Sintalow Hardware v OSK Engineering: Contract Formation & Misrepresentation Dispute
In a suit before the High Court of Singapore, Sintalow Hardware Pte Ltd, the Plaintiff, sued OSK Engineering Pte Ltd, the Defendant, for breach of contract and misrepresentation related to the supply of plumbing materials for a hotel construction project. Sintalow claimed OSK failed to purchase agreed quantities and misrepresented its purchase intentions to secure discounts. OSK denied the claims, asserting a different contractual agreement. The court, presided over by Judith Prakash J, found for the Plaintiff in part, ordering damages to be assessed for specific claims while dismissing the broader claims of breach of contract and misrepresentation.
1. Case Overview
1.1 Court
High Court of the Republic of Singapore1.2 Outcome
Judgment for the plaintiff for damages to be assessed in respect of those claims in which it succeeded.
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
Singapore court case between Sintalow Hardware and OSK Engineering over contract formation and alleged misrepresentation in a plumbing supply agreement. Judgment for Plaintiff in part.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Sintalow Hardware Pte Ltd | Plaintiff | Corporation | Judgment for Plaintiff in part | Partial | |
OSK Engineering Pte Ltd | Defendant | Corporation | Judgment against Defendant in part | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Judith Prakash | Judge | Yes |
4. Counsels
4. Facts
- Sintalow Hardware sued OSK Engineering for breach of contract and misrepresentation.
- The dispute concerned the supply of plumbing materials for a hotel construction project.
- Sintalow claimed OSK failed to purchase agreed quantities and misrepresented purchase intentions.
- OSK denied the claims, asserting a different contractual agreement (Master Contract).
- The court found that the general contractual terms were contained in the Master Contract rather than in the Total Package Agreement.
- The court found that the defendant did not make any representations as to the Estimated Sales Amount or that it would purchase this quantity of products from the plaintiff.
- The court found that the defendant would be unjustly enriched if it was allowed to take advantage of the plaintiff’s mistake in failing to bill it for the CV Couplings.
5. Formal Citations
- Sintalow Hardware Pte Ltd v OSK Engineering Pte Ltd, Suit No 662 of 2012, [2016] SGHC 104
6. Timeline
Date | Event |
---|---|
Sintalow Hardware Pte Ltd incorporated | |
OSK Engineering informed Sintalow Hardware it was tendering for plumbing works at Marina Sands Integrated Resort Project | |
Sintalow Hardware sent OSK Engineering its May 2007 price list | |
OSK Engineering appointed as subcontractor for plumbing works for the Project | |
Meeting between Mr. Chew, Mr. Tan, and Mdm. Oh to discuss product supply for the Project | |
Sintalow Hardware sent OSK Engineering a letter confirming special discount rates | |
Further meetings took place in October 2007 | |
Further meetings took place in November 2007 | |
OSK Engineering sent Sintalow Hardware a letter outlining the terms and conditions of the contract | |
Sintalow Hardware sent OSK Engineering a letter to correct the agreed terms | |
Sintalow Hardware gave OSK Engineering a quotation for the supply of Fusiotherm PPR Pipes and Fittings | |
OSK Engineering signed and returned the Fusiotherm quotation with amendments | |
Sintalow Hardware sent OSK Engineering its second quotation for Duker Hubless Pipes and Fittings | |
OSK Engineering signed and returned the Duker Hubless Pipes and Fittings quotation | |
Sintalow Hardware asked OSK Engineering to send a letter of approval from the consultant for Fusiotherm products | |
OSK Engineering replied attaching several Schedules of the materials required for the Project | |
Sintalow Hardware sent a letter to OSK Engineering setting out the situation at the time | |
OSK Engineering sent Sintalow Hardware a letter enclosing a revised Schedule for the Fusiotherm products | |
OSK Engineering furnished Sintalow Hardware with a delivery schedule for Duker products | |
Sintalow Hardware wrote to OSK Engineering to set out the differences in the quantities and types of Duker products ordered | |
Sintalow Hardware sent OSK Engineering a quotation setting out the prices and quantities of the new items and additional items alongside those that had been ordered previously | |
