C & P Holdings v Witco Industries: Breach of Contract Dispute over ISO Tank Cleaning Facilities
In a suit before the High Court of Singapore on 20 January 2006, C & P Holdings Pte Ltd sued Witco Industries Pte Ltd for breach of contract, alleging failure to deliver and install ISO Tank Cleaning and Wastewater Treatment Facilities by the agreed date. Witco Industries counterclaimed for the outstanding balance due under the contract. Justice Choo Han Teck dismissed C & P Holdings' claim, finding that C & P Holdings was in breach of contract by failing to make payment. The court allowed Witco Industries' counterclaim in part, ordering C & P Holdings to pay $250,000, after deducting $34,850 for resources left idle due to C & P Holdings' breach.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Plaintiff's claim dismissed; Defendant's counterclaim allowed in part.
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
C & P Holdings sued Witco Industries for breach of contract related to the design, build, and installation of ISO tank cleaning facilities. The court dismissed the claim and allowed Witco's counterclaim.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
C & P Holdings Pte Ltd | Plaintiff | Corporation | Claim Dismissed | Lost | |
Witco Industries Pte Ltd | Defendant | Corporation | Counterclaim Allowed in part | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Choo Han Teck | Judge | Yes |
4. Counsels
4. Facts
- Plaintiff commissioned defendant to design and build ISO Tank Cleaning and Wastewater Treatment Facilities.
- The facilities were to be delivered and installed by 30 November 2004.
- The total contract sum was $584,850 inclusive of goods and services tax.
- The initial down payment of $200,000 was paid.
- The defendant claimed the plaintiff did not wish to make the corresponding payment.
- The plaintiff gave an incomplete and unbankable cheque.
- The plaintiff terminated the contract on 23 December 2004.
5. Formal Citations
- C & P Holdings Pte Ltd v Witco Industries Pte Ltd, , [2006] SGHC 8
6. Timeline
Date | Event |
---|---|
Contract signed | |
Plaintiff invited to inspect equipment | |
Defendant delivered part of the equipment | |
Seow agreed with Kwek for delivery of the rest of the equipment to be made on 17 December 2004 | |
Defendant arrived at plaintiff’s premises with the equipment but left without unloading | |
Defendant delivered the remaining equipment | |
Defendant notified by its bank that the plaintiff’s cheque was dishonoured | |
Contract terminated | |
Judgment reserved |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that the plaintiff, C & P Holdings, was in breach of contract for failing to make payment.
- Category: Substantive
- Sub-Issues:
- Failure to make payment
- Failure to honour contractual delivery date
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
No cited cases |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- ISO Tank Cleaning and Wastewater Treatment Facilities
- Contractual delivery and installation date
- Down payment
- Progressive claims
- Defects liability period
- Dishonoured cheque
- Termination of contract
15.2 Keywords
- breach of contract
- ISO tank cleaning
- wastewater treatment
- construction
- Singapore
- High Court
17. Areas of Law
Area Name | Relevance Score |
---|---|
Breach of Contract | 90 |
Contract Law | 80 |
Commercial Disputes | 60 |
16. Subjects
- Construction Dispute
- Contract Law