CAA Technologies v Newcon Builders: Sub-Contract Breach & Delay in Construction Project

In [2016] SGHC 246, CAA Technologies Pte Ltd sued Newcon Builders Pte Ltd in the High Court of Singapore, alleging wrongful termination of their sub-contract for the design, production, and delivery of pre-cast concrete hollow core slabs for a medical technology hub project in Jurong. Newcon Builders counterclaimed for damages resulting from CAA Technologies' failure to deliver the slabs as promised, causing delays to the project. Justice Vinodh Coomaraswamy disallowed substantially the whole of CAA's claim and allowed substantially the whole of Newcon's counterclaim, finding that CAA breached both express and implied terms of the contract. CAA has appealed the decision.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Judgment for Defendant in Counterclaim

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

CAA Technologies sues Newcon Builders for wrongful contract termination. Newcon counterclaims for breach due to CAA's delayed slab delivery. Court largely disallows CAA's claim.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
CAA Technologies Pte LtdPlaintiff, Defendant in CounterclaimCorporationClaim DismissedLost
Newcon Builders Pte LtdDefendant, Plaintiff in CounterclaimCorporationCounterclaim AllowedWon

3. Judges

Judge NameTitleDelivered Judgment
Vinodh CoomaraswamyJudgeYes

4. Counsels

4. Facts

  1. Newcon was the main contractor for a building project in Jurong.
  2. Newcon sub-contracted the design, production, and delivery of structural elements to CAA.
  3. CAA failed to deliver the elements as promised, causing delays.
  4. Newcon revised the delivery schedule to accommodate CAA’s initial failure.
  5. CAA failed to meet even the revised schedule.
  6. Newcon terminated the contract with CAA and engaged a substitute contractor.
  7. CAA treated Newcon’s termination as a breach of contract.

5. Formal Citations

  1. CAA Technologies Pte Ltd v Newcon Builders Pte Ltd, Suit No 1063 of 2013, [2016] SGHC 246

6. Timeline

DateEvent
Letter of intent signed between Newcon Builders and CAA Technologies.
Overall main contract period began.
CAA Technologies countersigned and returned the acknowledgement for the letter of intent.
Letter of acceptance sent from Newcon to CAA.
CAA received the letter of acceptance.
Superstructure works scheduled to start.
Newcon requested CAA to submit various items before commencing production of slabs.
Newcon emailed CAA again, repeating the contents of its earlier email.
Newcon expressed its hope that CAA would sign and return the letter of acceptance by email.
Newcon noted that CAA had not replied regarding the letter of acceptance, and asked CAA to sign and return it by 25 February 2013.
CAA carried out its first casting.
Newcon sent CAA a revised schedule for CAA’s initial delivery of slabs.
Revised delivery date for area 2a.
Revised delivery date for area 2b; Newcon emailed CAA recording CAA’s failure to deliver any slabs thus far.
Newcon instructed CAA to deliver the first slabs.
Newcon sent another reminder to CAA.
CAA delivered its first batch of slabs.
CAA delivered another batch of slabs.
CAA delivered slabs which matched the specifications for area 2a.
Meeting between Dr. Chi (CAA), Mr. Cao and Mr. Lin (Newcon).
Newcon emailed CAA a “Proposed Delivery Schedule for Hollow Core Slab – Medtech Hub project”.
Meeting between Newcon and CAA.
Newcon sent CAA an email titled “Letter 027 – Notice of Delay – Slow Progress in Supply of Hollow Core Slab”.
CAA did not respond to Newcon; Newcon sent to CAA formal written notice of termination.
CAA sent two letters in reply to Newcon; Newcon responded to CAA’s photographs.
CAA sent Newcon a letter before action.
Newcon replied to CAA, rejecting the allegation that it had terminated the parties’ contract without legal basis.
Newcon wrote to CAA quantifying its loss and damage at $1,554,259.93.
CAA commenced this action against Newcon.
Statement of claim (Amendment No. 1) dated.
CAA collected the I-beams.
AEIC of Chi Chao-Ton Tony dated.
Interim final payment certificate issued under the main contract.
AEIC of Chen Linhui dated.
AEIC of Cao Wei Min dated; AEIC of Lin Haifeng dated.
Trial began.
Trial.
Defendant’s closing submissions dated; Plaintiff’s closing submissions dated.
Hearing.
Judgment Date.

