Aik Heng v Deshin: Security of Payment Act Adjudication Determination Dispute

Aik Heng Contracts and Services Pte Ltd applied to enforce an adjudication determination against Deshin Engineering & Construction Pte Ltd under the Building and Construction Industry Security of Payment Act. Deshin Engineering appealed the assistant registrar's decision, arguing the notice of intention was invalid and the adjudicator breached natural justice. The High Court dismissed Deshin's appeal and its application for a stay of execution, finding no grounds to set aside the determination.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Appeal dismissed and application for stay of execution dismissed.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Aik Heng Contracts sought to enforce an adjudication determination under the SOPA. The court dismissed Deshin Engineering's appeal to set aside the determination.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Aik Heng Contracts and Services Pte LtdApplicantCorporationAppeal AllowedWonAshok Kumar Rai
Deshin Engineering & Construction Pte LtdRespondentCorporationAppeal DismissedLostTan Joo Seng

3. Judges

Judge NameTitleDelivered Judgment
Lee Seiu KinJudgeYes

4. Counsels

Counsel NameOrganization
Ashok Kumar RaiChan Neo LLP
Tan Joo SengChong Chia & Lim LLC

4. Facts

  1. The respondent was the main contractor for a condominium project.
  2. The applicant was appointed as a subcontractor for installation of aluminium, steel & glazing works.
  3. The applicant served a payment claim on the respondent for $85,974.19.
  4. The respondent did not file a payment response.
  5. The adjudicator determined in favor of the applicant.
  6. The applicant applied for leave to enforce the determination.
  7. The respondent sought to set aside the determination and stay its enforcement.

5. Formal Citations

  1. Aik Heng Contracts and Services Pte Ltd v Deshin Engineering & Construction Pte Ltd, Originating Summons No 432 of 2015 (Registrar's Appeal No 195 of 2015), [2015] SGHC 293

6. Timeline

DateEvent
Letter of Award issued
Letter of Award signed and accepted by applicant
Payment claim served by applicant on respondent
Adjudication Application lodged
Order of court granted for leave to enforce the Determination
Letter of award evidencing that the applicant had secured a new project with YSR
Appeal dismissed and application for stay of execution dismissed

7. Legal Issues

  1. Breach of Natural Justice
    • Outcome: The court held that there was no material breach of natural justice.
    • Category: Procedural
    • Sub-Issues:
      • Failure to properly adjudicate claim
      • Failure to allow respondent to raise contentions
    • Related Cases:
      • [2013] 3 SLR 380
  2. Validity of Notice of Intention
    • Outcome: The court held that the breach of regulation 7(1)(a) was a technical breach insufficient to invalidate the notification.
    • Category: Jurisdictional
    • Related Cases:
      • [2013] 1 SLR 401
      • [2013] 2 SLR 776
      • [2015] 5 SLR 689
  3. Stay of Enforcement of Adjudication Determination
    • Outcome: The court declined to order a stay of execution of the Order.
    • Category: Procedural
    • Related Cases:
      • [2013] 3 SLR 380

8. Remedies Sought

  1. Setting aside of Adjudication Determination
  2. Stay of Enforcement of Order

9. Cause of Actions

  • Enforcement of Adjudication Determination

10. Practice Areas

  • Construction Law
  • Commercial Litigation
  • Arbitration

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appealCourt of AppealYes[2013] 1 SLR 401SingaporeCited for the principle that not all breaches of regulations warrant setting aside an adjudication determination.
Australian Timber Products Pte Ltd v A Pacific Construction & Development Pte LtdHigh CourtYes[2013] 2 SLR 776SingaporeCited for the principle that a payment claim would not be invalidated for failure to comply with regulations where that failure did not impede the adjudication process.
Progressive Builders Pte Ltd v Long Rise Pte LtdHigh CourtYes[2015] 5 SLR 689SingaporeCited for the principle that a payment claim would only be invalidated for failure to comply with the Act where that failure impeded the adjudication process.
SEF Construction Pte Ltd v Skoy Connected Pte LtdHigh CourtYes[2010] 1 SLR 733SingaporeCited for the principle that a breach of section 16(3) of the Act is sufficient basis for setting aside an adjudication determination.
W Y Steel Construction Pte Ltd v Osko Pte LtdCourt of AppealYes[2013] 3 SLR 380SingaporeCited for the principle that an adjudicator is bound to consider the payment claim and cannot make a determination as if the absence of a response obviates the need for consideration.
Balfour Beatty Construction Limited v The Mayor and Burgesses of the London Borough of LambethN/AYes[2002] BLR 288United KingdomCited for the principle that the purpose of adjudication is not to be thwarted by an overly sensitive concern for procedural niceties.
Cantillon Ltd v Urvasco LtdN/AYes[2008] BLR 250N/AEndorsed the principles in Balfour Beatty Construction Limited v The Mayor and Burgesses of the London Borough of Lambeth.
Brodyn Pty Ltd (trading as Time Cost and Quality) v Davenport and anotherSupreme Court of New South WalesYes(2004) 61 NSWLR 421New South WalesCited for the principle that an adjudication determination would be void if there had been a substantial denial of natural justice.
Watpac Constructions v Austin CorpN/AYes[2010] NSWSC 168New South WalesCited for the principle that any entitlement to natural justice must accommodate the scheme of the Act, including the compressed timetable.
Management Corporation Strata Title Plan No 301 v Lee Tat Development Pte LtdCourt of AppealYes[2011] 1 SLR 998SingaporeCited for the principle that a breach of the hearing rule does not entail that the tainted decision must be set aside.
The Oriental Insurance Co Ltd v Reliance National Asia Re Pte LtdN/AYes[2009] 2 SLR(R) 385SingaporeCited for the definition of 'manifest errors' as oversights and blunders so obvious and obviously capable of affecting the determination as to admit of no difference of opinion.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore
Building and Construction Industry Security of Payment Act s 13(2)Singapore
Building and Construction Industry Security of Payment Act s 15(3)Singapore
Building and Construction Industry Security of Payment Act s 16(3)Singapore
Rules of Court (Cap 322, R 5, 2014 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Adjudication Determination
  • Payment Claim
  • Payment Response
  • Notice of Intention
  • Natural Justice
  • Patent Error
  • Stay of Execution

15.2 Keywords

  • adjudication
  • security of payment
  • construction
  • natural justice
  • payment claim
  • notice of intention

16. Subjects

  • Construction Dispute
  • Adjudication
  • Security of Payment
  • Breach of Natural Justice

17. Areas of Law

  • Building and Construction Law
  • Contract Law
  • Civil Procedure
  • Security of Payment