W Y Steel v Osko: Security of Payment Act Adjudication Dispute
W Y Steel Construction Pte Ltd appealed against the High Court's decision to refuse setting aside an adjudication determination ordering them to pay $1,767,069.80 to Osko Pte Ltd under the Building and Construction Industry Security of Payment Act. W Y Steel also sought a stay of enforcement pending separate proceedings. The Court of Appeal dismissed the appeal, holding that the adjudicator did not err in refusing to consider W Y Steel's late submissions due to their failure to file a timely payment response. The court also denied the stay application, finding insufficient evidence of Osko's financial distress.
1. Case Overview
1.1 Court
Court of Appeal1.2 Outcome
Appeal dismissed and stay application denied.
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Appeal regarding an adjudication determination under the Building and Construction Industry Security of Payment Act. Appeal dismissed; stay application denied.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
W Y Steel Construction Pte Ltd | Appellant | Corporation | Appeal Dismissed | Lost | |
Osko Pte Ltd | Respondent | Corporation | Appeal Upheld | Won |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Sundaresh Menon | Chief Justice | Yes |
V K Rajah | Justice of the Court of Appeal | No |
Quentin Loh | Judge | No |
4. Counsels
4. Facts
- W Y Steel was the main contractor for alteration works at the Singapore Turf Club.
- W Y Steel subcontracted part of the work to Osko for $3,752,436.15.
- W Y Steel purported to terminate the sub-contract on 12 March 2012.
- Osko claimed it continued working until 31 March 2012 and served a payment claim.
- W Y Steel failed to file a payment response within the statutory deadline.
- Osko filed an adjudication application, and W Y Steel again failed to file a response.
- The adjudicator ordered W Y Steel to pay Osko $1,767,069.80.
5. Formal Citations
- W Y Steel Construction Pte Ltd v Osko Pte Ltd, Civil Appeal No 108 of 2012, [2013] SGCA 32
6. Timeline
Date | Event |
---|---|
Contract signed between W Y Steel and Singapore Turf Club. | |
W Y Steel purported to terminate the Sub-Contract with Osko. | |
Osko served a payment claim on W Y Steel. | |
W Y Steel failed to file a payment response by the due date. | |
Osko filed Adjudication Application No SOP/AA036 of 2012 against W Y Steel. | |
W Y Steel did not file an adjudication response by the due date. | |
Adjudication conference held. | |
W Y Steel attempted to file submissions with the Singapore Mediation Centre, but these submissions were rejected. | |
The Adjudicator issued the Adjudication Determination ordering W Y Steel to pay Osko the Adjudicated Sum plus costs and fees. | |
Osko applied under s 27 of the Act for leave to enforce the Adjudication Determination. | |
W Y Steel filed OS 484/2012 to set aside the Adjudication Determination and also paid the Adjudicated Sum into court. | |
OS 484/2012 was heard by the Judge. | |
Court of Appeal dismissed the appeal and stay application. |
7. Legal Issues
- Interpretation of Section 15(3) of the Building and Construction Industry Security of Payment Act
- Outcome: The court held that section 15(3) precludes an adjudicator from considering reasons for withholding payment not included in a timely payment response, even if no payment response was filed.
- Category: Substantive
- Sub-Issues:
- Exclusion of reasons for withholding payment not included in payment response
- Related Cases:
- [2008] SGHC 159
- [2010] 1 SLR 658
- [2010] 3 SLR 459
- [2013] SGHC 56
- Stay of Enforcement of Adjudication Determination
- Outcome: The court held that a stay of enforcement may be justified where there is clear evidence of the claimant's insolvency or irrecoverability of the adjudicated sum, but denied the stay in this case.
