Winstech Engineering v Shanghai Chong Kee: Sub-contractor Claims & Privity of Contract
In Winstech Engineering Pte Ltd v Shanghai Chong Kee Furniture & Construction Pte Ltd, the High Court of Singapore dismissed Winstech Engineering's claim against Shanghai Chong Kee for breach of contract. Winstech, a sub-contractor, alleged that Shanghai Chong Kee failed to provide a line of credit as specified in a letter of award. The court, presided over by Lee Seiu Kin J, found that the contract was between Winstech and JDK Construction Pte Ltd, not Shanghai Chong Kee, and therefore there was no privity of contract. The court also dismissed Winstech's claims for outstanding progress payments and variation order payments, as these claims arose from the contract with JDK. The judgment was delivered on 12 September 2019.
1. Case Overview
1.1 Court
High Court of the Republic of Singapore1.2 Outcome
Plaintiff's claims are dismissed.
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
Winstech Engineering sues Shanghai Chong Kee for breach of contract regarding a line of credit. The court dismissed the claims due to lack of privity.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Shanghai Chong Kee Furniture & Construction Pte Ltd | Defendant | Corporation | Judgment for Defendant | Won | |
Winstech Engineering Pte Ltd | Plaintiff | Corporation | Claim Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Lee Seiu Kin | Judge | Yes |
4. Counsels
4. Facts
- Defendant was the main contractor for a hotel project.
- Defendant engaged JDK Construction Pte Ltd as its main sub-contractor.
- JDK sub-contracted M&E works to the plaintiff, Winstech Engineering Pte Ltd.
- The letter of award stated a line of credit to be issued by the defendant.
- Plaintiff claimed the defendant breached the contract by failing to provide the full line of credit.
- Plaintiff requested financing from JDK, not the defendant.
- Defendant terminated the sub-contract with JDK.
5. Formal Citations
- Winstech Engineering Pte Ltd v Shanghai Chong Kee Furniture & Construction Pte Ltd, Suit No 788 of 2018, [2019] SGHC 213
6. Timeline
Date | Event |
---|---|
Defendant engaged as main contractor for hotel project. | |
Letter of award issued to Plaintiff by JDK Construction Pte Ltd. | |
Plaintiff completed 95% of sub-contract works. | |
Defendant terminated sub-contract with JDK. | |
Trial began. | |
Judgment reserved. |
7. Legal Issues
- Breach of Contract
- Outcome: The court held that there was no breach of contract because the defendant was not a party to the contract between the plaintiff and JDK.
- Category: Substantive
- Privity of Contract
- Outcome: The court held that the defendant was not bound by the contract between the plaintiff and JDK due to lack of privity.
- Category: Substantive
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
No cited cases |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Sub-contract
- Line of Credit
- Privity of Contract
- Letter of Award
- Variation Orders
- Progress Payments
15.2 Keywords
- Sub-contractor
- Breach of Contract
- Privity of Contract
- Construction Law
- Singapore High Court
17. Areas of Law
Area Name | Relevance Score |
---|---|
Construction Law | 85 |
Subcontracts | 80 |
Breach of Contract | 70 |
Contract Law | 70 |
16. Subjects
- Construction Dispute
- Contract Law