In Hong Kiat Construction Pte Ltd v Ngiam Benjamin, the High Court of Singapore heard an appeal by Ngiam Benjamin against the Assistant Registrar's order to appoint Mr. Johnny Tan as the arbitrator in an ongoing arbitration with Hong Kiat Construction. The dispute arose from a construction contract for Ngiam's house, with Hong Kiat claiming $177,237.30 and Ngiam counter-claiming for $280,500. The initial arbitrator, Mr. Yang Yung Chong, had considered his appointment terminated due to delays. The court dismissed the appeal, finding that the arbitrator had terminated his own appointment and that there was no agreement between the parties to terminate the arbitration.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Appeal Dismissed
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Appeal regarding the appointment of an arbitrator in a construction dispute. The court dismissed the appeal, allowing the new arbitrator's appointment.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Hong Kiat Construction Pte Ltd | Plaintiff, Respondent | Corporation | Appointment of arbitrator allowed | Won | |
Ngiam Benjamin | Defendant, Appellant | Individual | Appeal Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Choo Han Teck | Judge | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Eugene Tan | Drew & Napier LLC |
Tan Chee Kiong | Seah Ong & Partners |
4. Facts
- Hong Kiat Construction was the builder for Ngiam Benjamin's house.
- A dispute arose between the parties regarding the construction contract.
- Hong Kiat Construction claimed $177,237.30 against Ngiam Benjamin.
- Ngiam Benjamin counter-claimed for $280,500.
- Mr. Yang Yung Chong was initially appointed as the sole arbitrator.
- Mr. Yang considered his appointment terminated due to delays in proceedings.
- The plaintiff applied to appoint a new arbitrator under the Arbitration Act.
5. Formal Citations
- Hong Kiat Construction Pte Ltd v Ngiam Benjamin, OS 1184/2008, RA 418/2008, [2009] SGHC 158
6. Timeline
Date | Event |
---|---|
Contract between Hong Kiat Construction and Ngiam Benjamin signed | |
Arbitration commenced by Hong Kiat Construction | |
Mr. Yang Yung Chong appointed sole arbitrator | |
Directions given by Mr. Yang for exchange of affidavits and submissions | |
Mr. Yang wrote to parties regarding compliance with directions | |
Plaintiff's solicitor requested more time from Mr. Yang | |
Mr. Yang inquired if the plaintiff was proceeding with the matter | |
Defendant expressed surprise that Mr. Yang still considered himself the arbitrator | |
Mr. Yang treated his appointment as terminated | |
Plaintiff applied to appoint a new arbitrator | |
Appeal dismissed |
7. Legal Issues
- Appointment of Arbitrator
- Outcome: The court dismissed the appeal, upholding the appointment of the new arbitrator.
- Category: Procedural
- Termination of Arbitration
- Outcome: The court held that the arbitrator had terminated his own appointment, not the parties by agreement.
- Category: Substantive
8. Remedies Sought
- Appointment of Arbitrator
- Monetary Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Arbitration
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
No cited cases |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Arbitration Act, Cap 10 (1985 Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Arbitration
- Arbitrator
- Construction Contract
- Termination of Appointment
- Singapore Institute of Architects Conditions of Contract
15.2 Keywords
- Arbitration
- Construction
- Singapore
- Appeal
- Arbitrator Appointment
17. Areas of Law
Area Name | Relevance Score |
---|---|
Arbitration | 90 |
Building and Construction Contracts | 80 |
Construction Law | 70 |
Breach of Contract | 60 |
Contract Law | 50 |
Civil Procedure | 30 |
Costs | 20 |
16. Subjects
- Arbitration
- Construction Dispute