Store+Deliver+Logistics v Chin Siew Gim: Architect Negligence & Breach of Contract in Warehouse Construction

In Store+Deliver+Logistics Pte Ltd v Chin Siew Gim (trading as S G Chin and Associates), the High Court of Singapore heard a case regarding claims by Store+Deliver+Logistics against Chin Siew Gim for breach of contract and negligence in relation to the design and supervision of the construction of a warehouse. The court, presided over by Justice Lee Seiu Kin, found the defendant liable for failing to specify a superflat floor in the building contract and for failing to provide as-built drawings, awarding damages of $95,000 and $4,500 respectively. The court dismissed the other claims.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Judgment for Plaintiff in part.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Store+Deliver+Logistics sued Chin Siew Gim for negligence and breach of contract in a warehouse project. The court found the architect liable for failing to specify a superflat floor and provide as-built drawings.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Store+Deliver+Logistics Pte LtdPlaintiffCorporationJudgment for Plaintiff in partPartial
Chin Siew Gim (trading as S G Chin and Associates)DefendantIndividualJudgment against Defendant in partLost

3. Judges

Judge NameTitleDelivered Judgment
Lee Seiu KinJudgeYes

4. Counsels

4. Facts

  1. The plaintiff engaged the defendant as the architect for a warehouse construction project.
  2. The defendant recommended Kin Lin Builders, but the plaintiff chose Expedite Construction instead.
  3. The plaintiff required a 'superflat' floor for a VNA racking system.
  4. The defendant did not specify a superflat floor in the building contract.
  5. The constructed floor did not meet the superflat specification, requiring the plaintiff to grind the floor at a cost of $95,000.
  6. The defendant specified Sisalation roof insulation, which the plaintiff claimed was unsuitable due to the corrosive environment.
  7. The defendant failed to provide as-built drawings.

5. Formal Citations

  1. Store+Deliver+Logistics Pte Ltd v Chin Siew Gim (trading as S G Chin and Associates), Suit No 188 of 2009, [2012] SGHC 89

6. Timeline

DateEvent
Defendant sent letter to plaintiff outlining terms of appointment.
Tenders closed for the warehouse project.
Defendant produced tender report recommending Kin Lin Builders.
Defendant advised against awarding project to Expedite.
Contract for construction of Warehouse awarded to Expedite.
Construction commenced.
Phase 1 completed and handed to plaintiff.
Expedite commenced work on phase 2.
Original completion date.
Expedite commenced work on phase 3.
Defendant certified works completed.
Defendant listed 12 defects.
Fire broke out in the Warehouse.
Expedite provided schedule for rectification of defects.
Defendant instructed Expedite to rectify unlevelled floor.
Expedite claimed time for performance was at large.
Defendant set out further list of defects.
Defendant advised plaintiff to call on performance bond.
Call made on the performance bond.
Expedite filed Suit 309 of 2004.
Defendant set out new list of defects.
Suit 309 settled.
Defendant issued letter listing new defects.
T J Chiam produced report on defective works.
Defendant issued delay certificate extending completion date.
Defendant gave list of new defects.
Expedite disagreed with defendant's evaluation of extension of time.
Plaintiff engaged Franklin + Andrews to prepare cost estimate.
Expedite submitted final claim.
Defendant pointed out claims were unsubstantiated.
Defendant issued Statement of Final Account.
Plaintiff and Expedite appointed arbitrator.
Arbitrator issued award.
Suit No 188 of 2009 filed.
Judgment reserved.

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found the defendant liable for breach of contract for failing to specify a superflat floor and provide as-built drawings.
    • Category: Substantive
  2. Negligence
    • Outcome: The court found the defendant negligent in failing to specify a superflat floor and supervise the installation of roof insulation.
    • Category: Substantive

8. Remedies Sought

  1. Damages for breach of contract and negligence

9. Cause of Actions

  • Breach of Contract
  • Negligence

10. Practice Areas

  • Commercial Litigation
  • Construction Defect Litigation

11. Industries

  • Construction
  • Logistics

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
No cited cases

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Superflat floor
  • VNA racking system
  • As-built drawings
  • Sisalation
  • Parsec
  • Warehouse construction
  • Architectural services

15.2 Keywords

  • architect
  • negligence
  • breach of contract
  • warehouse
  • construction
  • superflat floor
  • as-built drawings

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Architectural Services
  • Negligence
  • Contract Law