CAA Technologies v Newcon Builders: Sub-Contract Breach & Delay in Construction Project
In [2016] SGHC 246, CAA Technologies Pte Ltd sued Newcon Builders Pte Ltd in the High Court of Singapore, alleging wrongful termination of their sub-contract for the design, production, and delivery of pre-cast concrete hollow core slabs for a medical technology hub project in Jurong. Newcon Builders counterclaimed for damages resulting from CAA Technologies' failure to deliver the slabs as promised, causing delays to the project. Justice Vinodh Coomaraswamy disallowed substantially the whole of CAA's claim and allowed substantially the whole of Newcon's counterclaim, finding that CAA breached both express and implied terms of the contract. CAA has appealed the decision.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Judgment for Defendant in Counterclaim
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
CAA Technologies sues Newcon Builders for wrongful contract termination. Newcon counterclaims for breach due to CAA's delayed slab delivery. Court largely disallows CAA's claim.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
CAA Technologies Pte Ltd | Plaintiff, Defendant in Counterclaim | Corporation | Claim Dismissed | Lost | |
Newcon Builders Pte Ltd | Defendant, Plaintiff in Counterclaim | Corporation | Counterclaim Allowed | Won |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Vinodh Coomaraswamy | Judge | Yes |
4. Counsels
4. Facts
- Newcon was the main contractor for a building project in Jurong.
- Newcon sub-contracted the design, production, and delivery of structural elements to CAA.
- CAA failed to deliver the elements as promised, causing delays.
- Newcon revised the delivery schedule to accommodate CAA’s initial failure.
- CAA failed to meet even the revised schedule.
- Newcon terminated the contract with CAA and engaged a substitute contractor.
- CAA treated Newcon’s termination as a breach of contract.
5. Formal Citations
- CAA Technologies Pte Ltd v Newcon Builders Pte Ltd, Suit No 1063 of 2013, [2016] SGHC 246
6. Timeline
Date | Event |
---|---|
Letter of intent signed between Newcon Builders and CAA Technologies. | |
Overall main contract period began. | |
CAA Technologies countersigned and returned the acknowledgement for the letter of intent. | |
Letter of acceptance sent from Newcon to CAA. | |
CAA received the letter of acceptance. | |
Superstructure works scheduled to start. | |
Newcon requested CAA to submit various items before commencing production of slabs. | |
Newcon emailed CAA again, repeating the contents of its earlier email. | |
Newcon expressed its hope that CAA would sign and return the letter of acceptance by email. | |
Newcon noted that CAA had not replied regarding the letter of acceptance, and asked CAA to sign and return it by 25 February 2013. | |
CAA carried out its first casting. | |
Newcon sent CAA a revised schedule for CAA’s initial delivery of slabs. | |
Revised delivery date for area 2a. | |
Revised delivery date for area 2b; Newcon emailed CAA recording CAA’s failure to deliver any slabs thus far. | |
Newcon instructed CAA to deliver the first slabs. | |
Newcon sent another reminder to CAA. | |
CAA delivered its first batch of slabs. | |
CAA delivered another batch of slabs. | |
CAA delivered slabs which matched the specifications for area 2a. | |
Meeting between Dr. Chi (CAA), Mr. Cao and Mr. Lin (Newcon). | |
Newcon emailed CAA a “Proposed Delivery Schedule for Hollow Core Slab – Medtech Hub project”. | |
Meeting between Newcon and CAA. | |
Newcon sent CAA an email titled “Letter 027 – Notice of Delay – Slow Progress in Supply of Hollow Core Slab”. | |
CAA did not respond to Newcon; Newcon sent to CAA formal written notice of termination. | |
CAA sent two letters in reply to Newcon; Newcon responded to CAA’s photographs. | |
CAA sent Newcon a letter before action. | |
Newcon replied to CAA, rejecting the allegation that it had terminated the parties’ contract without legal basis. | |
Newcon wrote to CAA quantifying its loss and damage at $1,554,259.93. | |
CAA commenced this action against Newcon. | |
Statement of claim (Amendment No. 1) dated. | |
CAA collected the I-beams. | |
AEIC of Chi Chao-Ton Tony dated. | |
Interim final payment certificate issued under the main contract. | |
AEIC of Chen Linhui dated. | |
AEIC of Cao Wei Min dated; AEIC of Lin Haifeng dated. | |
Trial began. | |
Trial. | |
Defendant’s closing submissions dated; Plaintiff’s closing submissions dated. | |
Hearing. | |
Judgment Date. |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that CAA breached both express and implied terms of the contract, constituting a repudiatory breach.
