Robertson Quay Investment v Steen Consultants: Delay Damages & Interest
In Robertson Quay Investment Pte Ltd v Steen Consultants Pte Ltd, the Singapore Court of Appeal addressed an appeal by Robertson Quay Investment Pte Ltd (RQI) against a decision regarding damages awarded for delays in the construction of the Gallery Hotel. The primary legal issue was whether RQI was entitled to claim interest incurred on loans during the period of delay as damages, and from what date interest on the awarded damages should run. The Court dismissed RQI's appeal, finding that RQI failed to sufficiently prove it incurred additional interest as a result of the delay and upholding the decision that interest on damages should run from the date of service of the statement of claim.
1. Case Overview
1.1 Court
Court of Appeal1.2 Outcome
Appeal dismissed with costs.
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Singapore Court of Appeal addresses damages for construction delay, focusing on interest on loans and the Hadley v Baxendale rule.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Robertson Quay Investment Pte Ltd | Appellant | Corporation | Appeal dismissed with costs | Lost | Chou Sean Yu, Chua Sui Tong |
Steen Consultants Pte Ltd | Respondent | Corporation | Appeal dismissed | Won | Morris John |
Shahbaz Ahmad | Respondent | Individual | Appeal dismissed | Won | Morris John |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Chan Sek Keong | Chief Justice | No |
Andrew Phang Boon Leong | Justice of the Court of Appeal | Yes |
V K Rajah | Justice of the Court of Appeal | No |
4. Counsels
Counsel Name | Organization |
---|---|
Chou Sean Yu | WongPartnership |
Chua Sui Tong | WongPartnership |
Morris John | Drew & Napier LLC |
4. Facts
- RQI is the owner and developer of the Gallery Hotel.
- Steen Consultants was engaged by RQI to provide civil and structural engineering services for the construction of the Hotel.
- Shahbaz Ahmad was a director of Steen Consultants and the civil and structural engineer responsible for the Hotel’s structural works.
- The structural drawings of the Hotel were underdesigned.
- The respondents gave the building contractor the uncorrected 1996 version of the drawings instead.
- Structural deficiencies in the Hotel required additional remedial and strengthening works.
- The repairs delayed the completion of the Project by 101 days.
- RQI claimed interest on loans as damages due to the delay.
5. Formal Citations
- Robertson Quay Investment Pte Ltd v Steen Consultants Pte Ltd and Another, CA 36/2007, [2008] SGCA 8
6. Timeline
Date | Event |
---|---|
Structural drawings of the Hotel were done by Shahbaz. | |
Drawings were corrected and submitted to the relevant building authorities. | |
Facility Agreement signed between RQI and UOB. | |
Original completion date of the Project. | |
Steen Consultants undertook to pay for the costs of the repairs in a letter to RQI. | |
Actual completion date of the Project after delay. | |
Originally scheduled date for the issuance of the temporary occupation permit for the Hotel. | |
Steen Consultants certified payment of a total sum of $597,893.35 to the contractor carrying out the repairs. | |
Temporary occupation permit for the Hotel was eventually issued. | |
Steen Consultants certified payment of a total sum of $597,893.35 to the contractor carrying out the repairs. | |
Repayment date for the Term Loan. | |
RQI filed its writ of summons against Steen Consultants and Goh. | |
RQI filed an amended writ of summons which added Shahbaz as a defendant. | |
Amended writ served on Steen Consultants. | |
Amended writ served on Shahbaz. | |
Statement of claim was filed and served. | |
Interlocutory judgment was entered by consent against the respondents. | |
Assistant registrar delivered oral judgment following an assessment of damages hearing. | |
Judgment reserved. |
7. Legal Issues
- Remoteness of Damage
- Outcome: The court found that additional interest incurred on construction loans as a result of a delay in the completion of a construction project is not too remote to be recoverable under the first limb of Hadley.
- Category: Substantive
- Related Cases:
- (1854) 9 Exch 341; 165 ER 145
- Proof of Damage
- Outcome: The court found that RQI failed to sufficiently prove it incurred additional interest as a result of the delay.
- Category: Substantive
- Date of Commencement of Interest
- Outcome: The court upheld the decision that interest on damages should run from the date of service of the statement of claim.