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that CAA breached both express and implied terms of the contract, constituting a repudiatory breach.
    • Category: Substantive
    • Sub-Issues:
      • Failure to deliver slabs on time
      • Failure to follow site progress
      • Failure to proceed with due diligence and expedition
  2. Wrongful Termination
    • Outcome: The court held that Newcon was justified in terminating the contract due to CAA's repudiatory breach.
    • Category: Substantive
  3. Implied Terms
    • Outcome: The court found that the contract contained implied terms requiring CAA to proceed with due diligence and expedition, and making time of the essence in relation to that obligation.
    • Category: Substantive
    • Sub-Issues:
      • Due diligence and expedition
      • Time is of the essence
  4. Acceptance of Contract Terms
    • Outcome: The court held that CAA's silence and conduct were not sufficient to constitute acceptance of the letter of acceptance.
    • Category: Substantive
    • Sub-Issues:
      • Silence as acceptance
      • Objective intention

8. Remedies Sought

  1. Monetary Damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Re Selectmove LtdN/AYes[1995] 1 WLR 474N/ACited for the principle that silence in response to an offer does not constitute acceptance.
Midlink Development Pte Ltd v The Stansfield Group Pte LtdN/AYes[2004] 4 SLR(R) 258SingaporeCited for the principle that it is a question of fact whether the offeree’s response was complete silence and, even if so, whether the effect of the silence, objectively ascertained against the factual background, supports the existence of a contract.
Ng Giap Hon v Westcomb Securities Pte Ltd and othersCourt of AppealYes[2009] 3 SLR(R) 518SingaporeCited for the principles on which terms will be implied in fact into a contract.
Chua Choon Cheng and others v Allgreen Properties Ltd and another appealCourt of AppealYes[2009] 3 SLR(R) 724SingaporeCited for the principles governing implied terms in law.
Jurong Engineering Ltd v Paccan Building Technology Pte LtdCourt of AppealYes[1999] 2 SLR(R) 849SingaporeCited regarding implied terms in law in construction contracts.
Sembcorp Marine Ltd v PPL Holdings Pte Ltd and another and another appealN/AYes[2013] 4 SLR 193SingaporeCited for the three-step process for ascertaining whether a contract contains a particular implied term in fact.
The MoorcockN/AYes(1889) 14 PD 64N/ACited for the business efficacy test for implying a term in fact into a contract.
Shirlaw v Southern Foundries (1926) LimitedN/AYes[1939] 2 KB 206N/ACited for the officious bystander test for implying a term in fact into a contract.
Felthouse v BindleyN/AYes(1862) 142 ER 1037N/ACited for the contractual rule that silence in response to an offer does not constitute acceptance of that offer because it is equivocal.
Greater London Council v Cleveland Bridge & Engineering Company LtdN/AYes(1984) 34 BLR 50N/AConsidered the status of an implied term obliging a contractor to proceed with due diligence and expedition.
Leander Construction Limited v Mulalley and Company LimitedN/AYes[2011] EWHC 3449 (TCC)N/AConsidered the status of an implied term obliging a contractor to proceed with due diligence and expedition.
Man Financial (S) Pte Ltd (formerly known as E D & F Man International (S) Pte Ltd) v Wong Bark Chuan DavidN/AYes[2008] 1 SLR(R) 663SingaporeCited for the principle that whether a term is a condition is to be determined by ascertaining the objective intentions of the parties on the contract’s proper construction in light of all the surrounding circumstances.
Chua Tian Chu and another v Chin Bay Ching and anotherHigh CourtYes[2011] SGHC 126SingaporeCited regarding the consequence of acts of prevention.
ACES System Development Pte Ltd v Yenty Lily (trading as Access International Services)N/AYes[2013] 4 SLR 1317SingaporeCited regarding a claim for damages in tort for wrongful detention of property.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Pre-cast concrete hollow core slabs
  • Letter of intent
  • Letter of acceptance
  • Construction schedule
  • Superstructure works
  • Notice of delay
  • Notice of termination
  • Due diligence
  • Expedition
  • Repudiatory breach

15.2 Keywords

  • Construction
  • Contract
  • Breach
  • Delay
  • Sub-contract
  • Slabs
  • Termination

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Contract Law
  • Sub-Contract
  • Breach of Contract