Guobena Sdn Bhd v New Civilbuild Pte Ltd: Damages for Breach of Sub-Contract
Guobena Sdn Bhd, the main contractor for the Tanglin Regency project, appealed against the High Court's decision ordering them to pay New Civilbuild Pte Ltd, the sub-contractor, $1,748,624.65 for monies due under the sub-contract. The Court of Appeal dismissed the appeal, affirming the High Court's decision. The court determined that Guobena's argument to ignore the original contract sum when calculating the final accounts was incorrect, and that New Civilbuild was entitled to the outstanding amount.
1. Case Overview
1.1 Court
Court of Appeal1.2 Outcome
Appeal dismissed
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Appeal regarding damages for breach of sub-contract. The Court of Appeal held Guobena liable to pay New Civilbuild $1,748,624.65.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Guobena Sdn Bhd | Appellant | Corporation | Appeal dismissed | Lost | |
New Civilbuild Pte Ltd | Respondent | Corporation | Judgment for Respondent | Won |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Chao Hick Tin | Judge of Appeal | No |
Tan Lee Meng | Judge | No |
Yong Pung How | Chief Justice | Yes |
4. Counsels
4. Facts
- New Civilbuild (NCB) was a sub-contractor for a condominium project, Tanglin Regency.
- Guobena (GSB) was the main contractor of the Tanglin Regency project.
- The sub-contract between NCB and GSB was for structural and architectural works, valued at $16,413,047.88, later increased to $16,800,732.03.
- NCB claimed outstanding progress payments and return of retention monies.
- GSB counter-claimed for damages for delay and non-compliance, including expenses to complete the project.
- GSB made a demand on the performance bond issued by Tai Ping Insurance Co Ltd.
- The Assistant Registrar gave judgment in favour of GSB for $72,150.61, which was appealed by NCB.
5. Formal Citations
- Guobena Sdn Bhd v New Civilbuild Pte Ltd, CA 600140/2001, [2002] SGCA 39
6. Timeline
Date | Event |
---|---|
Action instituted by New Civilbuild Pte Ltd | |
Trial judge ruled on progress claims and counterclaim | |
Case Number CA 600140/2001 | |
Appeal dismissed |
7. Legal Issues
- Breach of Contract
- Outcome: The court held that Guobena was liable for breach of contract and had to pay New Civilbuild the outstanding amount.
- Category: Substantive
- Assessment of Damages
- Outcome: The court determined the correct measure of damages claimable by the aggrieved party, emphasizing the principle of restitutio in integrum.
- Category: Substantive
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Commercial Litigation
- Construction Law
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Victoria Laundry (Winsdor) Ltd v Newman Industries Ltd | KB | Yes | [1949] 2 KB 528 | England and Wales | Cited regarding the principle of remoteness and measure of damages in contract law. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Sub-contract
- Performance bond
- Restitutio in integrum
- Damages
- Progress payments
- Retention monies
- Counterclaim
- Mutual set-offs
- Contract sum
- Agreed variations
15.2 Keywords
- Breach of contract
- Damages
- Construction
- Sub-contract
- Singapore
- Court of Appeal
17. Areas of Law
Area Name | Relevance Score |
---|---|
Breach of Contract | 95 |
Contract Law | 90 |
Damages | 85 |
Contracts | 80 |
Restituo in integrum | 70 |
Assessment of Damages | 65 |
16. Subjects
- Contract Law
- Construction Law
- Damages