Premier Properties v Tan Soo Tiong: En-Bloc Sale Dispute over Wrongful Demand and Delay

In Premier Properties Pte Ltd v Tan Soo Tiong, the High Court of Singapore addressed a dispute arising from an en-bloc sale agreement. Premier Properties, the plaintiff, sought a declaration that the demands made by the defendants, Tan Soo Tiong and others, under performance guarantees were wrongful and invalid. The defendants counterclaimed for various declarations, alleging breach of contract and seeking to terminate the agreement due to delays in delivering vacant possession of new flats. The court (Lee Seiu Kin JC) declared the demands wrongful, found Premier Properties in breach for failing to deliver vacant possession by the due date, and held that the defendants were not entitled to terminate the agreement. The court also ruled on the payment of liquidated damages.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

The court declared the demands wrongful and invalid, found the Plaintiffs in breach of contract for failing to deliver vacant possession, and held that the Defendants were not entitled to terminate the agreement.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Premier Properties sought a declaration that demands by Tan Soo Tiong for en-bloc sale guarantees were wrongful. The court addressed breach and termination.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Chua Chay LeeDefendantIndividualDemands declared wrongful and invalidLost
Premier Properties Pte LtdPlaintiffCorporationDemands declared wrongful and invalidWon
Tan Soo TiongDefendantIndividualDemands declared wrongful and invalidLost
Loei Tiak binDefendantIndividualDemands declared wrongful and invalidLost
Eunice Chee Ai LienDefendantIndividualDemands declared wrongful and invalidLost
Phoebe FongDefendantIndividualDemands declared wrongful and invalidLost

3. Judges

Judge NameTitleDelivered Judgment
Lee Seiu KinJudicial CommissionerYes

4. Counsels

4. Facts

  1. The Plaintiffs are property developers.
  2. The five Defendants were owners of various units in two blocks of 24 apartments.
  3. The parties entered into an agreement for en-bloc sale of the 24 apartments on 22 March 1996.
  4. The Plaintiffs had procured a banker's guarantee for each of the Defendants in November 1996.
  5. The Defendants made demands under these guarantees for the sum of $2,762,603.84 each on 12 May 1999.
  6. The Plaintiffs sought a declaration that those demands were wrongful and invalid.
  7. The Handing Over Date was 28 August 1999 and the Plaintiffs had failed to deliver possession of the New Flats to the Defendants on that date.

5. Formal Citations

  1. Premier Properties Pte Ltd v Tan Soo Tiong and Others, OS 789/1999, [2000] SGHC 12

6. Timeline

DateEvent
Agreement for en-bloc sale made
Plaintiffs procured banker's guarantee for each defendant
Completion Date; Defendants transferred titles to apartments to Plaintiffs
Defendants delivered vacant possession of apartments
Preview of proposed development
Receipt of preliminary layout
Approval of name
URA Grant of Written Permission
Housing Developer's Licence
PWD Approval
BCA Approval
Corrigendum on URA Approval
Notice to attend selection served to defendants
Defendants' solicitors' letter
Plaintiffs' solicitors’ letter
First and third Defendants attended a preview of the selection
Defendants' solicitors' letter to Plaintiffs' solicitors purporting to terminate the Agreement
Defendants made demands under guarantees
Plaintiffs took out Originating Summons
Second Defendant filed an affidavit on behalf of all five Defendants
Project commenced
Inspection of site showed construction work had barely started
Defendants filed Notice of Counterclaim
Plaintiffs filed affidavit
Handing Over Date
Hearing of counsel for the parties
Decision Date

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found the Plaintiffs in breach of contract for failing to deliver vacant possession of the New Flats to the Defendants by the due date.
    • Category: Substantive
    • Sub-Issues:
      • Failure to deliver vacant possession
      • Delay in completion of development
  2. Repudiation of Contract
    • Outcome: The court held that the Defendants were not entitled to terminate the Agreement dated 22 March 1996.
    • Category: Substantive
    • Sub-Issues:
      • Anticipatory breach
      • Termination of agreement
  3. Validity of Demand under Guarantee
    • Outcome: The court declared the demands dated 12 May 1999 by the Defendants collectively for the sum of $2,762,603.84 each on the performance guarantees dated 29 November 1996 issued by the Hongkong and Shanghai Banking Corporation Ltd are wrongful and invalid.
    • Category: Substantive
    • Sub-Issues:
      • Condition precedent
      • Compliance with terms of guarantee
  4. Frustration of Contract
    • Outcome: The court held that the delay of 12 months in the circumstances of the case has not so altered the nature of the bargain as to frustrate the contract.
    • Category: Substantive
    • Sub-Issues:
      • Abnormal delay
      • Unforeseeable event

8. Remedies Sought

  1. Declaration that demands were wrongful and invalid
  2. Damages for breach of contract

9. Cause of Actions

  • Breach of Contract
  • Wrongful Demand under Guarantee

10. Practice Areas

  • Commercial Litigation
  • Construction Dispute

11. Industries

  • Real Estate
  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Universal Cargo Carriers Corporation v CitatiQueen's BenchYes[1957] 2 QB 401England and WalesCited regarding how long a ship is obliged to remain on demurrage and the rights of the owner if the charterer detains her too long.
A.G. v Wong Wai ChengCourt not specifiedYes[1978-1979] SLR 151SingaporeCited by the Plaintiffs but the court did not find it useful because it dealt with a provision in the contract that specifically provided that any delay shall not vitiate the contract.
Pioneer Shipping Ltd v B.T.P. Tioxide Ltd (The Nema)House of LordsYes[1982] AC 724England and WalesCited for the test of whether the delay will make any ultimate performance of the relevant contractual obligations 'radically different' from that which was undertaken by the contract.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • En-bloc sale
  • Banker's guarantee
  • Performance bond
  • Vacant possession
  • Handing Over Date
  • Liquidated damages
  • Repudiation
  • Frustration

15.2 Keywords

  • en-bloc sale
  • wrongful demand
  • breach of contract
  • liquidated damages
  • Singapore
  • property development

17. Areas of Law

16. Subjects

  • Contract Law
  • Real Estate
  • Construction