Newcon Builders v Sino New Steel: Premature Adjudication Application under SOPA
In Newcon Builders Pte Ltd v Sino New Steel Pte Ltd, the High Court of Singapore addressed a Registrar's Appeal concerning an adjudication determination under the Building and Construction Industry Security of Payment Act. Newcon Builders, the plaintiff, engaged Sino New Steel, the defendant, for structural steel works. A dispute arose over Payment Claim No 14, leading Sino New Steel to file an adjudication application. Newcon Builders challenged the adjudication, arguing it was filed prematurely. The High Court, Quentin Loh J presiding, allowed the appeal, holding that an adjudication application filed during the dispute settlement period is invalid under the Act.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Appeal Allowed
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
The High Court held that an adjudication application filed during the dispute settlement period is invalid under the Building and Construction Industry Security of Payment Act.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Newcon Builders Pte Ltd | Plaintiff, Respondent | Corporation | Appeal Allowed | Won | |
Sino New Steel Pte Ltd | Defendant, Appellant | Corporation | Appeal Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Quentin Loh | Judge | Yes |
4. Counsels
4. Facts
- Newcon Builders was engaged as main contractor for a construction project.
- Newcon Builders entered into a sub-contract with Sino New Steel for structural steel works.
- Sino New Steel served Payment Claim No 14 on Newcon Builders.
- Newcon Builders sought clarification of the Payment Claim.
- Sino New Steel served a notice of intention to apply for adjudication and filed an adjudication application.
- Newcon Builders submitted a Statement of Final Account.
- The adjudicator issued an adjudication determination in favor of Sino New Steel.
- Newcon Builders commenced Originating Summons No 228 of 2015 to set aside the Adjudication Determination.
5. Formal Citations
- Newcon Builders Pte Ltd v Sino New Steel Pte Ltd, Originating Summons No 228 of 2015 (Registrar's Appeal No 179 of 2015), [2015] SGHC 226
6. Timeline
Date | Event |
---|---|
Sub-contract works substantially completed | |
Payment Claim No 14 served by Defendant | |
Defendant served notice of intention to apply for adjudication | |
Plaintiff submitted Statement of Final Account | |
Defendant filed adjudication application | |
Adjudication Application served on Plaintiff | |
Adjudicator appointed | |
Plaintiff filed adjudication response | |
Adjudication conference began | |
Adjudication conference concluded | |
Site inspection conducted by Adjudicator | |
Adjudication Determination issued | |
Hearing for Originating Summons No 228 of 2015 commenced | |
Hearing for Originating Summons No 228 of 2015 concluded | |
AR's Decision delivered | |
Parties heard | |
Judgment reserved |
7. Legal Issues
- Premature Adjudication Application
- Outcome: The court held that an adjudication application cannot be made during the dispute settlement period and any such application is invalid.
- Category: Procedural
- Sub-Issues:
- Filing of adjudication application before expiry of dispute settlement period
- Incorporation of Main Contract Terms into Sub-contract
- Outcome: The court held that the terms of the Main Contract in relation to the interim certificate was incorporated into the Sub-contract.
- Category: Substantive
- Sub-Issues:
- Interpretation of incorporation clauses
- Conflict between main contract and sub-contract terms
8. Remedies Sought
- Setting aside of Adjudication Determination
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Construction Litigation
- Commercial Litigation
- Arbitration
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appeal | Court of Appeal | Yes | [2013] 1 SLR 401 | Singapore | Cited for the principle that the court has the power to decide whether the adjudicator was validly appointed and may set aside an adjudication determination on the ground of non-compliance with provisions under the Act. |
Taisei Corp v Doo Ree Engineering & Trading Pte Ltd | High Court | Yes | [2009] SGHC 156 | Singapore | Cited for the holding that a premature adjudication application was ground for setting aside an adjudication determination; disagreed with by the AR. |
JRP & Associates Pte Ltd v Kindly Construction & Services Pte Ltd | High Court | Yes | [2015] 3 SLR 575 | Singapore | Cited regarding the test for non-compliance with the Act. |
Citiwall Safety Glass Pte Ltd v Mansource Interior Pte Ltd | Court of Appeal | Yes | [2015] 1 SLR 797 | Singapore | Cited for the principle that the court does not review the merits of the adjudicator’s decision, and any setting aside must be premised on issues relating to the jurisdiction of the adjudicator, a breach of natural justice or non-compliance with the SOPA. |
Quanta Industries Pte Ltd v Strategic Construction Pte Ltd | High Court | Yes | [2015] 2 SLR 70 | Singapore | Cited as an instance where the High Court has set aside an adjudication determination on the basis that a mandatory condition of the Act had not been complied with. |
YTL Construction (S) Pte Ltd v Balanced Engineering & Construction Pte Ltd | High Court | Yes | [2014] SGHC 142 | Singapore | Cited for setting aside the adjudication determination on the basis that the adjudication application had been lodged out of time. |
