I-Lab Engineering v Shriro (Singapore): Suspension of Work & Recovery of Loss

I-Lab Engineering Pte Ltd, the plaintiff, sued Shriro (Singapore) Pte Ltd, the defendant, in the High Court of Singapore, regarding a dispute over payment for air-conditioning and mechanical ventilation works on a construction project. The court, presided over by Assistant Registrar Elton Tan Xue Yang, addressed the central question of whether the defendant, as a sub-contractor, is entitled to claim the full contract price for omitted works during a period of suspension under s 26(3) of the Building and Construction Industry Security of Payment Act. The court ordered that the counterclaim for omitted works be amended to replace the phrase 'the full contract sum' with 'damages to be assessed'.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Counterclaim for Omitted Works to be amended to replace the phrase 'the full contract sum' with 'damages to be assessed'.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Subcontractor I-Lab Engineering sued Shriro (Singapore) over a payment dispute. The court addressed the scope of loss recoverable under s 26(3) of the SOP Act.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
I-Lab Engineering Pte LtdApplicant, PlaintiffCorporationPartialPartial
Shriro (Singapore) Pte LtdRespondent, DefendantCorporationPartialPartial

3. Judges

Judge NameTitleDelivered Judgment
Elton Tan Xue YangAssistant RegistrarYes

4. Counsels

4. Facts

  1. I-Lab Engineering is the sub-contractor for a construction project.
  2. Shriro (Singapore) is I-Lab Engineering's sub-contractor for ACMV and electrical installation works.
  3. The Sub-Contract provided for lump sum payment of $10,650,000 to Shriro.
  4. Shriro lodged an adjudication application against I-Lab for the amount claimed in Payment Claim No. 19.
  5. I-Lab did not serve a valid payment response.
  6. The adjudicator directed I-Lab to pay Shriro $2,467,343.54 (including GST).
  7. Shriro suspended its works pending payment of the adjudicated sum.
  8. I-Lab carried out various works falling within the scope of the Sub-Contract Works during the Suspension Period.

5. Formal Citations

  1. I-Lab Engineering Pte Ltd v Shriro (Singapore) Pte Ltd, Suit No 94 of 2018 (Summons No 3510 of 2018), [2018] SGHCR 15

6. Timeline

DateEvent
Plaintiff issued a letter of award to the Defendant
Defendant signed the letter of award
Defendant lodged an adjudication application against the Plaintiff
Adjudication determination directing Plaintiff to pay Defendant $2,467,343.54 (including GST)
Defendant suspended its works
Plaintiff commenced Suit No 94 of 2018 against the Defendant
End of Suspension Period
Plaintiff filed Summons No 3510 of 2018
Hearing of parties
Hearing of parties
Hearing of parties
Decision delivered on the Striking Out Application
Judgment reserved
Judgment

7. Legal Issues

  1. Recovery of Loss or Expenses
    • Outcome: The court held that the right to recover loss or expenses under s 26(3) of the Act does not extend to the full contract sum.
    • Category: Substantive
    • Sub-Issues:
      • Measure of damages
      • Causation of loss
  2. Suspension of Performance
    • Outcome: The court discussed the right to suspend the carrying out of construction work under s 26(1) of the Building and Construction Industry Security of Payment Act.
    • Category: Substantive

8. Remedies Sought

  1. Declaration
  2. Damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Jia Min Building Construction Pte Ltd v Ann Lee Pte LtdHigh CourtYes[2004] 3 SLR(R) 288SingaporeCited for the principle that a contractor has no general right at common law to suspend work unless expressly agreed upon.
Parkview Constructions Pty Ltd v Sydney Civil Excavations Pte Ltd & anorNew South Wales Supreme CourtYes[2009] NSWSC 61AustraliaCited to emphasize the need for a causal connection between the loss or expenses claimed and the removal of contractual works by the respondent.
Paul Michael Pty Ltd (subject to deed of company arrangement) v Urban Traders Pty LtdNew South Wales Supreme CourtYes[2010] NSWSC 1246AustraliaCited to emphasize the need for a causal connection between the loss or expenses claimed and the removal of contractual works by the respondent.
Urban Traders Pty Ltd v Paul Michael Pty LtdNew South Wales Supreme CourtYes[2009] NSWSC 1072AustraliaCited for the principle that the right to suspend work would lose much of its efficacy if a proprietor could react to the suspension by withdrawing the work from the builder.
Alvin Nicholas Nathan v Raffles Assets (Singapore) Pte LtdCourt of AppealYes[2016] 2 SLR 1056SingaporeCited for the principles of awarding damages pursuant to a repudiatory breach of contract.

13. Applicable Rules

Rule Name
Rules of Court (Cap 322, R 5, 2014 Rev Ed) O 18 r 19(1)(a)
Rules of Court (Cap 322, R 5, 2014 Rev Ed) O 18 r 19(1)

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 26(1)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 26(3)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 23(1)(b)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 26(2)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 26(2)(b)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) s 15(3)Singapore
Building and Construction Industry Security of Payment Act 1999 s 27(1)New South Wales
Building and Construction Industry Security of Payment Act 1999 s 27(2A)New South Wales
Building and Construction Industry Security of Payment Act 1999 s 4New South Wales
Housing Grants, Construction and Regeneration Act 1996 (c. 53) s 112(1)United Kingdom

15. Key Terms and Keywords

15.1 Key Terms

  • Suspension of works
  • Adjudication determination
  • Omitted Works
  • Loss or expenses
  • Full contract sum
  • Sub-Contract Works
  • Adjudicated amount
  • Payment Claim
  • Payment Response

15.2 Keywords

  • Building and Construction Industry Security of Payment Act
  • Suspension of work
  • Loss and expenses
  • Construction adjudication
  • Singapore High Court

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Security of Payment
  • Contract Law