AQU v AQV: Application to Set Aside Arbitration Award for Breach of Natural Justice
In AQU v AQV, the High Court of Singapore heard an application by AQU to set aside an arbitration award rendered in favor of AQV. AQU alleged breaches of natural justice by the arbitrator. The court, per Judith Prakash J, dismissed the application, finding no breaches of natural justice in the arbitrator's decision-making process. The underlying dispute concerned payments for stone finishings supplied by AQV to AQU under two sub-contracts.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Application dismissed with costs.
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
AQU applied to set aside an arbitration award, alleging breaches of natural justice. The court dismissed the application, finding no such breaches.
1.7 Decision Date
2. Parties and Outcomes
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Judith Prakash | Judge | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Kelvin Chia | Samuel Seow Law Corporation |
Ng Yuen | Malkin & Maxwell LLP |
4. Facts
- The plaintiff applied to set aside an arbitration award.
- The plaintiff alleged breaches of natural justice by the arbitrator.
- The underlying dispute concerned payments for stone finishings supplied under two sub-contracts.
- The arbitrator found in favor of the Supplier in respect of its claims and dismissed the counterclaim of the Contractor.
- The Contractor claimed the Arbitrator reached a conclusion not argued by either party.
- The Contractor claimed the Arbitrator failed to consider an argument raised by the plaintiff.
- The Contractor claimed the Arbitrator made a finding of fact in the absence of any logically probative evidence to support the same.
5. Formal Citations
- AQU v AQV, Originating Summons No 133 of 2014, [2015] SGHC 26
6. Timeline
Date | Event |
---|---|
Contract awarded to the Supplier for the supply and delivery of stone finishing. | |
Contract novated, substituting the Contractor for Times Development Pte Ltd. | |
Contractor sent the Supplier a Letter of Acceptance – Subcontract Standard Clauses (Supply Only). | |
Supplier sent a letter stating it was not responsible for taking site measurements. | |
Supplier sent a letter stating it was entitled to payment based on quantities supplied. | |
Parties met to discuss matters raised by the Supplier's letters. | |
Supplier sent a letter to the Contractor referencing prior letters and the meeting. | |
Supplier signed the Letter of Acceptance with a handwritten clause. | |
Contractor engaged the Supplier to supply and deliver tiles and stone finishings to common areas. | |
Supplier sent the Contractor a Notice of Arbitration. | |
Parties agreed to the appointment of the Arbitrator. | |
Tribunal was constituted. | |
Arbitrator heard evidence. | |
Parties filed written submissions and reply submissions. | |
Award was delivered. | |
Contractor filed application to set aside the Award. | |
Decision Date |
7. Legal Issues
- Breach of Natural Justice
- Outcome: The court found no breach of natural justice.
- Category: Procedural
- Sub-Issues:
- Failure to consider argument
- Finding of fact without evidence
- Conclusion not argued by either party
8. Remedies Sought
- Setting aside of arbitration award
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Arbitration
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte Ltd | Court of Appeal | Yes | [2007] 3 SLR(R) 86 | Singapore | Cited for the principle that there may be a breach of natural justice if an arbitrator decides a case on a point he has invented for himself. |
TMM Division Maritima SA de CV v Pacific Richfield Marine Pte Ltd | High Court | Yes | [2013] 4 SLR 972 | Singapore | Cited for the principle that arbitrators are not restricted to adopting only the premises put forward by the parties in their conclusions. |
Pacific Recreation Pte Ltd v S Y Technology Inc and Another Appeal | Court of Appeal | Yes | [2008] 2 SLR(R) 491 | Singapore | Cited for the principle that courts can make reasonable inferences of fact and findings that lie between the extreme positions taken by parties. |
BLC v BLB | Court of Appeal | Yes | [2014] 4 SLR 79 | Singapore | Cited for the principle that an award should be read in a reasonable and commercial way, not with a meticulous legal eye to find faults. |
Front Row Investment Holdings (Singapore) Pte Ltd v Daimler South East Asia Pte Ltd | High Court | Yes | [2010] SGHC 80 | Singapore | Cited for the principle that it is a breach of natural justice for an arbitrator to disregard submissions and arguments made by parties without considering the merits thereof. |
Castel Electronics Pty Ltd v TCL Air Conditioner (Zhongshan) Co Ltd (No 2) | Federal Court of Australia | No | [2012] FCA 1214 | Australia | Cited in relation to the 'no evidence' rule as a potential basis for setting aside an arbitral award for breach of natural justice. |
Downer-Hill Joint Venture v Government of Fiji | High Court | No | [2005] 1 NZLR 554 | New Zealand | Cited in relation to the 'no evidence' rule as a potential basis for setting aside an arbitral award for breach of natural justice. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Arbitration Act (Cap 10, 2002 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Arbitration Award
- Natural Justice
- Nominated Sub-Contract
- Domestic Sub-contract
- As-built quantities
- Delivered quantities
- Letter of Acceptance
- Shop Drawings
- Variation Order
15.2 Keywords
- Arbitration
- Natural Justice
- Singapore
- Construction
- Contract
17. Areas of Law
Area Name | Relevance Score |
---|---|
Arbitration | 90 |
Contract Law | 75 |
Construction Law | 60 |
Natural justice | 50 |
16. Subjects
- Arbitration
- Contract Law
- Civil Procedure