Eng Seng Precast v SLF Construction: SOP Act & Construction vs. Supply Contracts

In Eng Seng Precast Pte Ltd v SLF Construction Pte Ltd, the High Court of Singapore addressed whether a contract for the supply of prefabricated components manufactured offsite falls under the definition of a 'construction contract' or a 'supply contract' under the Building and Construction Industry Security of Payment Act (SOP Act). The court allowed the defendant's application to set aside an adjudication determination, holding that the contract was a construction contract, not a supply contract, due to the offsite prefabrication work, and the adjudication application was filed out of time.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Defendant's application allowed; the adjudication determination and order are set aside.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

The case clarifies whether a contract for prefabricated components with offsite manufacture falls under 'construction' or 'supply' contract under the SOP Act.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Eng Seng Precast Pte LtdPlaintiffCorporationApplication DismissedLostLim Ker Sheon, Ang Minghao
SLF Construction Pte LtdDefendantCorporationApplication AllowedWonLoy Wee Sun

3. Judges

Judge NameTitleDelivered Judgment
Lee Seiu KinJudgeYes

4. Counsels

Counsel NameOrganization
Lim Ker SheonCharacterist LLC
Ang MinghaoCharacterist LLC
Loy Wee SunLoy & Co

4. Facts

  1. The defendant awarded a sub-contract to the plaintiff for the supply and delivery of precast concrete components.
  2. The contract involved offsite manufacture of prefabricated components.
  3. The plaintiff served a payment claim on the defendant.
  4. The defendant filed a payment response.
  5. The plaintiff lodged an adjudication application.
  6. The adjudicator determined that the defendant was liable for a sum of money.
  7. The defendant applied to set aside the determination, arguing the application was out of time.

5. Formal Citations

  1. Eng Seng Precast Pte Ltd v SLF Construction Pte Ltd, Originating Summons No 410 of 2015 (Summons No 2618 of 2015), [2015] SGHC 252

6. Timeline

DateEvent
Sub-contract awarded to the plaintiff for supply and delivery of precast concrete components.
Plaintiff served a payment claim on the defendant for $747,229.13.
Defendant filed a payment response.
Plaintiff lodged the Adjudication Application.
Adjudication determination was dated.
Plaintiff obtained a court order to enforce the adjudication determination.
Defendant's application to set aside the determination was allowed.
Decision Date

7. Legal Issues

  1. Classification of Contract: Construction vs. Supply Contract under SOP Act
    • Outcome: The court held that a contract for the supply and offsite manufacture of prefabricated components is a construction contract, not a supply contract.
    • Category: Substantive
  2. Validity of Adjudication Determination
    • Outcome: The court held that the adjudication determination was invalid because the adjudication application was not made within the stipulated time.
    • Category: Procedural
    • Related Cases:
      • [2013] 1 SLR 401
      • [2014] SGHC 142

8. Remedies Sought

  1. Setting aside of Adjudication Determination
  2. Setting aside of Court Order

9. Cause of Actions

  • Enforcement of Adjudication Determination

10. Practice Areas

  • Construction Disputes
  • Commercial Litigation
  • Arbitration

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appealHigh CourtYes[2013] 1 SLR 401SingaporeCited for the test of whether a breached provision is so important that an act done in breach of the provision should be invalid.
YTL Construction (S) Pte Ltd v Balanced Engineering & Construction Pte LtdHigh CourtYes[2014] SGHC 142SingaporeCited for setting aside an adjudication application made out of time.
Anthony Hordern and Sons Limited and others v The Amalgamated Clothing and Allied Trades Union of AustraliaHigh Court of AustraliaYesAnthony Hordern and Sons Limited and others v The Amalgamated Clothing and Allied Trades Union of Australia (1932) 47 CLR 1AustraliaCited regarding the interpretation of 'prescribed' and the validity of an order by the Commonwealth Court of Conciliation and Arbitration.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore
s 2 of the Building and Construction Industry Security of Payment ActSingapore
s 3(1) of the Building and Construction Industry Security of Payment ActSingapore
s 13(3)(a) of the Building and Construction Industry Security of Payment ActSingapore
s 16(2)(a) of the Building and Construction Industry Security of Payment ActSingapore
Interpretation Act (Cap 1, 2002 Rev Ed)Singapore
Section 2(1) of the Interpretation Act (Cap 1, 2002 Rev Ed)Singapore
Building and Construction Industry Security of Payment Act 1999 (Act 46 of 1999) (NSW)New South Wales

15. Key Terms and Keywords

15.1 Key Terms

  • Construction contract
  • Supply contract
  • Prefabricated components
  • Adjudication determination
  • Security of Payment Act
  • Payment claim
  • Payment response
  • Offsite manufacture
  • Construction work

15.2 Keywords

  • Construction contract
  • Supply contract
  • Security of Payment Act
  • Prefabrication
  • Adjudication
  • Singapore

16. Subjects

  • Construction Law
  • Contract Law
  • Security of Payment
  • Adjudication

17. Areas of Law

  • Construction Law
  • Building and Construction Industry Security of Payment Act
  • Contract Law
  • Arbitration Law