Hi-Amp Engineering v Technicdelta: Labour Supply Contract Dispute for MRT Stations
Hi-Amp Engineering Pte Ltd sued Technicdelta Electrical Engineering Pte Ltd in the High Court of Singapore, alleging breach of contract related to a labour supply agreement for electrical installation works at the Boon Keng and Potong Pasir MRT stations. Hi-Amp claimed outstanding payments for progress claims, extended labour, and additional works. Technicdelta counterclaimed for overpayment and damages. The court, presided over by MPH Rubin J, ruled in favor of Hi-Amp, awarding $155,235.47 for progress claims and $206,672.65 for variation works, dismissing Technicdelta's counterclaim.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Judgment for Plaintiff
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Hi-Amp Engineering sued Technicdelta Electrical for breach of contract regarding electrical installation work at MRT stations. The court ruled in favor of Hi-Amp, awarding damages.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Hi-Amp Engineering Pte Ltd | Plaintiff | Corporation | Judgment for Plaintiff | Won | |
Technicdelta Electrical Engineering Pte Ltd | Defendant | Corporation | Counterclaim Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
MPH Rubin | Judge | Yes |
4. Counsels
4. Facts
- Hi-Amp Engineering was contracted by Technicdelta to provide labour for electrical installation at Boon Keng and Potong Pasir MRT stations.
- The Hi-Amp contract was for a fixed sum of $762,984.00.
- Hi-Amp claimed that Technicdelta failed to make payments for progress, extended labour, and additional works.
- Technicdelta counterclaimed, alleging overpayment and breach of contract by Hi-Amp.
- The original completion date was December 2001, but the project extended into 2002.
- Hi-Amp alleged that delays were due to lack of materials and instructions from Technicdelta and the main contractor.
5. Formal Citations
- Hi-Amp Engineering Pte Ltd v Technicdelta Electrical Engineering Pte Ltd, Suit 972/2002/M, [2003] SGHC 316
6. Timeline
Date | Event |
---|---|
AMEC awarded a sub-contract to Technicdelta for electrical installation services. | |
Technicdelta awarded a labour supply sub-contract to Hi-Amp Engineering. | |
Hi-Amp Engineering commenced work on the project. | |
Original contract period ended. | |
Hi-Amp Engineering received a copy of the AMEC contract. | |
Boon Keng station achieved Temporary Occupation Permit. | |
Hi-Amp Engineering stopped work on the project. | |
Writ issued. | |
Judgment reserved. |
7. Legal Issues
- Breach of Contract
- Outcome: The court found the defendant breached the contract by failing to make due payments for work completed and variations.
- Category: Substantive
- Sub-Issues:
- Failure to make progress payments
- Disputes over variation works
- Extension of time claims
- Incorporation of Main Contract Terms into Subcontract
- Outcome: The court held that the terms of the main contract were not fully incorporated into the sub-contract due to lack of evidence that the plaintiff had sight of the main contract.
- Category: Substantive
- Related Cases:
- [1999] 3 SLR 667
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
- Quantum Meruit
10. Practice Areas
- Commercial Litigation
- Construction Disputes
11. Industries
- Construction
- Transportation
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Jurong Engineering Ltd v Paccan Building Technology Pte Ltd | Court of Appeal | Yes | [1999] 3 SLR 667 | Singapore | Cited regarding the incorporation of general conditions of a main contract into a sub-contract. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Labour Supply Contract
- Progress Claims
- Variation Works
- Extension of Time
- Free Issue Materials
- Back-to-Back Contract
- MRT Stations
15.2 Keywords
- contract
- construction
- electrical
- MRT
- Singapore
- litigation
17. Areas of Law
Area Name | Relevance Score |
---|---|
Contract Law | 80 |
Breach of Contract | 75 |
Construction Contracts | 65 |
Construction Law | 60 |
Commercial Disputes | 50 |
Civil Procedure | 30 |
Electrical Engineering | 25 |
16. Subjects
- Contract Dispute
- Construction Contract
- Sub-Contracting