LH Aluminium Industries Pte Ltd v Newcon Builders Pte Ltd | High Court | Yes | [2015] 1 SLR 648 | Singapore | Cited as a case where the defendant sought to set aside an adjudication determination on the basis that the adjudication application was lodged prematurely, but the court did not address the question as to whether this was a valid ground for setting aside. |
Bouygues (UK) Ltd v Dahl-Jensen (UK) Ltd | England and Wales Court of Appeal (Civil Division) | Yes | [2000] EWCA Civ 507 | England and Wales | Cited for the principle that if the adjudicator has answered the right question in the wrong way, his decision will be binding, but if he has answered the wrong question, his decision will be a nullity. |
GIB Automation Pte Ltd v Deluge Fire Protection (SEA) Pte Ltd | High Court | Yes | [2007] 2 SLR(R) 918 | Singapore | Cited for the principle that a back-to-back provision had to be construed in the light of the factual matrix known to the parties at the time of contracting. |
Modern Building Wales Ltd v Limmer & Trinidad Co Ltd | England and Wales Court of Appeal (Civil Division) | Yes | [1975] 1 WLR 1281 | England and Wales | Cited for the principle that the court will adopt an approach where reference is made (even if briefly and inaccurately) to a document which both parties will be aware of and will recognise, and which both parties would normally expect to be included. |
Schindler Lifts (Singapore) Pte Ltd v Paya Ubi Industrial Park Pte Ltd and Another | High Court | Yes | [2004] SGHC 34 | Singapore | Cited as an example of a case where a clause acted as an incorporation clause. |
Progressive Builders Pte Ltd v Long Rise Pte Ltd | High Court | Yes | [2015] SGHC 223 | Singapore | Cited as a case where the court recited facts without controversy that payment certificate was in response to progress claim. |
Citywall Safety Glass Pte Ltd v Mansource Interior Pte Ltd | Court of Appeal | Yes | [2015] SGCA 42 | Singapore | Cited for the strict application of timelines under the SOPA. |
Shin Khai Construction Pte Ltd v FL Wong Construction Pte Ltd | High Court | Yes | [2013] SGHCR 4 | Singapore | Cited for the need for certainty and an unambiguous test under s 13(3)(a) of the Act. |
Walter Construction Group Ltd v CPL (Surry Hills) Pty Ltd | Supreme Court of New South Wales | Yes | [2003] NSWSC 266 | Australia | Cited as a case that generated concerns that led to the inclusion of the 7-day dispute settlement period in the Singapore adjudication scheme. |
CIB Properties Ltd v Birse Construction Ltd | High Court of Justice | Yes | [2004] EWHC 2365 | England and Wales | Cited as an English example of a case where it was alleged that while the claimant appeared to negotiate, it was secretly preparing its adjudication claim. |
The Dorchester Hotel Limited v Vivid Interiors Limited | High Court of Justice | Yes | [2009] EWHC 70 (TCC) | England and Wales | Cited as an example of a case where claimants serve payment claims with voluminous documentation on the eve of public holidays or during the holiday season. |
Macob Civil Engineering Ltd v Morrison Construction Ltd | Technology and Construction Court | Yes | [1999] BLR 93 | England and Wales | Cited for the acknowledgement that the timeline for adjudications is very tight. |
Multiplex Constructions Pty Ltd v Luikens and Anor | Supreme Court of New South Wales | Yes | [2003] NSWSC 1140 | Australia | Cited for the principle that reasons for withholding payment of a claim be indicated in the payment schedule with sufficient particularity to enable the claimant to understand, at least in broad outline, what is the issue between it and the respondent. |
ABB Holdings Pte Ltd and others v Sher Hock Guan Charles | High Court | Yes | [2009] 4 SLR(R) 111 | Singapore | Cited for the principle that when ascertaining if a document has been incorporated into a contract, what is crucial is the intention of both of the parties to the contract. |
R1 International Pte Ltd v Lonstroff AG | Court of Appeal | Yes | [2015] 1 SLR 521 | Singapore | Cited for the principle that the law adopts an objective approach towards questions of contractual formation and the incorporation of terms. |
Brightside Kilpatrick Engineering Services Ltd v Mitchell Construction (1973) Ltd | Unknown | Yes | [1975] 2 Lloyd’s Rep 493 | Unknown | Cited as a case with similar facts. |
Petroleum Oil & Gas Corp of South Africa (Pty) Ltd v FR8 Singapore PTE Ltd (The Eternity) | Unknown | Yes | [2009] 1 Lloyd’s Rep 107 | Unknown | Cited for the principle that where possible, the court should seek to construe the clauses in a contract in a manner which reconciles potentially conflicting clauses. |
Bayoil SA v Seawind Tankers Corporation (The Leonidas) | Unknown | Yes | [2001] 1 Lloyd’s Rep 533 | Unknown | Cited for the principle that where possible, the court should seek to construe the clauses in a contract in a manner which reconciles potentially conflicting clauses. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Adjudication Application
- Adjudication Determination
- Payment Claim
- Payment Response
- Dispute Settlement Period
- Main Contract
- Sub-contract
- Interim Certificate
- Building and Construction Industry Security of Payment Act
- Statement of Final Account
15.2 Keywords
- Adjudication
- Construction
- Payment
- SOPA
- Singapore
- Building
- Contract
17. Areas of Law
Area Name | Relevance Score |
---|---|
Adjudication | 90 |
Building and Construction Contracts | 90 |
Construction Law | 90 |
Contract Law | 70 |
Arbitration | 30 |
16. Subjects
- Construction Dispute
- Adjudication
- Contract Law