Meeting to discuss the quotation, Mdm Oh informed Mr Chew that OSK Engineering wanted to proceed with its orders for the new and additional items | |
OSK Engineering sent Sintalow Hardware further letters setting out Schedules with changes to the quantities of the Fusiotherm products that would be required for delivery | |
OSK Engineering confirmed that both parties had agreed that Sintalow Hardware would go ahead first with the order of pipes and fittings | |
Sintalow Hardware sent a letter accepting the variations and quantities set out in the defendant’s March 2008 Schedule | |
OSK Engineering asked Sintalow Hardware whether it could supply certain Rubber Collars that were not standard but had to be specially manufactured | |
Sintalow Hardware quoted the unit price of the Rubber Collars | |
OSK Engineering sent in a revised quantity and asked Sintalow Hardware to re-quote | |
OSK Engineering confirmed the order of the rubber sealing with 5mm thickness | |
OSK Engineering confirmed the order of Hubless Cross Tees | |
OSK Engineering wrote seeking to vary the quantity of Cross Tees from 1,000 to 1,660 units | |
OSK Engineering slightly increased the quantities of Rubber Collars ordered | |
OSK Engineering requested Sintalow Hardware to put the order for Cross Tees on hold until further notice | |
Sintalow Hardware told OSK Engineering that no cancellation was allowed | |
Sintalow Hardware sent OSK Engineering a letter enclosing a summary of the Duker Hubless products allegedly ordered by OSK Engineering reiterating that the orders could not be cancelled | |
Sintalow Hardware placed an order for 1000 pieces of Cross Tees with its own suppliers | |
OSK Engineering notified Sintalow Hardware that the consultants for the Project refused to approve the Fusiotherm products | |
OSK Engineering sent a letter to Sintalow Hardware following a meeting held by the parties to discuss the issue of the prices for the Duker Hubless products | |
Suit commenced | |
Hearing in August 2015 | |
Judgment reserved |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that the general contractual terms were contained in the Master Contract rather than in the Total Package Agreement and the plaintiff and the defendant did not conclude the three Product Agreements.
- Category: Substantive
- Sub-Issues:
- Failure to deliver goods
- Repudiation of contract
- Misrepresentation
- Outcome: The court found that the defendant did not make any representations as to the Estimated Sales Amount or that it would purchase this quantity of products from the plaintiff.
- Category: Substantive
- Unjust Enrichment
- Outcome: The court found that the defendant would be unjustly enriched if it was allowed to take advantage of the plaintiff’s mistake in failing to bill it for the CV Couplings.
- Category: Substantive
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
- Misrepresentation
- Unjust Enrichment
10. Practice Areas
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Projection Pte Ltd v The Tai Ping Insurance Co Ltd | N/A | Yes | [2001] 1 SLR(R) 798 | Singapore | Cited to support the approach of considering the conduct of parties over the period of negotiations. |
Norwest Holdings Pte Ltd (in liquidation) v Newport Mining Ltd and another appeal | Court of Appeal | Yes | [2011] 4 SLR 617 | Singapore | Cited to support the approach of considering all circumstances, including words and conduct, to determine if a binding contract existed. |
OCBC Capital Investment Asia Ltd v Wong Hua Choon | Court of Appeal | Yes | [2012] 4 SLR 1206 | Singapore | Cited to support the approach of examining documentary evidence first in determining whether a contract existed. |
Hock Chuan Ann Construction Pte Ltd v Kimta Electric Pte Ltd | N/A | Yes | [1999] 2 SLR(R) 237 | Singapore | Cited for the principle that a bill of quantities is not a warranty of its contents. |
Koh Sin Chong Freddie v Singapore Swimming Club | N/A | Yes | [2015] 1 SLR 1240 | Singapore | Cited for the elements of unjust enrichment. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Total Package Agreement
- Master Contract
- Product Agreements
- Estimated Sales Amount
- Material Order Forms
- Approval Clause
- Estimated Quantities Clause
- Fixed Price Clause
- 10% Variation Term
- First Schedule
15.2 Keywords
- contract
- breach
- misrepresentation
- plumbing
- hardware
- Singapore
- construction
17. Areas of Law
Area Name | Relevance Score |
---|---|
Contract Law | 95 |
Breach of Contract | 90 |
Formation of contract | 80 |
Misrepresentation | 70 |
16. Subjects
- Contract Law
- Commercial Dispute