Linkforce v Kajima: Setting Aside Adjudication Determination Under SOPA for Premature Adjudication Application

In Linkforce Pte Ltd v Kajima Overseas Asia Pte Ltd, the High Court of Singapore heard an application by Kajima to set aside an adjudication determination (AD) and an Order of Court obtained by Linkforce. The dispute arose from a subcontract where Linkforce was to carry out fire protection installation works for Kajima. The court, led by Judicial Commissioner Foo Chee Hock, granted Kajima's application, finding that Linkforce's adjudication application was premature because the payment claim was served before the contractually stipulated deadline. The court held that there was no estoppel, waiver, or variation of the subcontract that would alter the deadline for serving payment claims. Linkforce has appealed the decision.

1. Case Overview

1.1 Court

High Court of the Republic of Singapore

1.2 Outcome

Adjudication Determination and Order of Court set aside.

1.3 Case Type

Building and Construction Law

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

The High Court set aside an adjudication determination under SOPA, finding the adjudication application was premature due to early payment claim.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Linkforce Pte LtdApplicant, AppellantCorporationApplication DismissedLost
Kajima Overseas Asia Pte LtdRespondentCorporationApplication AllowedWon

3. Judges

Judge NameTitleDelivered Judgment
Foo Chee HockJudicial CommissionerYes

4. Counsels

4. Facts

  1. Linkforce and Kajima entered into a subcontract on 1 November 2012 for fire protection installation works.
  2. A dispute arose between Linkforce and Kajima regarding payment.
  3. Linkforce served Payment Claim 33 (PC 33) on Kajima on 3 June 2016.
  4. Kajima did not provide a payment response by 24 June 2016, according to Linkforce.
  5. Linkforce lodged an adjudication application on 8 July 2016.
  6. Kajima lodged an adjudication response on 18 July 2016, objecting to the prematurity of the adjudication application.
  7. The adjudicator agreed with Linkforce and awarded Linkforce $893,751.86 and costs of $22,470.

5. Formal Citations

  1. Linkforce Pte Ltd v Kajima Overseas Asia Pte Ltd, HC/Originating Summons No 947/2016(HC/Summons No 4806/2016), [2017] SGHC 46

6. Timeline

DateEvent
Subcontract signed between Kajima and Linkforce.
Kajima's project manager sent an email regarding progress claim submission requirements.
Linkforce served Payment Claim 33 on Kajima.
Linkforce notified Kajima of its intention to apply for adjudication.
Linkforce lodged an adjudication application.
Kajima lodged an adjudication response.
Kajima provided a payment response to Linkforce.
Adjudication determination made by Mr. Seah Choo Meng.
Linkforce filed Originating Summons No 947 of 2016.
Kajima filed Summons No 4806 of 2016 to set aside the Order of Court and the adjudication determination.
Hearing date.
Hearing date.
Court granted Kajima’s application to set aside the Order of Court and the adjudication determination.
Date of the decision.

7. Legal Issues

  1. Premature Adjudication Application
    • Outcome: The court held that the adjudication application was premature, invalidating the adjudication determination.
    • Category: Procedural
    • Sub-Issues:
      • Failure to comply with SOPA timelines
    • Related Cases:
      • [2015] SGHC 226
      • [2014] SGHC 142
  2. Estoppel, Waiver, and Variation of Contract
    • Outcome: The court found that there was no clear and unambiguous representation from Kajima that payment claims need not be served on the last day of each month, and thus no estoppel, waiver, or variation of the subcontract.
    • Category: Substantive
    • Sub-Issues:
      • Clear and unambiguous representation
      • Reliance
      • Detriment
      • Offer
      • Acceptance
      • Consideration
    • Related Cases:
      • [2009] 2 SLR(R) 532
      • [2012] 1 SLR 152
      • [2009] 2 SLR(R) 332
      • [2013] 4 SLR 409
  3. Breach of Natural Justice
    • Outcome: The court found that the premature adjudication application caused Kajima's payment response to be wrongly excluded from consideration, resulting in a breach of natural justice.
    • Category: Procedural
    • Sub-Issues:
      • Wrongful exclusion of payment response from consideration

8. Remedies Sought

  1. Setting aside of adjudication determination
  2. Setting aside of order of court

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Lee Wee Lick Terence v Chua Say EngHigh CourtYes[2013] 1 SLR 401SingaporeCited for the test for setting aside an adjudication determination.
UES Holdings Pte Ltd v Grouteam Pte LtdHigh CourtYes[2016] 1 SLR 312SingaporeCited regarding the propriety of examining the merits of the adjudicator's decision.
Grouteam Pte Ltd v UES Holdings Pte LtdCourt of AppealYes[2016] 5 SLR 1011SingaporeCited for the importance of strict adherence to timelines under SOPA.
YTL Construction (S) Pte Ltd v Balanced Engineering & Construction Pte LtdHigh CourtYes[2014] SGHC 142SingaporeCited for the principle that out-of-time adjudication applications invalidate adjudication determinations.
Newcon Builders Pte Ltd v Sino New Steel Pte LtdHigh CourtYes[2015] SGHC 226SingaporeCited for the principle that premature adjudication applications invalidate adjudication determinations.
Yokogawa Engineering Asia Pte Ltd v Transtel Engineering Pte LtdCourt of AppealYes[2009] 2 SLR(R) 532SingaporeCited for the elements of estoppel by representation.
Chai Cher Watt v SDL Technologies Pte LtdHigh CourtYes[2012] 1 SLR 152SingaporeCited for the categorization of waiver into waiver by election and waiver by estoppel.
Gay Choon Ing v Loh Sze Ti Terence PeterCourt of AppealYes[2009] 2 SLR(R) 332SingaporeCited for the requirements of an offer in contract law.
Aero-Gate Pte Ltd v Engen Marine Engineering Pte LtdHigh CourtYes[2013] 4 SLR 409SingaporeCited for the elements required for the variation of a contract.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 13(3)(a)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 12(5)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 15(3)(a)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 16(3)(c)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Adjudication Application
  • Adjudication Determination
  • Payment Claim
  • Payment Response
  • Security of Payment Act
  • Estoppel
  • Waiver
  • Variation
  • Premature Adjudication
  • Natural Justice

15.2 Keywords

  • Building and Construction
  • Security of Payment Act
  • Adjudication
  • Singapore
  • Construction Law

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Adjudication
  • Contract Law