L & M Concrete Specialists v United Eng Contractors: Appeal on Registrar's Directions in Construction Dispute

In a dispute between L & M Concrete Specialists Pte Ltd and United Eng Contractors Pte Ltd, the High Court of Singapore heard an appeal by L & M Concrete Specialists against the Registrar's directions regarding trial dates. The appeal stemmed from a construction project at Hilltops Apartments, with a counterclaim by United Eng Contractors related to the Sinsov Building project. The court dismissed the appeal, refusing to vacate the trial dates pending the outcome of an appeal on security for costs.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Appeal dismissed

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Appeal concerning Registrar's directions in a construction dispute. The court dismissed the appeal, refusing to vacate trial dates pending appeal on security for costs.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
L & M Concrete Specialists Pte LtdPlaintiff, AppellantCorporationAppeal dismissedLostSean Tan, Michael Low
United Eng Contractors Pte LtdDefendant, RespondentCorporationAppeal dismissedWonRama Kasi

3. Judges

Judge NameTitleDelivered Judgment
Tay Yong KwangJudicial CommissionerYes

4. Counsels

Counsel NameOrganization
Sean TanJ Koh & Co
Michael LowJ Koh & Co
Rama KasiRaj Kumar & Rama

4. Facts

  1. Plaintiffs appealed against Registrar's directions at a pre-trial conference.
  2. The Registrar set deadlines for exchanging affidavits and setting down the action for trial.
  3. Plaintiffs sought to vacate the trial dates pending an appeal on security for costs.
  4. Defendants' counterclaim related to a separate project at the Sinsov Building.
  5. Plaintiffs applied for security for costs based on Defendants' financial status.
  6. A winding-up petition was pending against the Defendants.
  7. The High Court Judge had previously allowed the Defendants’ appeal against the Assistant Registrar’s decision on security for costs.

5. Formal Citations

  1. L & M Concrete Specialists Pte Ltd v United Eng Contractors Pte Ltd, Suit 600131/2000 ,RA 600154/2001, [2001] SGHC 285

6. Timeline

DateEvent
Writ of Summons
Defence & Counterclaim
Reply & Defence to Counterclaim
Amended Defence & Counterclaim
Amended Reply, Defence to Counterclaim And Counterclaim to Counterclaim
Summons-For-Directions
Notice for Further Directions by Plaintiffs
Plaintiff’s Application for security for costs fixed for hearing
Orders made at further PTC
Eng’s Affidavit (filed/served) in respect of security for costs hearing.
Further Affidavit by Plaintiff in respect of security for costs hearing
Security for costs hearing before A.R. Order made for Defendant to furnish security in the sum of $50,000.00 within 7 days
Appeal hearing on security for costs before Justice J. Prakash
Urgent PTC before Registrar
Appeal lodged against court's decision
Judgment issued

7. Legal Issues

  1. Vacation of Trial Dates
    • Outcome: The court refused to vacate the trial dates.
    • Category: Procedural
  2. Security for Costs
    • Outcome: The court considered the appeal on security for costs but did not make a ruling on the merits of the security for costs application itself in this judgment.
    • Category: Procedural

8. Remedies Sought

  1. Vacation of trial dates

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Dispute
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Dickson Trading (S) Pte Ltd v Transmarco LtdHigh CourtYes[1989] 2 MLJ 408SingaporeCited for principles regarding stay of execution and interim injunctions pending appeal.
Erinford Properties Ltd & Anor v Cheshire County CouncilChYes[1974] Ch 261England and WalesCited regarding interim injunction pending appeal.
Wilson v Church (No.2)ChDYes(1879-80) 12 ChD 454England and WalesCited regarding the court's discretion not to render an appeal nugatory.

13. Applicable Rules

Rule Name
O. 23 r. 1 of the Rules of Court
O. 57 r. 20

14. Applicable Statutes

Statute NameJurisdiction
Section 388 of the Companies ActSingapore

15. Key Terms and Keywords

15.1 Key Terms

  • Pre-trial conference
  • Security for costs
  • Affidavits of evidence-in-chief
  • Winding up petition
  • Counterclaim
  • Construction work

15.2 Keywords

  • construction
  • appeal
  • registrar
  • security for costs
  • trial dates

16. Subjects

  • Civil Procedure
  • Construction Dispute

17. Areas of Law

  • Civil Procedure
  • Construction Law