Doka Formwork v Grandbuild Construction: Formwork Rental Dispute over Defects & Delay
In a suit before the High Court of Singapore, Doka Formwork Pte Ltd sued Grandbuild Construction Pte Ltd for unpaid rental of formwork, the unpaid price of consumables, and damages to formwork. Grandbuild counterclaimed for losses arising from Doka's late delivery of formwork and defects in its design. The court ruled in favor of Doka Formwork, awarding them $432,443.66 after deducting payments already made by Grandbuild. The court dismissed Grandbuild's counterclaims.
1. Case Overview
1.1 Court
High Court of the Republic of Singapore1.2 Outcome
Judgment for Plaintiff
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
Doka Formwork sued Grandbuild Construction for unpaid formwork rental. Grandbuild counterclaimed for losses from late delivery and defective design. The court ruled in favor of Doka.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Doka Formwork Pte Ltd | Plaintiff | Corporation | Judgment for Plaintiff | Won | |
Grandbuild Construction Pte Ltd | Defendant | Corporation | Counterclaim Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Andrew Ang | Senior Judge | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Wee Xunji | CK Tan & Co |
Gan Kam Yuin | Bih Li & Lee LLP |
Eu Li Lian | Bih Li & Lee LLP |
4. Facts
- Doka Formwork supplied formwork to Grandbuild Construction for a warehouse project.
- The parties entered into a Principal Contract in January 2014 for the supply of formwork.
- Two variation orders were subsequently signed for the supply of formwork for the cargo and passenger lift cores.
- The Defendant informed the Plaintiff of changes to the project drawings in July 2014.
- The Plaintiff offered a variation order to amend the formwork design, but the Defendant rejected it.
- The Defendant used a forklift to reposition the formwork for the higher floors.
- The Defendant failed to attend joint inspections for damaged materials.
5. Formal Citations
- Doka Formwork Pte Ltd v Grandbuild Construction Pte Ltd, Suit No 434 of 2015, [2016] SGHC 248
6. Timeline
Date | Event |
---|---|
Principal Contract signed | |
Defendant emailed Plaintiff structural drawings | |
Plaintiff emailed slab and column formwork drawings to Defendant | |
Defendant requested first delivery of formwork | |
Plaintiff commenced delivery of formwork | |
Plaintiff sent draft drawings of cargo and passenger lift cores | |
Confirmed dimensions for cargo lift core sent to Plaintiff | |
Plaintiff replied with preliminary formwork drawings for cargo lift core | |
Defendant asked Plaintiff to proceed with liftcore material delivery | |
Cargo Lift Quotation signed | |
Plaintiff started delivering materials for cargo lift core | |
Defendant sent Plaintiff details of passenger lift core | |
Defendant asked Plaintiff to proceed with passenger lift core | |
Passenger Lift Quotation signed | |
Defendant emailed Plaintiff updated drawings of Project site | |
Plaintiff started delivering formwork for passenger lift core | |
Parties concluded a contract for the Plaintiff to supply 1000 beam connector plates | |
Parties concluded a contract for the Plaintiff to supply one set of Staxo 40 Frame | |
Defendant informed Plaintiff to start preparing formwork drawings for third storey | |
Plaintiff sent Defendant slab formwork drawing for third storey | |
Plaintiff sent a variation order to the Defendant | |
Plaintiff sent Defendant minutes of meeting dated 21 November 2014 | |
Plaintiff emailed the Defendant regarding damaged materials | |
Plaintiff issued Payment Claim No 11 | |
Settlement negotiations began | |
Returns of formwork completed | |
Judgment reserved |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that the Plaintiff did not breach the contract by delaying delivery of the lift core formwork or by providing defective formwork.
- Category: Substantive
- Sub-Issues:
- Failure to deliver formwork on time
- Defective formwork design
- Damages
- Outcome: The court awarded damages to the Plaintiff for unpaid rental, consumables, and damage to formwork.
- Category: Substantive
- Sub-Issues:
- Damages for defects
- Damages for delay in completion
- Unfair Contract Terms
- Outcome: The court held that the contractual clauses regarding the condition of delivered goods and the binding nature of the Plaintiff's findings were not unreasonable under the Unfair Contract Terms Act.
- Category: Substantive
- Pleadings
- Outcome: The court found that the Defendant was not irreparably prejudiced by the Plaintiff's failure to plead the specific clauses in the contract which it is presently relying on.
- Category: Procedural
- Related Cases:
- [2015] 5 SLR 1422
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
- Unpaid Rental
- Damages for Defects
10. Practice Areas
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
V Nithia (co-administratrix of the estate of Ponnusamy Sivapakiam, deceased) v Buthmanaban s/o Vaithilingam and another | Court of Appeal | Yes | [2015] 5 SLR 1422 | Singapore | Cited for the importance of adhering to the rules of pleadings and the court's discretion to allow reliance on unpleaded points where no irreparable prejudice would be caused. |
Kay Lim Construction & Trading Pte Ltd v Soon Douglas (Pte) Ltd and another | N/A | Yes | [2013] 1 SLR 1 | Singapore | Cited for the principle that courts should be less quick to intervene on the ground of unreasonableness when dealing with two commercial entities. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Unfair Contract Terms Act (Cap 396, 1994 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Formwork
- Rental
- Delivery Notes
- Staxo Frame
- Beam Connector Plates
- Lift Core
- Variation Order
- Joint Inspection
- Structural Drawings
15.2 Keywords
- formwork
- construction
- rental
- defects
- delay
- Singapore
- contract
17. Areas of Law
Area Name | Relevance Score |
---|---|
Construction Law | 90 |
Damages | 80 |
Breach of Contract | 60 |
Contract Law | 50 |
16. Subjects
- Construction Dispute
- Contract Law
- Building and Construction Law
- Formwork Rental