AUF v AUG: Challenge to Arbitral Award on Defective External Wall System
In AUF v AUG, the Singapore High Court heard three applications challenging an arbitral award concerning a dispute over a defective external wall system on a commercial building. AUF, the Contractor, challenged the award, seeking to set it aside in part and for leave to appeal on questions of law. AUG, the Owner, sought to uphold the award. The court, presided over by Belinda Ang Saw Ean J, dismissed all three applications, finding that the arbitrator did not exceed his jurisdiction or breach natural justice in making the award. The underlying dispute arose from leaks and water-seepage issues after the building's completion, leading to claims of breach of contract and damages.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Applications dismissed with costs.
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Challenge to an arbitral award regarding a defective external wall system. The court dismissed the challenge, upholding the arbitrator's decision.
1.7 Decision Date
2. Parties and Outcomes
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Belinda Ang Saw Ean | Judge | Yes |
4. Counsels
4. Facts
- The dispute arose from the construction of a 13-storey commercial building.
- The Owner claimed defects in the external wall system installed by a nominated sub-contractor.
- The Contractor was the main contractor for the project.
- Leaks and water seepage occurred after the building's completion in March 1997.
- The Owner initially sought recladding of the external walls, but later withdrew this claim.
- An independent expert was appointed to assess the defects.
- The arbitrator awarded damages based on 40% of the final sub-contract sum.
5. Formal Citations
- AUF v AUG and other matters, Originating Summons No 790 of 2014, Originating Summons No 791 of 2014 and Originating Summons No 789 of 2014 (Summons No 4899 of 2014), [2015] SGHC 305
6. Timeline
Date | Event |
---|---|
Main Contract signed between the Owner and the Contractor. | |
Building completed. | |
Complaints of leaks and water-seepage into the Building surfaced. | |
Contractor carried out ad hoc repair works by face-sealing and over-sealing the Building. | |
Further rectification works were carried out. | |
Rectification works completed, but the leaks persisted. | |
Owner informed the Contractor that it wanted the external wall to be re-cladded. | |
NSC was joined as a third party to the arbitral proceedings. | |
Owner added its alternative claim for damages for diminution in the value of the Building to its pleadings. | |
The Owner’s re-amended Points of Claim was dated. | |
First tranche of hearing on the issue of liability was held. | |
First tranche of hearing on the issue of liability was held. | |
Contractor offered the Owner a sum of $4.43m in full and final settlement of the Owner’s claims. | |
Owner's Calderbank letter. | |
Contractor's offer of 26 August 2005 was expressly withdrawn. | |
Procedural meeting held; Owner withdrew its claim for recladding of the external walls of the Building. | |
An independent expert was appointed. | |
The Independent Expert issued a draft report on the defects listed in Appendix A1.1 in two parts. | |
The Independent Expert issued a draft report on the defects listed in Appendix A1.1 in two parts. | |
A procedural meeting was held following the Contractor’s proposal to limit the scope of the arbitral hearing. | |
End of tender period. | |
Oral hearing was held for counsel on both sides to address the Arbitrator on their respective written submissions. | |
Oral hearing was held for counsel on both sides to address the Arbitrator on their respective written submissions. | |
The Arbitrator directed the parties to address the Tribunal on the issue of diminished value. | |
A procedural meeting was held. | |
Arbitral award dated. | |
Ex parte Order of Court dated to enforce the Award as a judgment of the High Court. | |
Parties clarified in their respective letters. | |
Parties clarified in their respective letters. | |
Judgment reserved. |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that the arbitrator did not err in finding a breach of contract.
- Category: Substantive
- Sub-Issues:
- Defective works
- Failure to perform contractual obligations
- Jurisdiction of Arbitrator
- Outcome: The court held that the arbitrator did not exceed his jurisdiction.
- Category: Jurisdictional
- Sub-Issues:
- Exceeding scope of reference
- Awarding damages on unpleaded basis
- Breach of Natural Justice
- Outcome: The court found no breach of natural justice.
- Category: Procedural
- Sub-Issues:
- Denial of fair hearing
- Lack of opportunity to present case
- Award based on unaddressed submissions
- Damages Assessment
- Outcome: The court upheld the arbitrator's assessment of damages based on diminution in value.
