CEX v CEY: Performance Bond Call & Unconscionability in Construction Contract

In CEX v CEY, the Singapore High Court addressed an application by CEX, the main contractor, for an injunction to restrain CEY, the developer, from calling on a performance bond. The dispute arose from delays in a construction project. CEX argued that CEY's call on the bond was unconscionable because CEY pressured CEX to continue construction works illegally after the project's qualified person was incapacitated. The court, presided over by Justice Lee Seiu Kin, found that CEY had acted unconscionably and granted the injunction, restraining CEY from calling on the performance bond.

1. Case Overview

1.1 Court

High Court of the Republic of Singapore

1.2 Outcome

Injunction granted, restraining the call on the performance bond.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Singapore High Court case concerning an injunction to restrain a call on a performance bond due to unconscionability in a construction project.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
CEXApplicantCorporationInjunction grantedWon
CEYRespondentCorporationInjunction granted against CEYLost
CEZRespondentCorporationNeutralNeutral

3. Judges

Judge NameTitleDelivered Judgment
Lee Seiu KinJudgeYes

4. Counsels

4. Facts

  1. CEY is the developer for six strata detached houses at [redacted].
  2. CEX took over the project as its main contractor on 9 May 2017.
  3. CEX procured a performance bond from CEZ in favour of CEY.
  4. Mr. John Seah, the architectural qualified person for the Project, took ill and was hospitalized on 7 January 2019.
  5. Mr. Seah passed away on 24 January 2019.
  6. Mr. Ng issued a termination certificate “on behalf of [Mr. Seah]” on 19 February 2019.
  7. CEY issued a notice of termination on 20 February 2019.
  8. CEY called on the performance bond on 19 July 2019.
  9. The permits issued under s 6 of the Building Control Act automatically lapsed when Mr. Seah took ill on 7 January 2019.

5. Formal Citations

  1. CEX v CEY and another, Originating Summons No 933 of 2019, [2020] SGHC 100

6. Timeline

DateEvent
Letter of award dated for the proposed erection of strata landed housing development.
Performance guarantee (DBPB17S019663) dated for the sum of S$1,063,000.00 issued by Ergo Insurance Pte Ltd in favour of CEY Development Pte Ltd
CEX took over the project as its main contractor.
Mr. John Seah took ill and was hospitalized.
Mr. Seah attempted to authorise Mr. Ng Hoe Theong to “cover [his] duties”.
Mr. Seah passed away.
Mr. Ng issued a termination certificate “on behalf of [Mr. Seah]”.
CEY issued a notice of termination.
CEX served a notice of arbitration.
CEY called on the performance bond.
Judgment by Lee Seiu Kin J.
Judgment date.

7. Legal Issues

  1. Unconscionability
    • Outcome: The court found that CEY had acted unconscionably in calling on the performance bond.
    • Category: Substantive
    • Sub-Issues:
      • Calls for excessive sums
      • Calls based on contractual breaches that the beneficiary of the call itself is responsible for
      • Calls tainted by unclean hands
      • Calls made for ulterior motives
      • Calls based on a position which is inconsistent with the stance that the beneficiary took prior to calling on the performance bond
    • Related Cases:
      • [1995] 2 SLR(R) 262
      • [1998] 2 SLR(R) 732
      • [1999] SGHC 201
      • [1998] 3 SLR(R) 961
      • [1996] SGHC 136
      • [1999] 3 SLR(R) 44
      • [2000] 1 SLR(R) 117
      • [2012] 3 SLR 352
      • [2011] 2 SLR 47
      • [2012] 3 SLR 125
      • [2013] 3 SLR 1142
      • [2019] 5 SLR 215
      • [2008] 3 SLR(R) 1029
      • [2019] 4 SLR 1324
      • [2018] SGHC 33
      • [2003] 4 SLR(R) 73
      • [2018] SGHC 249
      • [2009] SGHC 7
      • [2018] SGHC 163
      • [2000] 3 SLR(R) 198
      • [1996] 4 All ER 563
      • [2018] SGHC 145
      • [2013] SGHC 86
      • [2001] SGHC 334
      • [1990] 2 SLR(R) 520
      • [1993] 2 SLR(R) 341
      • [2003] 1 SLR(R) 394
      • [2019] 2 SLR 295
      • [2019] SGHC 267
      • [2018] 3 SLR 404
      • [2001] 3 SLR(R) 716
      • [2001] 1 SLR(R) 458
  2. Statutory Interpretation of s 6(5) of the Building Control Act
    • Outcome: The court held that the permit to carry out structural works lapsed on 7 January 2019 when Mr Seah was hospitalised.
    • Category: Statutory
    • Sub-Issues:
      • Whether the holder of a permit to carry out structural works ceases to be a qualified person should the permit holder take ill and become otherwise incapacitated