- Category: Substantive
- Sub-Issues:
- Failure to deliver slabs on time
- Failure to follow site progress
- Failure to proceed with due diligence and expedition
- Wrongful Termination
- Outcome: The court held that Newcon was justified in terminating the contract due to CAA's repudiatory breach.
- Category: Substantive
- Implied Terms
- Outcome: The court found that the contract contained implied terms requiring CAA to proceed with due diligence and expedition, and making time of the essence in relation to that obligation.
- Category: Substantive
- Sub-Issues:
- Due diligence and expedition
- Time is of the essence
- Acceptance of Contract Terms
- Outcome: The court held that CAA's silence and conduct were not sufficient to constitute acceptance of the letter of acceptance.
- Category: Substantive
- Sub-Issues:
- Silence as acceptance
- Objective intention
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Re Selectmove Ltd | N/A | Yes | [1995] 1 WLR 474 | N/A | Cited for the principle that silence in response to an offer does not constitute acceptance. |
Midlink Development Pte Ltd v The Stansfield Group Pte Ltd | N/A | Yes | [2004] 4 SLR(R) 258 | Singapore | Cited for the principle that it is a question of fact whether the offeree’s response was complete silence and, even if so, whether the effect of the silence, objectively ascertained against the factual background, supports the existence of a contract. |
Ng Giap Hon v Westcomb Securities Pte Ltd and others | Court of Appeal | Yes | [2009] 3 SLR(R) 518 | Singapore | Cited for the principles on which terms will be implied in fact into a contract. |
Chua Choon Cheng and others v Allgreen Properties Ltd and another appeal | Court of Appeal | Yes | [2009] 3 SLR(R) 724 | Singapore | Cited for the principles governing implied terms in law. |
Jurong Engineering Ltd v Paccan Building Technology Pte Ltd | Court of Appeal | Yes | [1999] 2 SLR(R) 849 | Singapore | Cited regarding implied terms in law in construction contracts. |
Sembcorp Marine Ltd v PPL Holdings Pte Ltd and another and another appeal | N/A | Yes | [2013] 4 SLR 193 | Singapore | Cited for the three-step process for ascertaining whether a contract contains a particular implied term in fact. |
The Moorcock | N/A | Yes | (1889) 14 PD 64 | N/A | Cited for the business efficacy test for implying a term in fact into a contract. |
Shirlaw v Southern Foundries (1926) Limited | N/A | Yes | [1939] 2 KB 206 | N/A | Cited for the officious bystander test for implying a term in fact into a contract. |
Felthouse v Bindley | N/A | Yes | (1862) 142 ER 1037 | N/A | Cited for the contractual rule that silence in response to an offer does not constitute acceptance of that offer because it is equivocal. |
Greater London Council v Cleveland Bridge & Engineering Company Ltd | N/A | Yes | (1984) 34 BLR 50 | N/A | Considered the status of an implied term obliging a contractor to proceed with due diligence and expedition. |
Leander Construction Limited v Mulalley and Company Limited | N/A | Yes | [2011] EWHC 3449 (TCC) | N/A | Considered the status of an implied term obliging a contractor to proceed with due diligence and expedition. |
Man Financial (S) Pte Ltd (formerly known as E D & F Man International (S) Pte Ltd) v Wong Bark Chuan David | N/A | Yes | [2008] 1 SLR(R) 663 | Singapore | Cited for the principle that whether a term is a condition is to be determined by ascertaining the objective intentions of the parties on the contract’s proper construction in light of all the surrounding circumstances. |
Chua Tian Chu and another v Chin Bay Ching and another | High Court | Yes | [2011] SGHC 126 | Singapore | Cited regarding the consequence of acts of prevention. |
ACES System Development Pte Ltd v Yenty Lily (trading as Access International Services) | N/A | Yes | [2013] 4 SLR 1317 | Singapore | Cited regarding a claim for damages in tort for wrongful detention of property. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Pre-cast concrete hollow core slabs
- Letter of intent
- Letter of acceptance
- Construction schedule
- Superstructure works
- Notice of delay
- Notice of termination
- Due diligence
- Expedition
- Repudiatory breach
15.2 Keywords
- Construction
- Contract
- Breach
- Delay
- Sub-contract
- Slabs
- Termination
17. Areas of Law
Area Name | Relevance Score |
---|---|
Construction Law | 95 |
Building and Construction Contracts | 90 |
Sub-contracts | 85 |
Breach of Contract | 80 |
Contract Law | 75 |
Compensation for delays | 70 |
Implied Terms | 65 |
Damages | 50 |
16. Subjects
- Construction Dispute
- Contract Law
- Sub-Contract
- Breach of Contract