[1949] Ch 649England and WalesEndorsed the approach that there is no distinction between the nature of repudiation required to constitute an anticipatory breach and that required where the alleged breach occurs after the time for performance has arisen.
Universal Cargo Carriers Corp v CitatiQueen's Bench DivisionYes[1957] 2 QB 401England and WalesExplained that a party is allowed to anticipate an inevitable event and is not obliged to wait till it happens, it must follow that the breach which he anticipates is of the same character as the breach which would actually have occurred if he had waited. Also, reiterated that while the application of the doctrine of frustration is a matter of law, the assessment of a period of delay sufficient to constitute frustration is a question of fact.
Hongkong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha LtdCourt of AppealYes[1962] 2 QB 26England and WalesAddressed the question of whether the occurrence of the event deprive the party who has further undertakings still to perform of substantially the whole benefit which it was the intention of the parties as expressed in the contract that he should obtain as the consideration for performing those undertakings?
Photo Production Ltd v Securicor Transport LtdHouse of LordsYes[1980] AC 827United KingdomReiterated that the effect of a failure by one party to perform his primary obligation depends on whether it has the effect of depriving the other party of substantially the whole benefit he was intended to have under the contract.
Afovos Shipping Co SA v R Pagnan & F LliHouse of LordsYes[1983] 1 All ER 449United KingdomReiterated that the effect of a failure by one party to perform his primary obligation depends on whether it has the effect of depriving the other party of substantially the whole benefit he was intended to have under the contract.
The Nanfri; Federal Commerce & Navigation Co Ltd v Molena Alpha Inc & OrsHouse of LordsYes[1979] AC 757United KingdomThe test of repudiation has been formulated in various ways by different judges. Will the consequences of the breach be such that it would be unfair to the injured party to hold him to the contract and leave him to his remedy in damages as and when a breach or breaches may occur? If this would be so, then a repudiation has taken place.
Decro-Wall International SA v Practitioners in Marketing LtdCourt of AppealYes[1971] 1 WLR 361England and WalesFormulation by Buckley LJ: `Will the consequences of the breach be such that it would be unfair to the injured party to hold him to the contract and leave him to his remedy in damages as and when a breach or breaches may occur? If this would be so, then a repudiation has taken place.`
Suisse Atlantique Société d`Armement Maritime SA v NV Rotterdamsche Kolen CentraleHouse of LordsYes[1967] 1 AC 361United KingdomThe `deliberate` character of a breach cannot, in my opinion, of itself give to a breach of contract a `fundamental` character, in either sense of that word.
Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty LtdHigh Court of AustraliaYes[1989] 166 CLR 623AustraliaThere is a difference between evincing an intention to carry out a contract only if and when it suits the party to do so and evincing an intention to carry out a contract as and when it suits the party to do so.
Ross T Smyth & Co Ltd v TD Bailey Son & CoHouse of LordsYes[1940] 3 All ER 60United KingdomI do not say that it is necessary to show that the party alleged to have repudiated should have an actual intention not to fulfil the contract. He may intend in fact to fulfil it, but may be determined to do so only in a manner substantially inconsistent with his obligations and not in any other way.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Repudiatory Breach
  • Anticipatory Breach
  • Liquidated Damages
  • En-bloc Transfer
  • Performance Guarantee
  • Handing Over Date

15.2 Keywords

  • Contract
  • Breach
  • Repudiation
  • Apartment
  • Construction
  • Delay
  • Singapore

16. Subjects

  • Contract Law
  • Real Estate Law
  • Construction Dispute

17. Areas of Law

  • Contract Law
  • Building and Construction Law