GIB Automation v Deluge Fire Protection: Sub-Contract Terms & Breach
GIB Automation Pte Ltd sued Deluge Fire Protection (SEA) Pte Ltd in the High Court of Singapore, alleging breach of contract related to a sub-contract for a fire protection system in the Marina Line MRT project. The court, Sundaresh Menon JC presiding, found that Deluge wrongfully terminated the sub-contract. The court dismissed GIB Automation's claims regarding the Changi Prison Cluster “A” Project and miscellaneous claims. Interlocutory judgment was entered in favor of GIB Automation, with damages to be assessed.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Interlocutory judgment entered in favor of the plaintiff for wrongful termination, with damages to be assessed.
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
GIB Automation sues Deluge Fire Protection for breach of contract. The court found Deluge wrongfully terminated the sub-contract.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Deluge Fire Protection (S.E.A.) Pte Ltd | Defendant | Corporation | Interlocutory Judgment Against | Lost | |
GIB Automation Pte Ltd | Plaintiff | Corporation | Interlocutory judgment entered in favor of the plaintiff for wrongful termination, with damages to be assessed. | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Sundaresh Menon | Judicial Commissioner | Yes |
4. Counsels
4. Facts
- The defendant was the main contractor for the supply, installation, testing, commissioning and maintenance of a fire protection system for the Stage 1 Marina Line MRT project.
- The defendant sub-contracted a substantial portion of the work to the plaintiff.
- The plaintiff was to design, supply, test, commission and maintain the fire alarm system for the project.
- A dispute arose as to whether the specifications had changed so as to result in the contract price having increased.
- The plaintiff refused to supply certain items towards the end of 2004 and in early 2005, alleging that its obligation to deliver was contingent upon the defendant issuing a letter of credit.
- The defendant denied that payment was to be made via letter of credit and terminated the agreement.
- The defendant was aware that a very substantial extension of time to complete the work had been granted by the Land Transport Authority but did not inform the plaintiff.
5. Formal Citations
- GIB Automation Pte Ltd v Deluge Fire Protection (SEA) Pte Ltd, Suit 360/2005, [2007] SGHC 48
6. Timeline
Date | Event |
---|---|
Letter of award for Changi Prison contract was dated. | |
Plaintiff submitted a letter of offer. | |
Meeting held between the representatives of the parties. | |
Plaintiff wrote to the defendant setting out certain matters. | |
Email regarding preliminary quote of increase in costs. | |
Email regarding preliminary quote of increase in costs. | |
Defendant wrote to the plaintiff a letter of award. | |
Issue raised again on 28 October 2002 at about the time the plaintiff was countersigning the letter of award. | |
Plaintiff wrote seeking to clarify or confirm an understanding as to the increase. | |
Defendant's project manager handed a copy of a draft delivery schedule to plaintiff's representative. | |
Plaintiff required a letter of credit for a sum of $118,793.29. | |
Defendant responded to say that the project “is based on a payment term of back-to-back basic (sic)”. | |
Defendant instructed plaintiff in writing that they are in ‘default of contract’. | |
Defendant instructed plaintiff in writing that they are in ‘default of contract’. | |
Plaintiff sent letter to defendant regarding terms of contract. | |
Defendant terminated the sub-contract. | |
Mr Cheo filed an affidavit in which he exhibited a letter from an entity related to EST. | |
Judgment reserved. |
7. Legal Issues
- Incorporation of main contract terms into sub-contracts
- Outcome: The court determined the extent to which the main contract terms were incorporated into the sub-contract, based on the factual matrix and the express terms of the sub-contract.
- Category: Substantive
- Sub-Issues:
- Construction of back-to-back provision
- Related Cases:
- [2003] SGHC 316
- [2003] SGHC 53
- [2005] SGCA 59
- Breach of Contract
- Outcome: The court found that the defendant wrongfully terminated the sub-contract.
- Category: Substantive
- Sub-Issues:
- Repudiatory breach
- Wrongful termination
- Related Cases:
- [1962] 2 QB 26
- [2004] 3 SLR 288
- [1980] 1 WLR 277
- Mitigation of Damage
- Outcome: The court found that the plaintiff failed to mitigate its damages.
- Category: Substantive
- Sub-Issues:
- Duty to mitigate losses
- Related Cases:
- [1912] AC 673
- Admissibility of Evidence
- Outcome: The court addressed the issue of whether the truth of the contents of a document accepted as authentic still needed to be proved.
