Comfort Resources v Alliance Concrete: Breach of Sand Supply Contract Dispute

In a consolidated suit before the High Court of Singapore on 2008-08-05, Comfort Resources Pte Ltd sued Alliance Concrete Singapore Pte Ltd for breach of contract, seeking payment for sand delivered and loss of profits due to under-ordering. Alliance Concrete counter-sued, alleging Comfort Resources failed to supply contracted quantities. The court found Alliance Concrete in repudiatory breach for under-ordering and late payments, awarding Comfort Resources $163,696.67 and interlocutory judgment for breach of contract, while dismissing Alliance Concrete's claim.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Judgment for Plaintiff (Comfort Resources); Defendant's (Alliance Concrete) claim dismissed.

1.3 Case Type

Civil

1.4 Judgment Type

Judgment reserved

1.5 Jurisdiction

Singapore

1.6 Description

Singapore High Court case involving Comfort Resources and Alliance Concrete over a sand supply contract, focusing on breach and repudiation claims.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Comfort Resources Pte LtdPlaintiffCorporationJudgment for PlaintiffWonJohn Seow, Lim Ming Yi
Alliance Concrete Singapore Pte LtdDefendant, PlaintiffCorporationClaim DismissedLostWinston Kwek, Eileen Lam

3. Judges

Judge NameTitleDelivered Judgment
Lai Siu ChiuJudgeYes

4. Counsels

Counsel NameOrganization
John SeowDrew & Napier LLC
Lim Ming YiDrew & Napier LLC
Winston KwekRajah & Tann LLP
Eileen LamRajah & Tann LLP

4. Facts

  1. Comfort Resources contracted to sell sand to Alliance Concrete.
  2. Alliance Concrete failed to make timely payments for sand deliveries.
  3. Alliance Concrete failed to order the minimum quantities of sand as stipulated in the contract.
  4. Alliance Concrete claimed Comfort Resources short-delivered sand.
  5. Comfort Resources stopped deliveries due to non-payment.
  6. Alliance Concrete purchased sand from another supplier, Lim Chye Heng Sand & Granite Pte Ltd.
  7. Alliance Concrete was contractually bound to order a minimum of 30,000 mt and a maximum of 50,000 mt from both Comfort and LCH every month.

5. Formal Citations

  1. Comfort Resources Pte Ltd v Alliance Concrete Singapore Pte Ltd and Another Suit, Suit 601/2006, 604/2006, [2008] SGHC 122

6. Timeline

DateEvent
Alliance Concrete sent a letter to Comfort Resources, evidencing a contract.
Comfort Resources countersigned the letter from Alliance Concrete, accepting the contract.
Contract period began.
Alliance Concrete failed to pay for deliveries made in May.
First meeting between Comfort Resources and Alliance Concrete.
Second meeting between Comfort Resources and Alliance Concrete.
Alliance Concrete paid the April 2006 invoices after the second meeting.
Comfort Resources stopped deliveries of sand to Alliance Concrete.
Alliance Concrete wrote to Comfort Resources alleging short-deliveries.
Alliance Concrete wrote to Comfort Resources alleging short-delivery of sand.
Comfort Resources sent a letter to Alliance Concrete demanding payment and threatening to treat the contract as repudiated.
Comfort Resources sent a letter to Alliance Concrete stating it considered Alliance as having repudiated the contract.
Alliance Concrete's solicitors sent a letter denying failure to make payments and alleging Comfort Resources was in repudiatory breach.
Both companies commenced proceedings.
Comfort Resources applied for summary judgment.
Alliance Concrete applied for judgment with damages to be assessed.
Alliance Concrete filed its first supplementary list of documents.
Alliance Concrete claimed that the rest of the F-10 forms for Toa Payoh and Queenstown plants for the period 1 August 2006 to 31 January 2007 and the F-10 forms for the other three plants for the period 1 February 2006 to 31 January 2007 were last in their possession before 1 May 2007.
Contract period ended.
Judgment reserved.

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that Alliance Concrete was in breach of contract due to repeated late payments and under-ordering of sand.
    • Category: Substantive
    • Sub-Issues:
      • Failure to make timely payment
      • Failure to order minimum quantities
  2. Repudiation
    • Outcome: The court determined that Alliance Concrete's actions constituted a repudiation of the contract, which Comfort Resources validly accepted.
    • Category: Substantive

8. Remedies Sought

  1. Monetary Damages
  2. Loss of Profits

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Decro-Wall International SA v Practitioners in Marketing LtdUK Court of AppealYes[1971] 2 All ER 216United KingdomCited to determine whether the breach by Alliance Concrete was fundamental enough to constitute repudiation of the contract, particularly in relation to late payments.
Brani Readymixed Pte Ltd v Yee Hong Pte LtdCourt of AppealYes[1995] 1 SLR 205SingaporeCited regarding whether a delay in payment entitles the seller to terminate the contract.
Kool Team Marketing v Pacific Sunwear Pte LtdHigh CourtYes[2000] 2 SLR 243SingaporeCited regarding whether a failure to make prompt payment allows the seller to stop supplying goods.
Maple Flock Company Ltd v Universal Furniture Products (Wembley) LimitedUK Court of AppealYes[1934] 1 KB 148United KingdomCited for the tests to determine whether a breach is fundamental and goes to the root of the contract, focusing on the ratio of the breach to the contract as a whole and the probability of repetition.
Browne v DunneN/AYes(1893) 6 R 67N/ACited regarding the rule that a party cannot raise an issue in submissions if it was not challenged during cross-examination.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Sale of Goods Act (Cap 393, 1999 Rev Ed)Singapore
Rules of Court (Cap 322, R 5, 2006 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Sand supply contract
  • Repudiatory breach
  • Short delivery
  • Under-ordering
  • Late payment
  • Liquidated damages
  • Force majeure
  • Contract quantity
  • Outstanding sum
  • Material Intake Record Book

15.2 Keywords

  • contract
  • breach
  • sand
  • supply
  • repudiation
  • payment
  • delivery
  • Comfort Resources
  • Alliance Concrete

16. Subjects

  • Contract Dispute
  • Sale of Goods
  • Breach of Contract
  • Repudiation

17. Areas of Law

  • Contract Law
  • Sale of Goods