Johnson Controls v Ho Air-Conditioning: Breach of Contract and Waiver in Equipment Supply
Johnson Controls (S) Pte Ltd (“Johnson”) sued Ho Air-Conditioning & Engineering Pte Ltd (“Ho Aircon”) in the High Court of Singapore on 30 April 2004, for the balance of a contract sum. Ho Aircon counterclaimed for liquidated damages and costs to remedy defects. The court found that Ho Aircon had waived the strict terms of the contract by accepting newer models of equipment and certifying completion of work. The court ruled in favor of Johnson, ordering Ho Aircon to pay the outstanding contract sum and costs for variation work, and dismissed Ho Aircon's counterclaim.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Judgment for Plaintiff
1.3 Case Type
Civil
1.4 Judgment Type
Judgment reserved
1.5 Jurisdiction
Singapore
1.6 Description
Johnson Controls sued Ho Air-Conditioning for breach of contract. The court found Ho Air-Conditioning liable for the balance of the contract sum.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Johnson Controls (S) Pte Ltd | Plaintiff | Corporation | Judgment for Plaintiff | Won | |
Ho Air-Conditioning and Engineering Pte Ltd | Defendant | Corporation | Counterclaim Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Tan Lee Meng | Judge | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Satwant Singh | Sim Mong Teck and Partners |
Lim Joo Toon | Joo Toon and Co |
4. Facts
- Johnson sued Ho Aircon for the balance of the contract sum.
- Ho Aircon counterclaimed for liquidated damages and costs to remedy defects.
- Ho Aircon accepted newer models of equipment from Johnson.
- Ho Aircon certified that Johnson had completed 100% of the work.
- Ho Aircon claimed Johnson failed to deliver some equipment.
- Ho Aircon claimed liquidated damages for delayed completion.
- Ho Aircon claimed costs for rectifying defects.
5. Formal Citations
- Johnson Controls (S) Pte Ltd v Ho Air-Conditioning and Engineering Pte Ltd, Suit 1116/2002, [2004] SGHC 86
6. Timeline
Date | Event |
---|---|
Liquidated damages incurred for phase 2 | |
Liquidated damages incurred for phase 2 | |
Liquidated damages incurred for phase 3 | |
Liquidated damages incurred for phase 3 | |
Action instituted by Johnson | |
Judgment reserved |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that the defendant was in breach of contract but had waived certain requirements.
- Category: Substantive
- Sub-Issues:
- Failure to complete work on time
- Substitution of equipment
- Waiver
- Outcome: The court held that the defendant waived the requirement for strict adherence to the contract terms by accepting newer models of equipment and certifying completion of work.
- Category: Substantive
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Commercial Litigation
- Construction Disputes
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Hoenig v Isaacs | English Court of Appeal | Yes | [1952] 2 All ER 176 | England and Wales | Cited for the principle of waiver in the context of a construction contract. |
Dunlop Pneumatic Tyre Company, Limited v New Garage and Motor Company, Limited | House of Lords | Yes | [1915] AC 79 | United Kingdom | Cited regarding the requirements of a liquidated damages clause. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Contract Sum
- Liquidated Damages
- Defects Liability Period
- Waiver
- Substituted Equipment
- Testing and Commissioning
- Progress Claim
- Certification
15.2 Keywords
- Contract
- Breach
- Waiver
- Construction
- Equipment
- Singapore
17. Areas of Law
Area Name | Relevance Score |
---|---|
Breach of Contract | 90 |
Contract Law | 80 |
Contracts | 70 |
Waiver | 60 |
Building and Construction Contracts | 30 |
Construction Law | 30 |
16. Subjects
- Contract Dispute
- Construction Contract
- Equipment Supply