Shia Kian Eng v Nakano Singapore: Construction Dispute over Plastering Works and Wrongful Termination

In a civil suit before the High Court of Singapore on 03 April 2001, Shia Kian Eng (trading as Forest Contractors) sued Nakano Singapore (Pte) Ltd for non-payment, under-payment, and damages related to construction work at the Woodsvale Executive Condominium. Nakano counter-sued for damages, alleging repudiation by Forest. The court, presided over by Judith Prakash J, found that Nakano had wrongfully terminated Forest's contract and awarded Shia Kian Eng $942,992.20 after setting off Nakano's counterclaim for rectification costs.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Judgment for Plaintiff

1.3 Case Type

Civil

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

Construction dispute between Shia Kian Eng and Nakano Singapore over payment for plastering works and wrongful termination. Judgment for Shia Kian Eng.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Shia Kian Eng (trading as Forest Contractors)PlaintiffIndividualJudgment for PlaintiffPartialGeorge Tan, Monica Neo
Nakano Singapore (Pte) LtdDefendantCorporationCounterclaim Allowed in PartPartialThio Ying Ying, Lim Kwee Huat, Cheong Aik Hock

3. Judges

Judge NameTitleDelivered Judgment
Judith PrakashJudgeYes

4. Counsels

Counsel NameOrganization
George TanChan Tan & Partners
Monica NeoChan Tan & Partners
Thio Ying YingKelvin Chia Partnership
Lim Kwee HuatKelvin Chia Partnership
Cheong Aik HockKelvin Chia Partnership

4. Facts

  1. Forest Contractors was subcontracted by Nakano Singapore for plastering works at Woodsvale Executive Condominium.
  2. Disputes arose over payment for work done, variation orders, and alleged defective workmanship.
  3. Nakano terminated Forest's contract, claiming repudiation due to delays and defective work.
  4. Forest sued for non-payment, under-payment, and damages for wrongful termination.
  5. Nakano counter-sued for damages, claiming additional expenses to complete the works and rectify defects.
  6. The court found that Nakano wrongfully terminated Forest's contract.
  7. The court found that the defects in the plastering work were the result of poor workmanship on the part of Forest.

5. Formal Citations

  1. Shia Kian Eng (trading as Forest Contractors) v Nakano Singapore (Pte) Ltd, Suit 600245/2000, [2001] SGHC 68

6. Timeline

DateEvent
Relationship between Forest Contractors and Nakano Singapore started
Block wall and external wall plastering works commenced
Purchase Order for block and external plastering works signed by Shia Kian Eng
Internal wall plastering works commenced
Nakano Singapore issued Termination Warning to Forest Contractors
Nakano Singapore terminated Forest Contractors' plastering works
SETSCO Services commissioned to investigate plaster defects
Nakano Singapore filed re-re-re-amended defence and counterclaim
Judgment issued by the High Court

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that Nakano wrongfully terminated the contract with Forest. The court also found that Forest's workmanship was defective.
    • Category: Substantive
    • Sub-Issues:
      • Wrongful Termination
      • Defective Workmanship
      • Failure to Complete
    • Related Cases:
      • [1998] 3 SLR 871
  2. Contract Interpretation
    • Outcome: The court held that the sub-contracts were partly in writing and partly oral, comprising the quotations and original Purchase Orders signed after commencing work.
    • Category: Substantive
    • Sub-Issues:
      • Incorporation of Terms
      • Parol Evidence Rule

8. Remedies Sought

  1. Monetary Damages
  2. Payment for Work Done

9. Cause of Actions

  • Breach of Contract
  • Wrongful Termination

10. Practice Areas

  • Construction Dispute
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
San International Pte Ltd v Keppel Engineering Pte LtdCourt of AppealYes[1998] 3 SLR 871SingaporeCited for the principle that a defaulting party repudiates a contract when they indicate an inability to perform their obligations in a material respect.
Trollope & Colls Ltd. v Atomic Power Construction LtdN/ANo[1962] 3 All ER 1035N/ACited regarding the retrospective effect of contracts, but distinguished based on differing circumstances.
Felton v WharrieN/AYes[1906] Hudsons BC 4th ed Vol 2 p 398N/ACited for the principle that delay to works does not amount to repudiation unless it shows the contractor is unable or has no intention of proceeding with the works.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Plastering
  • Sub-contract
  • Termination
  • Repudiation
  • Defective Workmanship
  • Variation Order
  • Smartplas
  • Debonding
  • Rectification

15.2 Keywords

  • construction
  • contract
  • plastering
  • termination
  • Singapore

16. Subjects

  • Construction Dispute
  • Contract Law
  • Termination of Contract

17. Areas of Law

  • Construction Law
  • Contract Law
  • Civil Procedure