- Category: Procedural
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
- Negligence
10. Practice Areas
- Construction Law
- Commercial Litigation
11. Industries
- Construction
- Hospitality
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Hadley v Baxendale | Court of Exchequer | Yes | (1854) 9 Exch 341; 165 ER 145 | England and Wales | Established the rule for remoteness of damage in contract law, central to determining recoverable losses. |
Robertson Quay Investment Pte Ltd v Steen Consultants Pte Ltd | High Court | Yes | [2007] SGHC 30 | Singapore | The trial judge's decision that is being appealed in the current judgment. |
Victoria Laundry (Windsor) Ld v Newman Industries Ld | Court of Appeal | Yes | [1949] 2 KB 528 | England and Wales | Reformulated the rule in Hadley v Baxendale, providing a modern exposition of remoteness in contract. |
Chaplin v Hicks | Court of Appeal | Yes | [1911] 2 KB 786 | England and Wales | Addressed the issue of certainty in proving damages, emphasizing that difficulty in assessment does not relieve the wrongdoer of liability. |
Biggin & Co Ld v Permanite, Ld | High Court | Yes | [1951] 1 KB 422 | England and Wales | Outlined the approach to proof of damage, stating that the court expects precise evidence where obtainable, and does its best where it is not. |
Raffles Town Club Pte Ltd v Tan Chin Seng | High Court | Yes | [2005] 4 SLR 351 | Singapore | Cited Chaplin v Hicks and Biggin & Co Ld v Permanite, Ld with approval and emphasized the observation by Devlin J. |
Koufos v C Czarnikow Ltd | House of Lords | Yes | [1969] 1 AC 350 | United Kingdom | Clarified the degree of probability required for remoteness under Hadley v Baxendale, rejecting the phrase 'on the cards'. |
CHS CPO GmbH v Vikas Goel | High Court | Yes | [2005] 3 SLR 202 | Singapore | Summarized the law on remoteness of damage in contract, distinguishing between imputed and actual knowledge. |
Jet Holding Ltd v Cooper Cameron (Singapore) Pte Ltd | Court of Appeal | Yes | [2006] 3 SLR 769 | Singapore | Reaffirmed that the principles established in Hadley v Baxendale continue to be the law in Singapore. |
Tang Kin Hwa v Traditional Chinese Medicine Practitioners Board | High Court | Yes | [2005] 4 SLR 604 | Singapore | Discussed the dangers of focusing on the form of words as opposed to their substance in the test for remoteness of damage in contract law. |
Aruna Mills Ltd v Dhanrajmal Gobindram | High Court | Yes | [1968] 1 QB 655 | England and Wales | Summarized the effect of the decision of the House in Koufos v C Czarnikow Ltd. |
Sempra Metals Ltd v Inland Revenue Commissioners | House of Lords | Yes | [2007] 3 WLR 354 | United Kingdom | Endorsed the rule in Hadley and distinguished between what is to be taken as within contracting parties’ reasonable contemplation and what may be said to be reasonably foreseeable for the purpose of a claim for purely tortious damages. |
Jackson v Royal Bank of Scotland plc | House of Lords | Yes | [2005] 1 WLR 377 | United Kingdom | Endorsed the rule in Hadley. |
The Achilleas | High Court | Yes | [2007] 1 Lloyd’s Rep 19 | England and Wales | Case commented that the rule in Hadley should be treated as a composite whole and viewed as stating a single principle. |
The Pegase | High Court | Yes | [1981] 1 Lloyd’s Rep 175 | England and Wales | Case commented that the rule in Hadley should be treated as a composite whole and viewed as stating a single principle. |
H Parsons (Livestock) Ltd v Uttley Ingham & Co Ltd | Court of Appeal | Yes | [1978] QB 791 | England and Wales | Case where Lord Denning MR sought to apply the tortious rules on remoteness to a contractual claim for physical injury or damage. |
Kienzle v Stringer | Court of Appeal | Yes | (1981) 130 DLR (3d) 272 | Canada | Case where Lord Denning MR sought to apply the tortious rules on remoteness to a contractual claim for physical injury or damage. |
Brown v KMR Services Ltd | Court of Appeal | Yes | [1995] 4 All ER 598 | England and Wales | Case where Lord Denning MR sought to apply the tortious rules on remoteness to a contractual claim for physical injury or damage. |
McElroy Milne v Commercial Electronics Ltd | Court of Appeal | Yes | [1993] 1 NZLR 39 | New Zealand | A New Zealand Court of Appeal decision that questioned the viability of Hadley v Baxendale. |
