Guthrie Engineering (S) Pte Ltd
Guthrie Engineering (S) Pte Ltd is a corporation in Singapore's legal system. The party has been involved in 3 cases in Singapore's courts. Represented by 4 counsels. Through 1 law firm. Their track record shows a 33.3% success rate in resolved cases. They have been involved in 2 complex cases, representing 66.7% of their total caseload.
Legal Representation
Guthrie Engineering (S) Pte Ltd has been represented by 1 law firm and 4 counsels.
Law Firm | Cases Handled |
---|---|
Ang and Partners | 1 case |
Case Complexity Analysis
Analysis of Guthrie Engineering (S) Pte Ltd's case complexity based on the number of parties involved and case characteristics.
Complexity Overview
- Average Parties per Case
- 3.3
- Complex Cases
- 2 (66.7%)
- Cases with more than 3 parties
Complexity by Case Type
Type | Cases |
---|---|
Lost | 12.0 parties avg |
Partial | 14.0 parties avg |
Won | 14.0 parties avg |
Complexity Trends Over Time
Year | Cases |
---|---|
2005 | 14.0 parties avg |
2004 | 23.0 parties avg |
Case Outcome Analytics
Analysis of Guthrie Engineering (S) Pte Ltd's case outcomes, including distribution by type, yearly trends, and monetary outcomes where applicable.
Outcome Distribution
Outcome Type | Cases |
---|---|
Lost | 1(33.3%) |
Partial | 1(33.3%) |
Won | 1(33.3%) |
Monetary Outcomes
Currency | Average |
---|---|
SGD | 500.002 cases |
Yearly Outcome Trends
Year | Total Cases |
---|---|
2005 | 1 1 |
2004 | 2 11 |
Case History
Displaying all 3 cases
Case | Role | Outcome |
---|---|---|
27 Mar 2005 | Respondent, Appellant | WonGuthrie's cross-appeal was allowed. |
10 Aug 2004 | Defendant | PartialJudgment for the plaintiff against the third defendant on the ground of inducing a breach of contract, but only nominal damages of $1,000 were awarded (assumed SGD, as the judgment originates from Singapore). |
11 Jul 2004 | Defendant | LostDefendant's counterclaim was dismissed. The judgment does not specify a currency, so SGD is assumed as the currency of the jurisdiction. |