8. Remedies Sought

  1. Injunction to restrain call on performance bond

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Law
  • Commercial Litigation
  • Arbitration

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Bocotra Construction Pte Ltd and others v Attorney-GeneralCourt of AppealYes[1995] 2 SLR(R) 262SingaporeCited for the principle of unconscionability in relation to restraining calls on performance bonds.
New Civilbuild Pte Ltd v Guobena Sdn BhdHigh CourtYes[1998] 2 SLR(R) 732SingaporeCited as a case that viewed 'unconscionability' as interchangeable with 'fraud' in the context of restraining calls on performance bonds.
Dauphin Offshore Engineering & Trading Pte Ltd v The Private Office of His Royal Highness Sheikh Sultan bin Khalifa bin Zayed Al NahyanHigh CourtYes[1999] SGHC 201SingaporeCited as a case that viewed 'unconscionability' as interchangeable with 'fraud' in the context of restraining calls on performance bonds.
Min Thai Holdings Pte Ltd v Sunlabel Pte Ltd and anotherHigh CourtYes[1998] 3 SLR(R) 961SingaporeCited as a case that recognized unconscionability as a separate ground for restraining calls on performance bonds.
Raymond Construction Pte Ltd v Low Yang Tong and anotherHigh CourtYes[1996] SGHC 136SingaporeCited as a case that recognized unconscionability as a separate ground for restraining calls on performance bonds and for elements of unfairness and conduct lacking in good faith.
GHL Pte Ltd v Unitrack Building Construction Pte Ltd and anotherCourt of AppealYes[1999] 3 SLR(R) 44SingaporeCited for ruling that unconscionability is a separate and distinct ground for granting an injunction to restrain the enforcement of a performance bond.
Dauphin Offshore Engineering & Trading Pte Ltd v The Private Office of HRR Sheikh Sultan bin Khalifa bin Zayed Al NahyanCourt of AppealYes[2000] 1 SLR(R) 117SingaporeCited for clarifying the legal threshold for establishing the unconscionability exception, requiring a strong prima facie case.
BS Mount Sophia Pte Ltd v Join-Aim Pte LtdHigh CourtYes[2012] 3 SLR 352SingaporeCited for clarifying the legal threshold for establishing the unconscionability exception, requiring a strong prima facie case.
JBE Properties Pte Ltd v Gammon Pte LtdHigh CourtYes[2011] 2 SLR 47SingaporeCited for defending the unconscionability exception and explaining its rationale.
Master Marine AS v Labroy Offshore Ltd and othersHigh CourtYes[2012] 3 SLR 125SingaporeCited for the principles to identify the nature of the performance bond.
York International Pte Ltd v Voltas LtdHigh CourtYes[2013] 3 SLR 1142SingaporeCited for ascertaining whether the call falls within the terms of the bond.
BWN v BWOHigh CourtYes[2019] 5 SLR 215SingaporeCited for ascertaining whether the call falls within the terms of the bond.
Zurich Insurance (Singapore) Pte Ltd v B-Gold Interior Design & Construction Pte LtdHigh CourtYes[2008] 3 SLR(R) 1029SingaporeCited for the principles of interpretation of the underlying contract.
Ryobi Tactics Pte Ltd v UES Holdings Pte Ltd and another and another matterHigh CourtYes[2019] 4 SLR 1324SingaporeCited for the principle that contractual terms may cumulatively give rise to an entirely separate requirement for a call on a performance bond.
Milan International Pte Ltd v Cluny Development Pte Ltd and anotherHigh CourtYes[2018] SGHC 33SingaporeCited for discussing whether a beneficiary’s termination of its contract with the obligor was unlawful.
Newtech Engineering Construction Pte Ltd v BKB Engineering Constructions Pte Ltd and othersHigh CourtYes[2003] 4 SLR(R) 73SingaporeCited for examining whether the obligors had been in breach of the underlying contract in the first place.
Hup Seng Lee Pte Ltd v Jaclyn Patrina ReutensHigh CourtYes[2018] SGHC 249SingaporeCited for relying on “credible prima facie evidence of defects in the works” in establishing unconscionability.
Leighton Contractors (Singapore) Pte Ltd v J-Power Systems Corp and anotherHigh CourtYes[2009] SGHC 7SingaporeCited for the proposition that if the obligor were able to demonstrate conclusively that there had in fact been no breach, then that would lend weight to its assertions that the beneficiary had acted unconscionably.
AES Façade Pte Ltd v Wyse Pte Ltd and anotherHigh CourtYes[2018] SGHC 163SingaporeCited for the principle that on-demand performance bonds do not typically require beneficiaries to prove their losses before being entitled to call on the bond.
