Eltraco v CGH: Performance Bond Call & Unconscionability in Construction Contract
Eltraco International Pte Ltd, the appellant, appealed against the High Court's decision regarding CGH Development Pte Ltd's, the respondent, call on a performance bond. The Court of Appeal of Singapore, on 18 September 2000, partially allowed the appeal, reducing the amount CGH could claim under the bond from $1.6 million to $600,000, citing unconscionability. The case concerned a building contract and disputes over defective works.
1. Case Overview
1.1 Court
Court of Appeal1.2 Outcome
Appeal allowed in part.
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Eltraco appealed against CGH's call on a performance bond. The court partially allowed the appeal, reducing the amount CGH could claim, citing unconscionability.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Eltraco International Pte Ltd | Appellant | Corporation | Appeal allowed in part | Partial | |
CGH Development Pte Ltd | Respondent | Corporation | Partial Loss | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Chao Hick Tin | Justice of the Court of Appeal | Yes |
L P Thean | Justice of the Court of Appeal | No |
4. Counsels
4. Facts
- Eltraco was the main contractor for superstructure works on a service apartment cum shops development.
- The contract sum was $24,388,000, and the contract incorporated the 1990 Singapore Institute of Architects Conditions.
- The project was completed on 29 August 1998, and a completion certificate was issued.
- A dispute arose regarding defective works.
- CGH called on a performance bond for $2,438,800 due to the defective works.
- Eltraco sought an injunction to restrain CGH from receiving payment under the bond.
- The architect issued a schedule of defects, which Eltraco claimed to have mostly rectified.
5. Formal Citations
- Eltraco International Pte Ltd v CGH Development Pte Ltd, CA 67/2000, [2000] SGCA 51
6. Timeline
Date | Event |
---|---|
Singapore Institute of Architects Conditions incorporated into contract | |
Eltraco submitted progress claim No 32 | |
Project completed; completion certificate issued | |
Original maintenance period expired | |
Correspondence between architect, Eltraco, and QS regarding defects | |
Architect forwarded a schedule of defects to Eltraco | |
CGH obtained a quotation from WTK Builders Pte Ltd to effect the rectification of all the defective works | |
Architect issued a letter to Eltraco enclosing a schedule of defects | |
Eltraco replied to architect regarding defects | |
Joint inspection carried out | |
Architects listed out twenty major items of defects in a letter to the QS | |
CGH demanded payment on the bond from QBE | |
Eltraco objected to CGH's call on the bond | |
Eltraco objected to CGH's call on the bond | |
Extended maintenance period expired | |
Eltraco wrote a chaser to the architect | |
QS stated that claim No 32 could not be recommended because the defective works had not been fully rectified | |
QS gave a valuation on eight items of defects amounting to $627,600 | |
Eltraco suggested settling five of the eight items valued by the QS at $61,716.80 | |
CGH instituted Suit 129/2000 against QBE | |
Eltraco instituted Suit 214/2000 against CGH seeking an injunction | |
Judgment issued |
7. Legal Issues
- Unconscionability
- Outcome: The court held that unconscionability is a valid ground to restrain a call on a performance bond and reduced the amount CGH could claim.
- Category: Substantive
- Sub-Issues:
- Lack of good faith
- Unfairness
- Related Cases:
- [1999] 4 SLR 604
- [2000] 1 SLR 657
- Performance Bond Call
- Outcome: The court determined that the terms of the bond did not require the beneficiary to establish a breach before calling on it, but the call could be restrained if unconscionable.
- Category: Substantive
- Sub-Issues:
- Premature call on bond
- Accrued rights to damages
8. Remedies Sought
- Injunctive Relief
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Commercial Litigation
- Construction Law
- Performance Bonds
11. Industries
- Construction
- Banking
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
GHL Pte Ltd v Unitrack Building Construction Pte Ltd | High Court | Yes | [1999] 4 SLR 604 | Singapore | Cited as authority for the principle that unconscionability is a separate ground, apart from fraud, to restrain a beneficiary from calling or receiving moneys under a performance bond. |
Dauphin Offshore Engineering & Trading Pte Ltd v The Private Office of HRH Sheikh Sultan bin Khalifa | Court of Appeal | Yes | [2000] 1 SLR 657 | Singapore | Considered the decision in GHL and stated that what kind of situation would constitute unconscionability would have to depend on the facts of each case. |
Cargill International SA & Anor v Bangladesh Sugar & Food Industries Corp | N/A | Yes | [1996] 4 All ER 563 | England | Discussed in relation to the terms of the bond and the possibility of issuing a restraint on the call due to unconscionability. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Performance bond
- Unconscionability
- Defective works
- Building contract
- Retention sum
- Progress claim
- SIA Conditions
- Demand bond
- Injunction
15.2 Keywords
- Performance bond
- Unconscionability
- Construction contract
- Defects
- Injunction
17. Areas of Law
Area Name | Relevance Score |
---|---|
Performance Bond | 90 |
Unconscionability | 85 |
Contract Law | 75 |
Building Contract | 65 |
Breach of Contract | 60 |
Construction Law | 50 |
Arbitration | 30 |
Civil Procedure | 25 |
16. Subjects
- Construction Dispute
- Contract Law
- Banking Law
- Performance Bonds