- Category: Substantive
- Sub-Issues:
- Diminution in value
- Cost of cure
- Appropriate measure of damages
8. Remedies Sought
- Setting aside arbitral award
- Leave to appeal on questions of law
- Damages
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Arbitration
- Construction Disputes
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Multiplex Constructions (UK) Limited v Cleveland Bridge UK Limited | High Court of Justice | Yes | [2006] EWHC 1314 (TCC) | England and Wales | Cited regarding the concept of abatement of value. |
St Louis LLC v Final Touch Glass & Mirror Inc | Superior Court of New Jersey | Yes | 386 NJ Super 177 | New Jersey, United States | Cited for the proposition that the tribunal could use the cost of repair as a measure of diminution in value, even though the market value could be ascertained. |
State Property & Building Commission of the Department of Finance v H W Miller Construction Company Inc | Court of Appeal of Kentucky | Yes | Ky 385 SW 2d 211 | Kentucky, United States | Cited for the principle that in the absence of evidence to the contrary, it would ordinarily be presumed that the anticipated cost of remedial work would reduce the price by an equivalent amount. |
Ruxley Electronics and Construction Ltd v Forsyth | House of Lords | Yes | [1996] 1 AC 344 | United Kingdom | Cited for the legal principle that damages must be reasonable. |
Philips v Ward | Court of Appeal | Yes | [1956] 1 WLR 471 | England and Wales | Cited as illustrative authority on how to derive the value of work supplied. |
Watts v Morrow | Court of Appeal | Yes | [1991] 1 WLR 1421 | England and Wales | Cited as illustrative authority on how to derive the value of work supplied. |
Nada Fadil Al-Medenni v Mars UK Limited | Court of Appeal | Yes | [2005] EWCA Civ 1041 | England and Wales | Cited regarding the principle that parties should clearly identify the issues that arise in the litigation. |
CRW Joint Operation v PT Perusahaan Gas Negara (Persero) TBK | Court of Appeal | Yes | [2011] 4 SLR 305 | Singapore | Cited for the distinction between an erroneous exercise of an available power and the purported exercise of a power which it did not possess. |
PT Prima International Development v Kempinski Hotels SA and other appeals | Court of Appeal | Yes | [2012] 4 SLR 98 | Singapore | Cited for the role of pleadings in arbitration. |
Carillion Construction Limited v Devonport Royal Dockyard Limited | English Court of Appeal | Yes | [2005] EWCA Civ 1358 | England and Wales | Explained that it is often not practicable for an adjudicator to put to the parties his provisional conclusions for comment. |
Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte Ltd | Court of Appeal | Yes | [2007] 3 SLR(R) 66 | Singapore | Considered the authorities and distilled the principles of fairness in arbitration. |
Trustees of Rotoaira Forest Trust v Attorney-General | High Court | Yes | [1999] 2 NZLR 452 | New Zealand | The test of whether a particular decision reasonably flows from or may be foreseen from parties’ arguments is to be tested on an objective basis. |
R v Deputy Industrial Injuries Commissioner, ex parte Moore | Queen's Bench | Yes | [1965] 1 QB 456 | England and Wales | Explained the 'no evidence rule'. |
TCL Air Conditioner (Zhongshan) Co Ltd v Castel Electronics Pty Ltd | Federal Court of Australia | Yes | [2014] FCAFC 83 | Australia | Considered the 'no evidence' rule in the context of international commercial arbitration. |
Emerald Grain Australia Pty Ltd v Agrocorp International Pte Ltd | Federal Court of Australia | Yes | [2014] FCA 414 | Australia | Analysed the 'no evidence' rule from a public policy perspective. |
TMM Division Maritima SA de CV v Pacific Richfield Marine Pte Ltd | High Court | Yes | [2013] 4 SLR 972 | Singapore | The status of the 'no evidence' rule was expressly left open. |
AQU v AQV | High Court | Yes | [2015] SGHC 26 | Singapore | The status of the 'no evidence' rule was expressly left open. |
Thong Ah Fat v Public Prosecutor | Court of Appeal | Yes | [2012] 1 SLR 676 | Singapore | Acknowledged that parties are to be given a fair opportunity to be heard, but also apprised of how and why a judge has reached his decision. |
Prestige Marine Services Pte Ltd v Marubeni International Petroleum (S) Pte Ltd | High Court | Yes | [2012] 1 SLR 917 | Singapore | The inadequate provision of reasons by an arbitral tribunal is a mere error of law. |
LW Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appeal | Court of Appeal | Yes | [2013] 1 SLR 125 | Singapore | Clarified the statement of 'actual prejudice' in Soh Beng Tee. |
