Panwah Steel v Koh Brothers: Contract Interpretation & Damages for Failure to Deliver Steel Rebars

Panwah Steel Pte Ltd sued Koh Brothers Building & Civil Engineering Contractor (Pte) Ltd in the High Court of Singapore, before Woo Bih Li J, on 27 December 2005, for $1,447,833.83 for the supply of reinforcing steel bars. Koh Brothers counterclaimed for Panwah's failure to deliver the balance of the contractual quantity. The court found that the contract was not 'project-specific' and interpreted the '-10% tolerance' provision. The court granted judgment to Koh Brothers for $70,014.39 with interest.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Judgment for Koh Brothers for $70,014.39 with interest.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Panwah Steel sued Koh Brothers for payment; Koh Brothers counterclaimed for failure to deliver steel rebars. The court addressed contract interpretation and damages.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Panwah Steel Pte LtdPlaintiffCorporationClaim DismissedLost
Koh Brothers Building & Civil Engineering Contractor (Pte) LtdDefendantCorporationCounterclaim AllowedWon

3. Judges

Judge NameTitleDelivered Judgment
Woo Bih LiJudgeYes

4. Counsels

4. Facts

  1. Panwah Steel agreed to supply 39,000mt of rebars to Koh Brothers under an agreement dated 26 April 2002.
  2. The agreement included a '-10% tolerance' provision regarding the quantity of rebars to be delivered.
  3. Panwah Steel entered into a contract with Burwill Trading to obtain the rebars.
  4. Burwill Trading declined to deliver the balance of the rebars to Panwah Steel.
  5. Panwah Steel did not deliver the full contractual quantity of rebars to Koh Brothers.
  6. Koh Brothers claimed damages for Panwah's omission to deliver 8,126.459mt of rebars.
  7. Koh Brothers notified Panwah that it would be obtaining rebars from alternative suppliers on 7 July 2004.

5. Formal Citations

  1. Panwah Steel Pte Ltd v Koh Brothers Building & Civil Engineering Contractor (Pte) Ltd, Suit 746/2004, [2005] SGHC 235

6. Timeline

DateEvent
Agreement between Panwah and Koh Brothers dated
Agreement between Panwah and Burwill Trading Pte Ltd dated
KB Agreement signed by Panwah
Koh Brothers notified Panwah that it would be obtaining rebars from alternative suppliers
Counterclaim date
Judgment reserved

7. Legal Issues

  1. Interpretation of Contractual Terms
    • Outcome: The court held that the contract was not 'project-specific' and interpreted the '-10% tolerance' provision to be at the option of both buyer and seller.
    • Category: Substantive
    • Sub-Issues:
      • Interpretation of minus 10% tolerance provision
      • Whether agreement was project-specific
    • Related Cases:
      • [2002] 2 SLR 308
      • [1971] 1 WLR 1381
      • [1976] 1 WLR 989
      • [1997] AC 749
      • [2002] 2 SLR 213
      • [1970] AC 583
      • [2004] SGHC 267
      • [2001] 2 SLR 458
      • [1918] 1 KB 592
      • [1995] EMLR 472
  2. Remoteness of Damages
    • Outcome: The court held that the damages claimed by Koh Brothers were not too remote.
    • Category: Substantive
    • Related Cases:
      • [1949] 2 KB 528

8. Remedies Sought

  1. Monetary Damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Litigation
  • Construction Contracts

11. Industries

  • Construction
  • Steel Industry

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
United Lifestyle Holdings Pte Ltd v Oakwell Engineering LtdHigh CourtYes[2002] 2 SLR 308SingaporeCited for principles regarding the interpretation of documents and the imposition of an implied term.
Prenn v SimmondsN/AYes[1971] 1 WLR 1381N/ACited for principles regarding the interpretation of documents and the imposition of an implied term.
Reardon Smith Line Ltd v Yngvar Hansen-TangenN/AYes[1976] 1 WLR 989N/ACited for principles regarding the interpretation of documents and the imposition of an implied term.
Mannai Investment Co Ltd v Eagle Star Life Assurance Co LtdN/AYes[1997] AC 749N/ACited for principles regarding the interpretation of documents and the imposition of an implied term.
Tan Hock Keng v L & M Group Investments LtdN/AYes[2002] 2 SLR 213SingaporeCited for principles regarding the interpretation of documents and the imposition of an implied term.
James Miller & Partners Ltd v Whitworth Street Estates (Manchester) LtdN/AYes[1970] AC 583N/ACited for the principle that subsequent conduct is not admissible as an aid to construction of a contract.
Telestop Pte Ltd v Telecom Equipment Pte LtdHigh CourtYes[2004] SGHC 267SingaporeCited for the principles regarding the implication of terms into a written contract.
Hiap Hong & Co Pte Ltd v Hong Huat Development Co (Pte) LtdCourt of AppealYes[2001] 2 SLR 458SingaporeCited for the relationship between the 'business efficacy' and 'officious bystander' tests for implying terms.
Reigate v Union Manufacturing Company (Ramsbottom), LimitedN/AYes[1918] 1 KB 592N/ACited for the 'officious bystander' test for implying terms.
Phillips Electronique Grand Public SA v British Sky Broadcasting LimitedN/AYes[1995] EMLR 472N/ACited for the principle that an implied term must be capable of clear expression and must not contradict any express term of the contract.
In Re An Arbitration between Thornett and Fehr and Yuills, LimitedN/AYes[1921] 1 KB 219N/ACited regarding the interpretation of tolerance provisions in contracts for the sale of goods.
Victoria Laundry (Windsor) Ld v Newman Industries LdN/AYes[1949] 2 KB 528N/ACited for the principle of remoteness of damages in contract law.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Rebars
  • Tolerance provision
  • Project-specific
  • Construction Material Prices
  • Construction Works

15.2 Keywords

  • Contract
  • Steel
  • Rebars
  • Damages
  • Construction
  • Singapore
  • Judgment

17. Areas of Law

16. Subjects

  • Contract Law
  • Construction Law
  • Sale of Goods