YTL Construction v Balanced Engineering: SOP Act Adjudication Determination Dispute

YTL Construction (S) Pte Ltd sought to set aside an adjudication determination under the Building and Construction Industry Security of Payment Act against Balanced Engineering & Construction Pte Ltd. The High Court, presided over by Justice Tan Siong Thye, allowed the application, finding that Balanced Engineering's payment claim was invalid because it did not specify the claimed amount for the relevant period, and the adjudication application was lodged out of time. The court determined that these failures affected the validity of the adjudicator's appointment, warranting the setting aside of the adjudication determination.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Plaintiff's application allowed; adjudication determination set aside.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Dispute over an adjudication determination under the SOP Act. The court set aside the determination due to an invalid payment claim.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
YTL Construction (S) Pte LtdPlaintiffCorporationApplication AllowedWon
Balanced Engineering & Construction Pte LtdDefendantCorporationAdjudication Determination Set AsideLost

3. Judges

Judge NameTitleDelivered Judgment
Tan Siong ThyeJudgeYes

4. Counsels

4. Facts

  1. YTL Construction appointed Balanced Engineering as a subcontractor for structural works.
  2. The original agreed value of the works to be executed by Balanced Engineering was about $9 million.
  3. Balanced Engineering served a payment claim on YTL Construction for work done in August 2013.
  4. The payment claim did not specify the amount claimed for August 2013.
  5. YTL Construction served a payment response certifying $695,370.76 (exclusive of GST) for August 2013.
  6. Balanced Engineering lodged an adjudication application claiming $1,328,536.83.
  7. The adjudicator determined that YTL Construction should pay Balanced Engineering $754,111.22.

5. Formal Citations

  1. YTL Construction (S) Pte Ltd v Balanced Engineering & Construction Pte Ltd, Originating Summons No 1223 of 2013, [2014] SGHC 142

6. Timeline

DateEvent
YTL Construction appointed as main contractor for the Project.
Balanced Engineering served a payment claim on YTL Construction.
YTL Construction served its payment response on Balanced Engineering.
Balanced Engineering issued a tax invoice to claim $744,046.71.
Balanced Engineering issued a revised tax invoice for $897,889.83.
Due date for payment of $754,111.22.
Balanced Engineering gave notice of intention to apply for adjudication.
Balanced Engineering lodged its adjudication application with the Singapore Mediation Centre.
YTL Construction received the adjudication application.
YTL Construction lodged its adjudication response with the Singapore Mediation Centre.
Adjudication determination issued.
Judgment reserved.

7. Legal Issues

  1. Validity of Payment Claim
    • Outcome: The court held that the payment claim was invalid because it did not state the specific amount claimed for the reference period.
    • Category: Substantive
    • Sub-Issues:
      • Failure to state the claimed amount for the relevant period
    • Related Cases:
      • [2013] 1 SLR 401
      • [2013] 2 SLR 776
  2. Timeliness of Adjudication Application
    • Outcome: The court held that the adjudication application was lodged out of time because the Defendant was disputing the payment response.
    • Category: Procedural
    • Sub-Issues:
      • Lodging application out of time
      • Dispute of payment response
    • Related Cases:
      • [2013] 1 SLR 848
  3. Waiver of Formal Requirements
    • Outcome: The court held that non-compliance with s 10(3) of the SOP Act cannot be waived.
    • Category: Procedural
    • Sub-Issues:
      • Estoppel
      • Implied waiver
    • Related Cases:
      • [2010] 1 SLR 658
      • [2013] 3 SLR 609
      • [2013] 1 SLR 1157
  4. Compliance with Natural Justice
    • Outcome: The court held that there was no breach of natural justice as the Plaintiff was given a fair opportunity to be heard.
    • Category: Procedural
    • Related Cases:
      • [2009] SGHC 260
  5. Timeliness of Adjudication Determination
    • Outcome: The court held that the adjudication determination was rendered within time.
    • Category: Procedural

8. Remedies Sought

  1. Setting aside of adjudication determination

9. Cause of Actions

  • Breach of Contract
  • Statutory Claim under the Building and Construction Industry Security of Payment Act

10. Practice Areas

  • Construction Litigation
  • Adjudication

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appealCourt of AppealYes[2013] 1 SLR 401SingaporeCited for the court's role in a setting-aside action and the importance of legislative provisions in the SOP Act.
Australia Timber Products Pte Ltd v A Pacific Construction & Development Pte LtdHigh CourtYes[2013] 2 SLR 776SingaporeCited for considerations in determining whether a provision of the SOP Act or SOPR is a legislatively important provision.
Chip Hup Hup Kee Construction Pte Ltd v Ssangyong Engineering & Construction Co LtdHigh CourtYes[2010] 1 SLR 658SingaporeCited regarding whether parties could be estopped from contesting jurisdiction.
Admin Construction Pte Ltd v Vivaldi (S) Pte LtdHigh CourtYes[2013] 3 SLR 609SingaporeCited regarding the validity of a payment claim and the jurisdiction of the adjudicator.
JFC Builders Pte Ltd v LionCity Construction Co Pte LtdHigh CourtYes[2013] 1 SLR 1157SingaporeCited regarding non-compliance with s 10(1) of the SOP Act and whether it could be waived.
RN & Associates Pte Ltd v TPX Builders Pte LtdHigh CourtYes[2013] 1 SLR 848SingaporeCited regarding s 16(2) of the SOP Act and the adjudicator's jurisdiction.
Shin Khai Construction Pte Ltd v FL Wong Construction Pte LtdHigh CourtYes[2013] SGHCR 4SingaporeCited regarding s 16(2)(a) of the SOP Act.
W Y Steel Construction Pte Ltd v Osko Pte LtdCourt of AppealYes[2013] 3 SLR 380SingaporeCited regarding the importance of tight timelines under the SOP Act.
Chase Oyster Bar v Hamo IndustriesNew South Wales Court of AppealYes[2010] NSWCA 190AustraliaCited regarding the strict observance of statutory requirements under the Security of Payment Act.
AM Associates (Singapore) Pte Ltd v Laguna National Golf and Country Club LtdHigh CourtYes[2009] SGHC 260SingaporeCited regarding the principles of natural justice and the review of adjudication determinations.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore
s 10(3)(a) of the SOP ActSingapore
s 12(2) of the SOP ActSingapore
s 12(5) of the SOP ActSingapore
s 13(3)(a) of the SOP ActSingapore
s 16(2)(a) of the SOP ActSingapore
s 16(3)(c) of the SOP ActSingapore
s 17(1) of the SOP ActSingapore
s 12(1) of the SOP ActSingapore
s 15(1) of the SOP ActSingapore

15. Key Terms and Keywords

15.1 Key Terms

  • Adjudication Determination
  • Payment Claim
  • Payment Response
  • Security of Payment Act
  • Adjudication Application
  • Claimed Amount
  • Dispute Settlement Period
  • Adjudicator
  • Jurisdiction
  • Estoppel

15.2 Keywords

  • SOP Act
  • Adjudication
  • Payment Claim
  • Construction
  • Singapore

17. Areas of Law

16. Subjects

  • Construction Law
  • Contract Law
  • Civil Procedure