Front Row v Daimler: Setting Aside Arbitration Award for Breach of Natural Justice

In Front Row Investment Holdings (Singapore) Pte Ltd v Daimler South East Asia Pte Ltd, the Singapore High Court allowed Front Row's application to set aside part of an arbitration award. The court found that the arbitrator breached the rule of natural justice by failing to consider all of Front Row's misrepresentation claims against Daimler. The court ordered that the counterclaim be tried afresh by a newly appointed arbitrator.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Application allowed; part of the award dealing with the counterclaim set aside.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Front Row's application to set aside an arbitration award against Daimler was allowed due to a breach of natural justice. The arbitrator failed to consider all misrepresentation claims.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Daimler South East Asia Pte LtdRespondent, ClaimantCorporationClaim Dismissed, Counterclaim AllowedLost
Front Row Investment Holdings (Singapore) Pte LtdApplicant, RespondentCorporationApplication allowed in partPartial

3. Judges

Judge NameTitleDelivered Judgment
Andrew AngJudgeYes

4. Counsels

4. Facts

  1. Front Row and Daimler entered into an agreement to jointly run a racing series.
  2. Front Row was responsible for financing the venture.
  3. Daimler was responsible for organizing the Asian Cup Series.
  4. Daimler was to ensure Buehler devoted 100% of his time to the series.
  5. Front Row purchased 35 SLK 55 cars for the racing series.
  6. Daimler only organized three races, which were not successful.
  7. Mercedes-AMG informed Front Row the cars were not made for actual racing.

5. Formal Citations

  1. Front Row Investment Holdings (Singapore) Pte Ltd v Daimler South East Asia Pte Ltd, Originating Summons No 1126 of 2009, [2010] SGHC 80

6. Timeline

DateEvent
Agreement signed between Front Row and Daimler
Mercedes-AMG letter received by Front Row
Daimler commenced arbitration proceedings against Front Row
Arbitration Award issued
Front Row filed originating summons
Decision Date

7. Legal Issues

  1. Breach of Natural Justice
    • Outcome: The court found that the arbitrator breached the rule of natural justice by failing to consider all of Front Row's misrepresentation claims.
    • Category: Procedural
    • Sub-Issues:
      • Failure to consider all submissions
      • Failure to give a fair hearing
  2. Misrepresentation
    • Outcome: The court did not rule on the merits of the misrepresentation claim but found that the arbitrator failed to consider all aspects of it.
    • Category: Substantive

8. Remedies Sought

  1. Setting aside part of the arbitration award
  2. Re-trial of the counterclaim by a newly appointed arbitrator

9. Cause of Actions

  • Misrepresentation

10. Practice Areas

  • Commercial Litigation
  • Arbitration

11. Industries

  • Automotive
  • Sports

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
John Holland Pty Ltd v Toyo Engineering Corp (Japan)High CourtYes[2001] 1 SLR(R) 443SingaporeCited for the test to establish a breach of natural justice in challenging an arbitration award.
Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte LtdCourt of AppealYes[2007] 3 SLR(R) 86SingaporeCited for the test to establish a breach of natural justice in challenging an arbitration award and the principles of natural justice.
Pacific Recreation Pte Ltd v SY Technology IncCourt of AppealYes[2008] 2 SLR(R) 491SingaporeCited for the principle that a court breaches natural justice if it decides a case on a basis not raised by the parties.
Koh Bros Building and Civil Engineering Contractor Pte Ltd v Scotts Development (Saraca) Pte LtdHigh CourtYes[2002] 2 SLR(R) 1063SingaporeCited for the duty of an arbitrator to listen to both sides and give each side an opportunity to submit on all relevant points.
Timwin Construction v Façade InnovationsNew South Wales Supreme CourtYes[2005] NSWSC 548AustraliaCited for the principle that there is a breach of natural justice when the arbitrator disregards the submissions made by a party during the hearing.
Lanskey v NoxequinNew South Wales Supreme CourtYes[2005] NSWSC 963AustraliaCited for the principle that a tribunal has to consider all issues raised by parties.
Trysams Pty Ltd v Club Constructions (NSW) Pty LtdNew South Wales Supreme CourtYes[2007] NSWSC 941AustraliaCited for the principle that natural justice requires the adjudicator to consider the report unless he determined that it was, or was part of, a submission not duly made.
SEF Construction Pte Ltd v Skoy Connected Pte LtdHigh CourtYes[2009] SGHC 257SingaporeCited to distinguish the present case where the arbitrator explicitly disregarded an issue, unlike in SEF Construction where the adjudicator had regard to the submissions.
Dongwoo Mann+Hummel Co Ltd v Mann+Hummel GmbHHigh CourtYes[2008] 3 SLR(R) 871SingaporeCited for the requirement of a causal nexus between the breach of natural justice and the making of the award.
Gas & Fuel Corporation of Victoria v Wood Hall Ltd & Leonard Pipeline Contractors LtdSupreme Court of VictoriaYes[1978] VR 385AustraliaCited for the essence of the two pillars of natural justice.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Arbitration Act (Cap 10, 2002 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Asian Cup Series
  • Misrepresentation
  • Natural Justice
  • Arbitration Award
  • Audi Alteram Partem
  • SLK 55 cars
  • Re-Amended Answer and Counterclaim

15.2 Keywords

  • arbitration
  • natural justice
  • misrepresentation
  • singapore
  • contract
  • award
  • setting aside

17. Areas of Law

16. Subjects

  • Arbitration
  • Contract Law
  • Civil Procedure