Senate Electrical Wholesalers Ltd v Alcatel Submarine Networks Ltd | Court of Appeal | Yes | [1999] 2 Lloyd’s Rep 423 | England and Wales | The plaintiff was denied recovery of damages for breach of contractual warranties as it failed to prove the relevance of the quantum of damages which it was claiming. |
Roanoke Hospital Association v Doyle and Russell, Inc | Supreme Court | Yes | 214 SE 2d 155 (1975) | Virginia, United States | Allowed recovery of added interest costs during the construction period arising from the longer term of borrowing necessitated by the contractor’s unexcused delay. |
Herbert & Brooner Construction Co v Golden | Court of Appeals | Yes | 499 SW 2d 541 (1973) | Missouri, United States | Allowed recovery of the extension fee and the interest paid for the extended construction period, given that the precise amounts paid by way of such extension fee and interest were clearly established. |
Overseas Tankship (UK) Ltd v Morts Dock & Engineering Co (The Wagon Mound) | Privy Council | Yes | [1961] AC 388 | United Kingdom | Case that established the term “reasonable foreseeability” in the law of tort. |
Sunny Metal & Engineering Pte Ltd v Ng Khim Ming Eric | Court of Appeal | Yes | [2007] 3 SLR 782 | Singapore | Recognized that the concept of remoteness of damages is essentially a necessary limitation imposed by the law to protect the contract-breaker from infinite damages. |
Dunlop Pneumatic Tyre Company, Limited v New Garage and Motor Company, Limited | House of Lords | Yes | [1915] AC 79 | United Kingdom | Classic statement of the applicable principles in this particular area of contractual remedies. |
Friis v Casetech Trading Pte Ltd | High Court | Yes | [2000] 3 SLR 590 | Singapore | Endorsed the principles that interest should commence to run from the moment the cause of action does accrue in respect of loss which also then accrues, and that the court may order interest to run from a date later than that at which the claimant’s loss accrued where there has been an unjustifiable delay on the part of the claimant in bringing his action to trial. |
Kaines (UK) Ltd v Osterreichische Warrenhandelsgesellshaft Austrowaren Gesellschaft mbH | Court of Appeal | Yes | [1993] 2 Lloyd’s Rep 1 | England and Wales | Case that illustrates the principle that interest was to run, not from the time when the breach occurred (and, hence, the cause of action accrued), but rather from the (later) time when the buyers were required to make payment for the substitute goods. |
MCST No 473 v De Beers Jewellery Pte Ltd | High Court | Yes | [2002] 2 SLR 1 | Singapore | Case that noted that s 12(1) of the Act is in pari materia with s 3(1) of the Law Reform (Miscellaneous Provisions) Act 1934 (c 41) (UK). |
Fidelity and Guaranty Insurance Underwriters, Inc v Allied Realty Company, Ltd | Supreme Court | Yes | 384 SE 2d 613 (1989) | Virginia, United States | Followed Roanoke Hospital Association. |
W M Foley Construction Corp v Bono | Circuit Court | Yes | 2006 WL 3604785 | Virginia, United States | Followed Roanoke Hospital Association. |
Elar Investments, Inc v Southwest Culvert Co, Inc | Court of Appeals | Yes | 676 P 2d 659 (1983) | Arizona, United States | Followed Roanoke Hospital Association. |
Multiplex Constructions Pty Ltd v Abgarus Pty Ltd | Supreme Court | Yes | (1992) 33 NSWLR 504 | New South Wales, Australia | Case concerned the validity of a liquidated damages clause and does not stand as direct authority that additional interest incurred on construction loans as a result of delays in construction projects is recoverable as direct damages under the first limb of Hadley. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Civil Law Act (Cap 43, 1999 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Period of Delay
- Shareholder Loans
- Bank Loans
- Capitalisation of Interest
- Remoteness of Damage
- Hadley v Baxendale
- Construction Loans
- Construction Project
15.2 Keywords
- construction delay
- damages
- interest on loans
- remoteness of damage
- Hadley v Baxendale
- Singapore Court of Appeal
16. Subjects
- Construction Dispute
- Contract Law
- Civil Procedure
- Damages
17. Areas of Law
- Building and Construction Law
- Contract Law
- Civil Procedure
- Damages