CRW v PT Perusahaan Gas Negara: Enforcing DAB Decisions in Construction Arbitration

In CRW Joint Operation v PT Perusahaan Gas Negara (Persero) TBK, the Singapore Court of Appeal addressed the enforceability of a Dispute Adjudication Board (DAB) decision under the 1999 FIDIC Red Book. CRW, a joint operation, appealed against the High Court's decision to set aside a final arbitral award in favor of CRW. The court dismissed the appeal, holding that the arbitral tribunal exceeded its jurisdiction by issuing a final award enforcing the DAB's decision without reviewing the merits of the underlying dispute, thereby depriving PT Perusahaan Gas Negara (PGN) of its right to a full hearing.

1. Case Overview

1.1 Court

Court of Appeal

1.2 Outcome

Appeal dismissed with costs. The court upheld the decision to set aside the Final Award.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Singapore Court of Appeal clarifies the enforceability of Dispute Adjudication Board (DAB) decisions in construction contracts and arbitration.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
PT Perusahaan Gas Negara (Persero) TBKRespondentCorporationApplication to set aside Final Award AllowedWon
CRW Joint OperationAppellantOtherAppeal DismissedLost

3. Judges

Judge NameTitleDelivered Judgment
Chao Hick TinJustice of the Court of AppealYes
Andrew Phang Boon LeongJustice of the Court of AppealYes
V K RajahJustice of the Court of AppealYes

4. Counsels

4. Facts

  1. CRW and PGN entered into a Pipeline Construction Contract in 2006.
  2. A dispute arose regarding 13 variation order proposals submitted by CRW.
  3. The dispute was referred to a DAB, which awarded US$17,298,834.57 to CRW.
  4. PGN filed a notice of dissatisfaction with the DAB's decision.
  5. CRW commenced arbitration to enforce the DAB's decision.
  6. The arbitral tribunal issued a final award in favor of CRW without reviewing the merits of the DAB decision.
  7. PGN applied to set aside the final award.

5. Formal Citations

  1. CRW Joint Operation v PT Perusahaan Gas Negara (Persero) TBK, Civil Appeal No 59 of 2010, [2011] SGCA 33

6. Timeline

DateEvent
Pipeline Construction Contract signed
Dispute adjudication agreement signed
Adjudicator awarded US$17,298,834.57 to CRW
PGN filed a notice of dissatisfaction
CRW issued an invoice to PGN for US$17,298,834.57
CRW filed a request for arbitration with the ICC
ICC confirmed appointments of Mr. Neil Kaplan and Prof. H Priyatna Abdurrasyid as co-arbitrators
PGN filed an answer to CRW’s Request for Arbitration
Mr. Alan J Thambiayah appointed as chairman of the Arbitral Tribunal
Preliminary meeting held
Arbitral Tribunal gave directions
Parties signed the terms of reference for the Arbitration
Hearing of the Preliminary Issues took place
Majority Members issued the Final Award in favour of CRW
Prof Abdurrasyid issued a dissenting opinion
Enforcement Order was made
Judgment reserved

7. Legal Issues

  1. Excess of Jurisdiction by Arbitral Tribunal
    • Outcome: The court held that the arbitral tribunal exceeded its jurisdiction by issuing a final award without reviewing the merits of the DAB decision.
    • Category: Jurisdictional
    • Sub-Issues:
      • Failure to review merits of DAB decision
      • Issuing final award without assessing underlying dispute
  2. Breach of Natural Justice
    • Outcome: The court found that the arbitral tribunal breached the rules of natural justice by not giving PGN a real opportunity to defend its position.
    • Category: Procedural
    • Sub-Issues:
      • Denial of opportunity to present case
      • Failure to provide a fair hearing
  3. Enforceability of DAB Decisions
    • Outcome: The court clarified that DAB decisions are binding but not final and are subject to review in subsequent arbitration proceedings.
    • Category: Substantive
    • Sub-Issues:
      • Interim binding effect of DAB decisions
      • Requirement for rehearing in arbitration

8. Remedies Sought

  1. Enforcement of Arbitral Award
  2. Setting Aside of Arbitral Award

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Arbitration
  • Commercial Litigation
  • Construction Law

11. Industries

  • Construction
  • Energy

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
PT Perusahaan Gas Negara (Persero) TBK v CRW Joint OperationHigh CourtYes[2010] 4 SLR 672SingaporeCited as the decision from which the appeal arose, concerning the setting aside of a final award.
Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte LtdCourt of AppealYes[2007] 3 SLR(R) 86SingaporeCited for the principle of minimal curial intervention in the arbitral process.
PT Asuransi Jasa Indonesia (Persero) v Dexia Bank SACourt of AppealYes[2007] 1 SLR(R) 597SingaporeCited for the two-stage enquiry in assessing whether an arbitral award ought to be set aside under Article 34(2)(a)(iii) of the Model Law.
Sui Southern Gas Co Ltd v Habibullah Coastal Power Co (Pte) LtdCourt of AppealYes[2010] 3 SLR 1SingaporeCited for the principle that mere errors of law or fact are not sufficient to warrant setting aside an arbitral award under Art 34(2)(a)(iii) of the Model Law.
Lesotho Highlands Development Authority v Impregilo SpA and othersHouse of LordsYes[2006] 1 AC 221United KingdomCited for the distinction between the erroneous exercise of an available power and the purported exercise of a power which the arbitral tribunal did not possess.
Paklito Investment Limited v Klockner East Asia LimitedHigh Court of Hong KongYes[1993] 2 HKLR 39Hong KongCited regarding the court's residual discretion to enforce an arbitral award notwithstanding that one of the prescribed grounds for resisting enforcement has been established.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
UNCITRAL Model Law on International Commercial ArbitrationUnited Nations
International Arbitration Act (Cap 143A, 2002 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Dispute Adjudication Board
  • DAB decision
  • FIDIC Red Book
  • Notice of Dissatisfaction
  • Arbitral Tribunal
  • Final Award
  • Interim Award
  • Jurisdiction
  • Natural Justice
  • Rehearing
  • Terms of Reference

15.2 Keywords

  • arbitration
  • construction
  • DAB
  • FIDIC
  • enforcement
  • jurisdiction
  • natural justice

17. Areas of Law

16. Subjects

  • Arbitration
  • Construction Dispute
  • Contract Law