Lesotho Highlands Development Authority v Impregilo SpA and others | House of Lords | Yes | [2006] 1 AC 221 | United Kingdom | If the arbitrator applies the correct remedy, but does so in an incorrect way, then there is no excess of jurisdiction. |
AKN and another v ALC and others and other appeals | Court of Appeal | Yes | [2015] 3 SLR 488 | Singapore | An example of an act in excess of jurisdiction would be where an arbitral tribunal makes an arbitral award that neither party requested. |
Pacific Recreation Pte Ltd v S Y Technology Inc and another appeal | Court of Appeal | Yes | [2008] 2 SLR(R) 491 | Singapore | The decision was sufficiently reasoned and is also reasonable either as a matter of inference or from the arguments made before the Arbitrator. |
Bulfracht (Cyprus) Ltd v Boneset Shipping Co Ltd (“The Pamphilos”) | Commercial Court | Yes | [2002] 2 Lloyd’s Rep 681 | England and Wales | Arbitrators are appointed because of their professional, legal, commercial or technical expertise and the parties take the risk that, in spite of that expertise, errors of fact may be made or invalid inferences drawn without proper warning. |
Chong Ah Kwee and another v Viva Realty Pte Ltd | High Court | Yes | [1990] 1 SLR(R) 244 | Singapore | Cases where the court allowed the purchaser to reclaim moneys which it had overpaid by way of a proportionate abatement of price where property had been sold with an inaccurate and inflated estimated floor area. |
Ling Kai Seng and another v Outram Realty Pte Ltd | High Court | Yes | [1991] 1 SLR(R) 885 | Singapore | Cases where the court allowed the purchaser to reclaim moneys which it had overpaid by way of a proportionate abatement of price where property had been sold with an inaccurate and inflated estimated floor area. |
Ahong Construction (S) Pte Ltd v United Boulevard Pte Ltd | Court of Appeal | Yes | [1994] 3 SLR(R) 669 | Singapore | An award of interest is at the discretion of the arbitral tribunal. |
Chin Yoke Choong Bobby and another v Hong Lam Marine Pte Ltd | Court of Appeal | Yes | [1999] 3 SLR(R) 907 | Singapore | The provision confers a wide discretion. |
Northern Elevator Manufacturing Sdn Bhd v United Engineers (Singapore) Pte Ltd | Court of Appeal | Yes | [2004] 2 SLR(R) 494 | Singapore | A ‘question of law’ must necessarily be a finding of law which the parties dispute, that requires the guidance of the court to resolve. |
Aloe Vera of America, Inc v Asianic Food (S) Pte Ltd and another | High Court | Yes | [2006] 3 SLR(R) 174 | Singapore | The first stage of enforcing an arbitral award is a “mechanistic” one and that it need only satisfy the court that the formalistic requirements in O 69 r 7(3) of the 1997 Rules of Court were complied with. |
The Vasiliy Golovnin | High Court | Yes | [2008] 4 SLR(R) 994 | Singapore | A party applying for an ex parte court order has a duty to make full and frank disclosure of the all the facts material to the application. |
Koh Bros Building and Civil Engineering Contractor Pte Ltd v Scotts Development (Saraca) Pte Ltd | High Court | Yes | [2002] 2 SLR(R) 1063 | Singapore | A mishandling of the arbitration may include cases where the arbitral tribunal acted in excess of jurisdiction, or where it committed a breach of natural justice. |
John Holland Pty Ltd (fka John Holland Construction & Engineering Pty Ltd) v Toyo Engineering Corp (Japan) | High Court | Yes | [2001] 1 SLR(R) 443 | Singapore | The complaint, if valid, reveals no more than a plain error of law, or of a mixed fact and law. That is outside the ambit of s 17(2) of [the 1985 Act]. |
Anwar Siraj and another v Ting Kang Chung and another | High Court | Yes | [2003] 2 SLR(R) 287 | Singapore | Sets out the applicable test for prejudice required under s 17(2) of the 1985 Act. |
13. Applicable Rules
Rule Name |
---|
Rules of Court (Cap 322, R 5, 1997 Rev Ed) O 68 r 7 |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Arbitration Act (Cap 10, 1985 Rev Ed) | Singapore |
Arbitration Act (Cap 10, 2002 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Arbitral award
- External wall system
- Diminution in value
- Cost of cure
- Breach of contract
- Natural justice
- Jurisdiction
- Sub-contract works
- Independent expert
- Final sub-contract sum
15.2 Keywords
- arbitration
- construction
- breach of contract
- defective works
- Singapore
- High Court
17. Areas of Law
Area Name | Relevance Score |
---|---|
Arbitration | 95 |
Breach of Contract | 90 |
Contract Law | 85 |
Damages | 80 |
Construction Law | 75 |
Construction Contracts | 70 |
Contractual Disputes | 65 |
Jurisdiction | 60 |
16. Subjects
- Arbitration
- Construction Dispute
- Contract Law