- Category: Procedural
- Sub-Issues:
- Financial distress of claimant
- Irrecoverability of adjudicated sum
- Related Cases:
- [2004] NSWCA 394
- [2006] NSWSC 13
- [2004] NSWSC 344
- [2001] CLC 927
- [2001] BLR 416
- [2005] BLR 374
8. Remedies Sought
- Setting aside of Adjudication Determination
- Stay of Enforcement of Adjudication Determination
9. Cause of Actions
- Statutory Claim under the Building and Construction Industry Security of Payment Act
10. Practice Areas
- Construction Litigation
- Commercial Litigation
- Arbitration
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
W Y Steel Construction Pte Ltd v Osko Pte Ltd | High Court | Yes | [2012] SGHC 194 | Singapore | Affirmed the High Court's decision to refuse setting aside the adjudication determination. |
RJT Consulting Engineers Ltd v DM Engineering (Northern Ireland) Ltd | N/A | Yes | [2002] 1 WLR 2344 | United Kingdom | Cited for the principle that parties to a construction contract should 'pay now, argue later'. |
Dawnays Ltd v F G Minter Ltd and Trollope and Colls Ltd | N/A | Yes | [1971] 1 WLR 1205 | United Kingdom | Cited for the rationale for temporary finality in the context of interim certificates of payment. |
Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd | House of Lords | Yes | [1974] AC 689 | United Kingdom | Cited to qualify the principle in Dawnays Ltd v F G Minter Ltd and Trollope and Colls Ltd. |
Macob Civil Engineering Ltd v Morrison Construction Ltd | N/A | Yes | [1999] CLC 739 | United Kingdom | Cited for the principle that decisions of adjudicators are binding and are to be complied with until the dispute is finally resolved. |
Chip Hup Hup Kee Construction Pte Ltd v Ssangyong Engineering & Construction Co Ltd | High Court | Yes | [2008] SGHC 159 | Singapore | Cited for the interpretation of section 15(3) of the Building and Construction Industry Security of Payment Act. |
Chip Hup Hup Kee Construction Pte Ltd v Ssangyong Engineering & Construction Co Ltd | High Court | Yes | [2010] 1 SLR 658 | Singapore | Cited for approving the reasoning in Chip Hup Hup Kee Construction Pte Ltd v Ssangyong Engineering & Construction Co Ltd [2008] SGHC 159. |
Sungdo Engineering & Construction (S) Pte Ltd v Italcor Pte Ltd | High Court | Yes | [2010] 3 SLR 459 | Singapore | Cited for the interpretation of section 15(3) of the Building and Construction Industry Security of Payment Act. |
Australian Timber Products Pte Ltd v A Pacific Construction & Development Pte Ltd | High Court | Yes | [2013] SGHC 56 | Singapore | Cited for the interpretation of section 11(3)(c) of the Building and Construction Industry Security of Payment Act. |
Multiplex Constructions Pty Limited v Jan Luikens and Lahey Detailed Joinery Pty Ltd | New South Wales Supreme Court | Yes | [2003] NSWSC 1140 | Australia | Cited for the interpretation of section 20(2B) of New South Wales’ Building and Construction Industry Security of Payment Act 1999. |
Brodyn Pty Limited t/as Time Cost and Quality v Philip Davenport and Dasein Constructions Pty Limited | New South Wales Court of Appeal | Yes | [2004] NSWCA 394 | Australia | Cited for the principle that natural justice is to be afforded to the extent contemplated by the provisions of the legislation. |
Pacific General Securities Ltd & Anor v Soliman & Sons Pty Ltd & Ors | New South Wales Supreme Court | Yes | [2006] NSWSC 13 | Australia | Cited for the principle that an adjudicator must come to a view as to what is properly payable. |
Grosvenor Constructions (NSW) Pty Limited (in administration) v Joseph Musico, Rosemary Musico, Luigi Genua and Rose Genua | New South Wales Supreme Court | Yes | [2004] NSWSC 344 | Australia | Cited for the principle that a stay should be granted where there is a certainty that the unsuccessful respondent’s rights will be otherwise rendered nugatory. |
Bouygues UK Ltd v Dahl-Jensen UK Ltd | N/A | Yes | [2001] CLC 927 | United Kingdom | Cited for the principle that a stay of enforcement may be granted where the successful claimant is in insolvent liquidation. |
Rainford House Limited v Cadogan Limited | N/A | Yes | [2001] BLR 416 | United Kingdom | Cited for the principle that a stay of enforcement may be granted where the successful claimant is in administrative receivership. |
Wimbledon Construction Company 2000 Limited v Derek Vago | N/A | Yes | [2005] BLR 374 | United Kingdom | Cited for the principle that evidence of financial difficulties which fall short of actual, objective insolvency will not usually suffice for a stay of enforcement. |
13. Applicable Rules
Rule Name |
---|
Rules of Court (Cap 322, R 5, 2006 Rev Ed) O 95 r 3(3) |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) | Singapore |
Interpretation Act (Cap 1, 2002 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Adjudication Determination
- Payment Claim
- Payment Response
- Adjudication Response
- Security of Payment Act
- Temporary Finality
- Stay of Enforcement
15.2 Keywords
- construction
- adjudication
- security of payment
- payment claim
- payment response
- stay of enforcement
17. Areas of Law
16. Subjects
- Construction Dispute
- Adjudication
- Security of Payment