Eltraco International Pte Ltd v CGH Development Pte LtdHigh CourtYes[2000] 3 SLR(R) 198SingaporeCited for the principle that when a beneficiary simply cannot point to any loss suffered, the courts may be prompted to infer that the call had been abusive and lacked bona fides.
Cargill International SA v Bangladesh Sugar & Food Industries CorporationQueen's Bench DivisionYes[1996] 4 All ER 563England and WalesDiscussed in Eltraco International Pte Ltd v CGH Development Pte Ltd for the principle that when a beneficiary simply cannot point to any loss suffered, the courts may be prompted to infer that the call had been abusive and lacked bona fides.
Sunrise Industries (India) Ltd v PT OKI Pulp & Paper Mills and anotherHigh CourtYes[2018] SGHC 145SingaporeCited as an authority that considered the actual and potential losses claimed by the beneficiaries in deciding whether the call had been excessive.
Ryobi-Kiso (S) Pte Ltd v Lum Chang Building Contractors Pte Ltd and anotherHigh CourtYes[2013] SGHC 86SingaporeCited as an authority that considered the actual and potential losses claimed by the beneficiaries in deciding whether the call had been excessive.
Liang Huat Aluminium Industries Pte Ltd v Hi-Tek Construction Pte LtdHigh CourtYes[2001] SGHC 334SingaporeCited for the principle that the burden of proving a strong prima facie case ultimately lies on the obligor to produce cogent evidence that the sums are indeed excessive.
Royal Design Studio Pte Ltd v Chang Development Pte LtdHigh CourtYes[1990] 2 SLR(R) 520SingaporeCited for the principle that it lies foul in the mouth of the beneficiary to complain of a breach of contract if it had itself been responsible for the breach.
Kvaerner Singapore Pte Ltd v UDL Shipbuilding (Singapore) Pte LtdHigh CourtYes[1993] 2 SLR(R) 341SingaporeCited for the principle that it lies foul in the mouth of the beneficiary to complain of a breach of contract if it had itself been responsible for the breach.
Anwar Siraj and another v Teo Hee Lai Building Construction Pte LtdCourt of AppealYes[2003] 1 SLR(R) 394SingaporeCited for the principle that the courts have professed an aversion towards overtly technical analysis at this stage of the proceedings.
Bintai Kindenko Pte Ltd v Samsung C&T Corp and anotherCourt of AppealYes[2019] 2 SLR 295SingaporeCited for the principle that unclean hands may manifest in less than full and frank disclosure during a hearing for an ex parte injunction.
Soon Li Heng Civil Engineering Pte Ltd v Samsung C&T Corp and anotherHigh CourtYes[2019] SGHC 267SingaporeCited for the principle that calls made for ulterior motives should be restrained.
LQS Construction Pte Ltd v Mencast Marine Pte Ltd and anotherHigh CourtYes[2018] 3 SLR 404SingaporeCited for the principle that proving that the bond had been called for an ulterior motive is ultimately a fact-sensitive inquiry involving reference to factors such as the timing of the call.
Samwoh Asphalt Premix Pte Ltd v Sum Cheong Piling Pte Ltd and anotherCourt of AppealYes[2001] 3 SLR(R) 716SingaporeCited for the principle that tactical calls aimed at putting contractors under financial pressure to compromise, to be unconscionable as well.
Hiap Hong & Co Pte Ltd v Hong Huat Development Co (Pte) LtdCourt of AppealYes[2001] 1 SLR(R) 458SingaporeCited for the principle that an architect’s actions are not relevant unless he is an agent of the beneficiary.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Arbitration Act (Cap 10, Rev Ed 2002)Singapore
Building Control Act (Cap 29, 1999 Rev Ed)Singapore
Building Control Act (Cap 29, 1999 Rev Ed) s 6(5)Singapore
Building Control Act (Cap 29, 1999 Rev Ed) s 8(2)Singapore
Architects Act (Cap 12, 2000 Rev Ed)Singapore
Professional Engineers Act (Cap. 253, 1992 Rev Ed)Singapore
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Performance bond
  • Unconscionability
  • Building Control Act
  • Qualified person
  • Termination certificate
  • Notice of termination
  • Illegality
  • Construction works
  • Architectural qualified person
  • Permit
  • Strata landed housing development

15.2 Keywords

  • Performance bond
  • Unconscionability
  • Construction contract
  • Injunction
  • Building Control Act

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Arbitration
  • Contract Law
  • Performance Bonds
  • Injunctions