National Skin Centre v Eutech: Breach of Contract for Computer System Commissioning
The National Skin Centre (NSC) sued Eutech Cybernetics Pte Ltd in the High Court of Singapore, alleging breach of contract for failing to deliver and commission a computer system with customized software by the agreed deadline. Eutech counterclaimed, alleging wrongful termination and seeking unpaid invoices and damages. The court, presided over by Judicial Commissioner Lee Seiu Kin, found Eutech in breach of contract and ruled in favor of NSC, awarding damages and dismissing Eutech's counterclaim.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Judgment for Plaintiff
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
The National Skin Centre sued Eutech for breach of contract related to a computer system. The court found Eutech liable for failing to commission the system.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
National Skin Centre (Singapore) Pte Ltd | Plaintiff | Corporation | Judgment for Plaintiff | Won | |
Eutech Cybernetics Pte Ltd | Defendant | Corporation | Counterclaim Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Lee Seiu Kin | Judicial Commissioner | Yes |
4. Counsels
4. Facts
- NSC contracted with Eutech for a computer system with customized software.
- The original commissioning date was 31 August 1999.
- Eutech failed to commission the system by the original deadline.
- NSC granted several extensions of time to Eutech.
- NSC sent a letter on 11 February 2000, expecting full system delivery within 3 months.
- Eutech submitted revised schedules with commissioning dates beyond the 3-month deadline.
- NSC terminated the contract on 21 March 2000 due to continuous delays.
5. Formal Citations
- National Skin Centre (Singapore) Pte Ltd v Eutech Cybernetics Pte Ltd, Suit 271/2000, [2001] SGHC 369
6. Timeline
Date | Event |
---|---|
Closed tender called by NSC | |
Meeting between NSC and Eutech representatives | |
Email from Prof Goh to Yadu regarding discount clause | |
Contract signed between NSC and Eutech | |
Prototyping stage commenced | |
Target date for Design Prototype Sign-off | |
NSC personnel trip to view Filenet Imaging System | |
Data migration and paper conversion commenced | |
Customization and integration stage commenced | |
Eutech proposed to implement DSC system first | |
Training commenced | |
NSC personnel trip to MSKCC | |
Target date for installation of application software | |
Installation tests commenced | |
Yadu confirmed agreement to pay for Y2K upgrade | |
Target date for System Live | |
System performance tests commenced | |
Original target date for commissioning of the System | |
Target date for completion of medical records and case notes conversion | |
Eutech proposed to install and run application software at both DSC and NSC servers | |
Eutech revised schedule, commissioning date set to 2000-06-20 | |
Yadu complained about work beyond contract scope | |
Partial DSC system installed | |
Sumeet took over project management | |
Top level meeting to review progress | |
Eutech submitted new schedule, commissioning date set to 2000-08-08 | |
NSC sent letter expecting full system delivery within 3 months | |
NSC informed Eutech orally that it would monitor progress over the next 2 months | |
Eutech submitted implementation plan, commissioning date set to 2000-07-28 | |
Eutech submitted implementation plan, commissioning date set to 2000-07-28 | |
NSC terminated the Contract | |
NSC called on the bankers guarantee |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that Eutech was in breach of contract for failing to commission the system by the agreed-upon date.
- Category: Substantive
- Sub-Issues:
- Failure to meet stipulated target dates
- Failure to commission the system
- Wrongful Termination
- Outcome: The court held that NSC validly terminated the contract after giving Eutech reasonable notice and opportunity to remedy the breach.
- Category: Substantive
- Sub-Issues:
- Validity of termination notice
- Reasonableness of notice period
- Time of the Essence
- Outcome: The court determined that while NSC initially waived the 'time is of the essence' clause, it validly reinstated it by giving reasonable notice to Eutech.
- Category: Substantive
- Sub-Issues:
- Waiver of time of the essence clause
- Reinstatement of time of the essence clause
8. Remedies Sought
- Monetary Damages
- Declaration of Liability
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Commercial Litigation
- Technology Contracts
11. Industries
- Healthcare
- Information Technology
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Charles Rickards Ltd v Oppenhaim | English Court of Appeal | Yes | [1950] 1 KB 616 | England and Wales | Cited for the principle that when time is of the essence in a contract, and one party waives that condition, they can reinstate it by giving reasonable notice. |
Stickney v Keeble | N/A | No | [1915] AC 386 | N/A | Cited regarding the factors to consider when determining whether a time limit is reasonable. |
Etablissements Chainbaux S.A.R.L. v Harbourmaster, Ltd | N/A | Yes | [1955] 1 Ll.LR 303 | N/A | Cited for the principle that a party who has waived the 'time is of the essence' clause must give reasonable notice to reinstate it, and for the circumstances under which a party can terminate a contract before the deadline. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Commissioning
- Implementation Plan
- Stipulated Target Dates
- Prototype
- Y2K Compliance
- Gap Analysis
- SWi system
- Copernicus system
- Design Prototype Sign-off
15.2 Keywords
- contract
- breach
- computer system
- software
- commissioning
- termination
- time of the essence
- national skin centre
- eutech
17. Areas of Law
Area Name | Relevance Score |
---|---|
Breach of Contract | 90 |
Contract Law | 85 |
Contracts | 80 |
Computer System Contract | 70 |
Software Contract | 65 |
Commissioning Contract | 50 |
Summary Judgement | 30 |
Damages | 30 |
16. Subjects
- Contract Law
- Information Technology
- Commercial Dispute