Sun Qi v Syscon: Sale of Goods Act & Defective Cranes Legal Issue

In Sun Qi (formerly trading as Power King International) and another v Syscon Pte Ltd, the High Court of Singapore addressed a dispute arising from two agreements for the sale and installation of overhead travelling cranes. Syscon Pte Ltd counterclaimed for rescission of the agreements, alleging breach of the implied condition of satisfactory quality. The court, presided over by Quentin Loh J, found in favor of Syscon, allowing the counterclaim for rescission and ordering the return of $100,800.00 paid to Power King, with Power King obliged to dismantle and remove the cranes from Syscon's factory site.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Judgment for Defendant

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

High Court case regarding breach of contract and rescission for defective cranes. Syscon successfully counterclaimed for rescission due to the cranes' unsatisfactory quality.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Sun Qi (formerly trading as Power King International)PlaintiffIndividualClaim DismissedLost
Wong Mai Jun, EugenePlaintiffIndividualClaim DismissedLost
Syscon Pte LtdDefendantCorporationCounterclaim AllowedWon

3. Judges

Judge NameTitleDelivered Judgment
Quentin LohJudgeYes

4. Counsels

4. Facts

  1. Plaintiffs and defendant entered into two agreements for the sale and installation of overhead travelling cranes.
  2. The defendant alleged the cranes were defective and not of satisfactory quality.
  3. The defendant sought rescission of the agreements and return of payments made.
  4. The plaintiffs claimed the defendant had lost the right of rejection due to the time elapsed.
  5. The court found the cranes were defective due to electrical and mechanical issues.
  6. The court found the defendant had not lost its right of rejection.
  7. The court dismissed the plaintiffs' claim and allowed the defendant's counterclaim for rescission.

5. Formal Citations

  1. Sun Qi (formerly trading as Power King International) and another v Syscon Pte Ltd, Suit No 775 of 2009, [2013] SGHC 38

6. Timeline

DateEvent
Quote given for one 30-ton overhead travelling crane.
Trial order placed for one 30-ton overhead travelling crane.
Load-test for the first crane conducted; MOM certificate issued.
First crane fully delivered, installed, and commissioned.
First agreement made for three 30-ton overhead travelling cranes.
Second agreement made for two 20-ton overhead travelling cranes.
First crane breakdown.
One 30-ton crane delivered and installed.
One 30-ton crane delivered and installed.
MOM certificates issued for two 30-ton cranes.
One 30-ton crane delivered and installed.
MOM certificate issued for one 30-ton crane.
Syscon paid Power King $50,000.00.
Problems with the cranes allegedly began.
Syscon sent a service request to Power King.
Mr. Wong wrote a letter regarding complaints about the cranes.
Breakdown of crane at Line 9.
Syscon sent a service request to Power King.
Meeting held at Syscon's premises to discuss crane problems.
Minutes of meeting faxed out.
Syscon sent a service request to Power King.
Breakage of hook-pulley and steel wire at Line 9.
Syscon sent a service request to Power King.
Breakdown of crane hoist at Line 11.
Syscon sent a service request to Power King.
Mr. Wong reminded Syscon to conduct commissioning and load-test.
Ms. Ang requested structural crane detail drawings.
Syscon sent a service request to Power King.
Long and cross travel brake coil jammed at Line 9.
Syscon sent a service request to Power King.
Power King sent a formal letter of demand to Syscon.
Syscon instructed Christopher Bridges Law Practice.
Breakdown of long travel system at Line 8.
Long travel motors-cum-gear box out of order at Lines 8, 10, 11.
Genesis Law wrote to Christopher Bridges asking whether the latter was authorised to accept service of process on behalf of Syscon.
Syscon gave notice to Power King that it was rejecting all the cranes.
Khor Thiam Beng & Partners requested a joint inspection.
Joint inspection carried out.
Suit filed.
Hearing.
Hearing.
Hearing.
Plaintiffs’ Closing Reply Submissions.
Defendant’s closing submissions.
Judgment reserved.

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that the plaintiffs were in breach of contract due to the defective cranes.
    • Category: Substantive
    • Sub-Issues:
      • Breach of implied condition of satisfactory quality
      • Breach of warranty of fitness for purpose
  2. Right of Rejection
    • Outcome: The court found that the defendant had not lost its right of rejection.
    • Category: Substantive
    • Sub-Issues:
      • Loss of right of rejection due to lapse of reasonable time
      • Intimation of rejection
  3. Rescission
    • Outcome: The court allowed the defendant's counterclaim for rescission.
    • Category: Substantive
  4. Misrepresentation
    • Outcome: The court found that the defendant's claim of misrepresentation failed.
    • Category: Substantive

8. Remedies Sought

  1. Outstanding payment for cranes
  2. Commissioning costs
  3. Rescission of agreements
  4. Return of payments made
  5. Damages for misrepresentation
  6. Damages for breach of contract

9. Cause of Actions

  • Breach of Contract
  • Breach of implied condition of satisfactory quality
  • Misrepresentation

10. Practice Areas

  • Commercial Litigation

11. Industries

  • Construction
  • Manufacturing

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Eastern Supply Co v KerrCourt of AppealYes[1973] SGCA 7SingaporeCited to establish that a buyer loses the right to reject goods for breach of conditions once they are deemed to have accepted the goods, but can still claim for damages.
Compact Metal Industries Ltd v PPG Industries (Singapore) LtdHigh CourtYes[2006] SGHC 242SingaporeCited for the principle that a reasonable time for rejection depends on the type of product and discoverability of the defect, and that conducting trials to resolve issues does not prejudice rejection rights.
Super Continental Pte Ltd v Essential Engineering & Construction Pte LtdHigh CourtYes[2010] SGHC 365SingaporeCited for the principle that repeated complaints and attempts to rectify defects are part of a reasonable opportunity to examine goods and do not necessarily indicate acceptance.
Bisset v WilkinsonPrivy CouncilYes[1927] AC 177United KingdomCited for the principle that a misrepresentation must be an unambiguous statement of existing fact or law, and that vague statements of opinion do not constitute misrepresentations.
Bestland Development Pte Ltd v Thasin Development Pte LtdHigh CourtYes[1991] SGHC 27SingaporeCited for affirming the principle that a misrepresentation must be an unambiguous statement of existing fact or law, and that vague statements of opinion do not constitute misrepresentations.

13. Applicable Rules

Rule Name
Rules of Court (Cap 322, R 5, 2006 Rev Ed) O 40A r 2(1)

14. Applicable Statutes

Statute NameJurisdiction
Sale of Goods Act (Cap 393, 1999 Rev Ed)Singapore
Sale of Goods Act (Cap 393, 1999 Rev Ed) s 14(2)Singapore
Sale of Goods Act (Cap 393, 1999 Rev Ed) s 35(4)Singapore
Sale of Goods Act (Cap 393, 1999 Rev Ed) s 35(6)Singapore
Misrepresentation Act (Cap 390, 1994 Rev Ed)Singapore
Misrepresentation Act (Cap 390, 1994 Rev Ed) s 2Singapore
Misrepresentation Act (Cap 390, 1994 Rev Ed) s 2(2)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Overhead travelling cranes
  • Satisfactory quality
  • Right of rejection
  • Rescission
  • Misrepresentation
  • Warranty
  • Defective goods
  • Reasonable time
  • Intimation of rejection
  • Rectification

15.2 Keywords

  • cranes
  • defective
  • sale of goods
  • rescission
  • rejection
  • contract
  • warranty
  • misrepresentation

17. Areas of Law

16. Subjects

  • Sale of Goods
  • Breach of Contract
  • Commercial Dispute
  • Construction Law