- Category: Procedural
- Sub-Issues:
- Hearsay
- Proof of contents of documents
- Related Cases:
- [2006] 3 SLR 769
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Multi-Pak Singapore Pte Ltd (In Receivership) v Intraco Ltd and others | Singapore High Court | Yes | [1992] 2 SLR 793 | Singapore | Cited for the principle that a court may not make findings on the basis of facts that are not pleaded. |
Jet Holding Ltd and others v Cooper Cameron (Singapore) Pte Ltd and Another and other Appeals | Court of Appeal | Yes | [2006] 3 SLR 769 | Singapore | Cited for the principle that even if a document is accepted as authentic, the truth of its contents may not be proved by the document itself because of the hearsay rule. |
Hi-Amp Engineering Pte Ltd v Technicdelta Electrical Engineering Pte Ltd | Singapore High Court | Yes | [2003] SGHC 316 | Singapore | Cited regarding the interpretation of back-to-back clauses and the relevance of whether the sub-contractor had sight of the main contract. |
Lam Hong Leong Aluminium Pte Ltd v Lian Teck Huat Construction Pte Ltd and Another | Singapore High Court | Yes | [2003] SGHC 53 | Singapore | Cited regarding the interpretation of back-to-back clauses and the relevance of whether the sub-contractor had sight of the main contract. |
Spandeck Engineering (S) Pte Ltd v China Construction (South Pacific) Development Co Pte Ltd | Court of Appeal | Yes | [2005] SGCA 59 | Singapore | Cited regarding the interpretation of back-to-back clauses in sub-contracts. |
Choon Construction Pte Ltd v L&M Concrete Specialists Pte Ltd | Singapore High Court | Yes | [1999] SGHC 228 | Singapore | Cited regarding the approach to back-to-back provisions in construction contracts. |
Hong Kong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd | Queen's Bench | Yes | [1962] 2 QB 26 | England and Wales | Cited for the principle that a breach of contract entitles the innocent party to terminate the contract if the consequence of the breach deprives the innocent party of substantially the whole benefit which it was intended he should obtain. |
Jia Min Building Construction Pte Ltd v Ann Lee Pte Ltd | Singapore High Court | Yes | [2004] 3 SLR 288 | Singapore | Cited for the principle that until a contract has been brought to an end, its terms continue to apply and to enure to the benefit of both parties. |
Woodar Investment Development Ltd v Wimpey Construction UK Ltd | House of Lords | Yes | [1980] 1 WLR 277 | United Kingdom | Cited for the principle that where there is a genuine dispute as to the construction of a contract, the courts may be unwilling to hold that an expression of an intention by one party to carry out the contract only in accordance with his own erroneous interpretation of it amounts to a repudiation. |
British Westinghouse Electric and Manufacturing Co Ltd v Underground Electric Railway Co of London | House of Lords | Yes | [1912] AC 673 | United Kingdom | Cited for the principle that a party has a duty to mitigate its losses and prevents it from claiming such damages as may be avoided by reasonable steps. |
The Karting Club of Singapore v David Mak and others | Singapore High Court | Yes | [1992] 2 SLR 483 | Singapore | Cited for the principle that the power to award costs conferred on the High Court is completely unfettered. |
Tullio v Maoro | Court of Appeal | Yes | [1994] 2 SLR 489 | Singapore | Cited for the principles on which costs were to be awarded. |
Re Elgindata Ltd (No 2) | England and Wales Court of Appeal (Civil Division) | Yes | [1993] 1 All ER 232 | England and Wales | Cited for the principles on which costs were to be awarded. |
Baylis Baxter v Sabath | England and Wales High Court (Chancery Division) | Yes | [1958] 1 WLR 529 | England and Wales | Cited for the principle that where a party acts unethically, for example by relying on false evidence, he may be penalised in costs. |
Anex Electrical Co Ltd v Kingsland International Ltd | Hong Kong Court of Appeal | Yes | [1998] 1 HKLRD 947 | Hong Kong | Cited for the principle that the burden is upon the party seeking to be released from the implied undertaking not to use such documents for collateral purposes, to provide persuasive and cogent reasons to warrant the discharge of the implied undertaking. |
Jaya Sarana Engineering Pte Ltd v GIB Automation Pte Ltd | Singapore High Court | Yes | [2007] SGHC 49 | Singapore | Related case involving similar parties. |
13. Applicable Rules
Rule Name |
---|
Rules of the Supreme Court |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Supreme Court of Judicature Act | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Sub-contract
- Back-to-back provision
- Letter of credit
- Mitigation of damages
- Wrongful termination
- Main contract
- Letter of award
- Equipment delivery
- Fixed lump sum
- Variations
15.2 Keywords
- Sub-contract
- Breach of contract
- Construction law
- Wrongful termination
- Singapore
- High Court
17. Areas of Law
16. Subjects
- Construction Law
- Contract Law
- Civil Procedure