Chai Yong Construction v Chan Hock Seng: Construction Dispute over Angsana Avenue Property
In Chai Yong Construction Co Pte Ltd v Chan Hock Seng and Han Lili, the High Court of Singapore ruled in favor of Chai Yong Construction in a dispute over a construction contract. Chai Yong Construction sued Chan Hock Seng and Han Lili for breach of contract related to construction and renovation work at Angsana Avenue. The court, presided over by Justice Lai Siu Chiu, found that Chai Yong Construction had satisfactorily proven their claim and dismissed the defendants' counterclaim, awarding damages and costs to the plaintiff.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Judgment for Plaintiff
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Chai Yong Construction sues Chan Hock Seng for breach of contract related to construction and renovation work. The court found in favor of Chai Yong Construction, dismissing Chan Hock Seng's counterclaim.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Chan Hock Seng | Defendant | Individual | Claim Dismissed | Lost | |
Chai Yong Construction Co Pte Ltd | Plaintiff | Corporation | Judgment for Plaintiff | Won | |
Han Lili | Defendant | Individual | Claim Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Lai Siu Chiu | Judge | Yes |
4. Counsels
4. Facts
- Chai Yong Construction was contracted to build a house and renovate another for Chan Hock Seng and Han Lili.
- The contract price was $729,000, governed by Singapore Institute of Architects Conditions of Contract.
- The plaintiffs furnished a performance bond of $72,900.
- The plaintiffs completed construction on 2 June 1999.
- The Building Control Authority refused to issue a Temporary Occupation Licence after an inspection.
- The first defendant ejected the plaintiffs from the site on 11 July 1999.
- The defendants claimed the plaintiffs' works were defective and lodged a counterclaim.
5. Formal Citations
- Chai Yong Construction Co Pte Ltd v Chan Hock Seng and Another, Suit 600276/2000, [2001] SGHC 360
6. Timeline
Date | Event |
---|---|
Original construction contract awarded to Rock Create Pte Ltd | |
First defendant incarcerated | |
Letter of award issued to Chai Yong Construction Co Pte Ltd | |
Rock Create's services terminated | |
Chai Yong Construction Co Pte Ltd given possession of the site | |
Performance bond issued by Cosmic Insurance Corporation Ltd | |
First defendant released from incarceration | |
Plaintiffs completed construction | |
First defendant submitted a list of defects | |
Defendants selected toilet doors | |
Soh issued certificate of payment no. Ala/09 | |
Certificate delivered to the defendants | |
Building Control Authority inspection | |
Building Control Authority refused to issue a Temporary Occupation Licence | |
Completion date under the agreement | |
Soh issued a Delay Certificate | |
Plaintiffs requested issuance of an Architect's Instruction for handrail installation | |
Plaintiffs asserted reasons for delay in issuance of the Temporary Occupation Licence | |
Soh issued an Architect's Instruction for installation of the handrails | |
Incident at the property involving Thai workers | |
Plaintiffs ejected from the site | |
Soh requested that the plaintiffs complete outstanding items of work | |
Without prejudice negotiations culminated in a meeting | |
Plaintiffs' solicitors wrote to the defendants and Soh setting out the terms of the agreement | |
Soh wrote to the plaintiffs' solicitors to inquire if the plaintiffs would be willing to install the handrails and toilet doors | |
First defendant issued a Notice of Termination to the plaintiffs | |
Defendants wrote to Soh requesting action on previous letters and list of defects | |
First defendant called for payment on the performance bond | |
Plaintiffs' solicitors replied to Soh indicating the plaintiffs' willingness to do the work requested | |
Ho informed by Cosmic that the first defendant called for payment on the performance bond | |
Soh told Ho that he would speak to the first defendant with a view to resolving the matter amicably | |
Defendants wrote to the Building Control Authority to withdraw their application for Temporary Occupation Licence | |
Soh told Ho that he was discussing the matter with the defendants and was confident that a settlement could be achieved | |
Soh wrote to the Building Control Authority to say that five of the items highlighted in Building Control Authority's letter dated 5 July 1999 would be complied with | |
Cosmic informed Ho that the first defendant was demanding payment of the sum under the performance bond | |
Plaintiffs filed D C Suit No. 4415 of 1999 and applied for an interim injunction | |
Defendants suspended the services of Soh | |
Soh notified the plaintiffs that he was no longer the qualified person for the project | |
Defendants applied to set aside the plaintiffs' interim injunction but failed | |
Defendants appointed Peter Von Selkey of Seifert Asia to take over from Soh as the architect | |
Temporary Occupation Licence issued for both properties | |
Suit transferred to the High Court | |
Certificate of Statutory Completion issued | |
Part-hearings took place | |
Trial resumed | |
Decision Date |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that the defendants breached the construction contract.
- Category: Substantive
- Sub-Issues:
- Failure to make payment
- Defective workmanship
- Delay in completion
- Defective Workmanship
- Outcome: The court found that some defects were due to the plaintiffs' workmanship, while others were caused by the defendants' actions.
- Category: Substantive
- Sub-Issues:
- Water ingress
- Mismatching of roof tiles
- Roof leakage
- Insufficient roof insulation
- Rusting of railings
- Leaks from copper piping
- Wrongful Call on Performance Bond
- Outcome: The court found that the defendants were not justified in calling on the performance bond.
- Category: Substantive
8. Remedies Sought
- Balance of contract sum
- Damages for defective works
- Indemnity
- Loss of rent
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Construction Disputes
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
No cited cases |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Construction contract
- Defects
- Performance bond
- Temporary Occupation Licence
- Certificate of Statutory Completion
- SIA Conditions
- Lump sum price
- Water ingress
- Roof leakage
- Anti-termite treatment
15.2 Keywords
- construction
- contract
- defects
- performance bond
- Singapore
- High Court
17. Areas of Law
16. Subjects
- Construction Dispute
- Contract Law