Schindler Lifts v Paya Ubi: Novation, 'Pay When Paid' Clauses & Defective Work in Construction Sub-Contracts
In a suit before the High Court of Singapore, Schindler Lifts (Singapore) Pte Ltd sued Paya Ubi Industrial Park Pte Ltd and Tekken Corporation regarding a sub-contract for lift installation in the Paya Ubi Industrial Park project. Schindler claimed against Paya Ubi based on an implied novation and, alternatively, against Tekken for sums due under the sub-contract. Tekken disputed the claim, citing conditions precedent and a 'pay when paid' clause. The court dismissed Schindler's claim against Paya Ubi, finding no novation, but ruled in favor of Schindler against Tekken for certain amounts due under the Final Certificate, adjusting deductions for alleged non-performance and defective works. Tekken's counterclaim against Paya Ubi was partially upheld, with the court disallowing certain deductions made by the Architect.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Judgment for Schindler Lifts against Tekken Corporation in part; Schindler Lifts' claim against Paya Ubi Industrial Park dismissed.
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Schindler Lifts sues Paya Ubi and Tekken over a lift installation sub-contract dispute. The court addresses novation, 'pay when paid' clauses, and deductions for defective work.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Schindler Lifts (Singapore) Pte Ltd | Plaintiff | Corporation | Claim against Paya Ubi Industrial Park dismissed | Lost | |
Paya Ubi Industrial Park Pte Ltd | Defendant | Corporation | Claim against Paya Ubi Industrial Park dismissed | Won | |
Tekken Corporation | Defendant | Corporation | Claim against Tekken Corporation allowed in part | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Judith Prakash | Judge | Yes |
4. Counsels
4. Facts
- Paya Ubi appointed Tekken as the main contractor for the Paya Ubi Industrial Park project.
- Schindler was the nominated sub-contractor for lift installation.
- Disputes arose between Paya Ubi and Tekken, leading to a Settlement Agreement where Tekken ceased work.
- No formal novation agreement was signed between Tekken, Paya Ubi, and Schindler.
- The Architect issued a Final Certificate certifying deductions for omitted work and alleged non-performance/defective works.
- Schindler commenced action to recover retention moneys and amounts due for variations/outstanding works.
- Tekken assigned the performance bond that Schindler had provided to Tekken to Paya Ubi pursuant to the terms of the Sub-Contract.
5. Formal Citations
- Schindler Lifts (Singapore) Pte Ltd v Paya Ubi Industrial Park Pte Ltd and Another, Suit 457/2002, [2004] SGHC 34
6. Timeline
Date | Event |
---|---|
Tekken's letter of award to Schindler | |
Sub-Contract between Tekken and Schindler made | |
Settlement Agreement made between Tekken and Paya Ubi | |
Completion certificate for the project issued by the Architect | |
First temporary occupation permit obtained | |
Tekken and Schindler acknowledged pending novation negotiations | |
Second temporary occupation permit obtained | |
Paya Ubi shut down the power supply to the lift motor room for blocks C and D | |
Alpha Engineering Consultant informed Schindler that all batteries provided should be fit for their purpose | |
Schindler commenced action against Tekken and Paya Ubi | |
Date of the issue of the amended writ | |
Final Certificate issued | |
Trial date | |
Judgment reserved |
7. Legal Issues
- Implied Novation
- Outcome: The court held that there was no implied novation of the Sub-Contract between Schindler and Tekken.
- Category: Substantive
- "Pay When Paid" Clause
- Outcome: The court found that the 'pay when paid' provision in the Sub-Contract was an integral part of the agreement and applied to the release of retention moneys.
- Category: Substantive
- Deductions for Defective Work
- Outcome: The court determined that the Architect was only entitled to deduct a portion of the amount claimed for defective works, finding the original deduction excessive.
- Category: Substantive
8. Remedies Sought
- Monetary Damages
- Declaration
9. Cause of Actions
- Breach of Contract
- Recovery of Debt
10. Practice Areas
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
A Building Contract Dictionary | N/A | Yes | A Building Contract Dictionary (2nd Ed, 1990) | N/A | Cited for the definition of 'defective work' in the context of standard forms of building contract. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Nominated Sub-Contractor
- Novation
- Retention Moneys
- Final Certificate
- Pay When Paid Clause
- Defective Work
- Maintenance Period
- Settlement Agreement
- Architect's Certificate
- ARD Batteries
15.2 Keywords
- Schindler Lifts
- Paya Ubi
- Tekken
- Construction Law
- Subcontract
- Novation
- Retention Monies
- Defective Work
- Singapore High Court
17. Areas of Law
Area Name | Relevance Score |
---|---|
Construction Law | 90 |
Sub-contracts | 80 |
Novation | 70 |
Breach of Contract | 70 |
Building and Construction Contracts | 70 |
Contract Law | 70 |
Pay when paid | 60 |
Arbitration | 30 |
16. Subjects
- Construction Dispute
- Contract Law
- Sub-contracts
- Building and Construction Law