Geocon Piling v Multistar: Construction Subcontract Dispute over KPE Bored Piling Works

Geocon Piling & Engineering Pte Ltd (in compulsory liquidation) sued Multistar Holdings Limited in the High Court of Singapore, seeking outstanding sums for construction works carried out at the Kallang-Paya Lebar Expressway (KPE) in 2004 and 2005. Geocon was the sub-subcontractor, and Multistar was the subcontractor for the bored piling works. The court, presided over by Justice Vinodh Coomaraswamy, found in favor of Geocon in part, determining that $4,343,569.35 remained due from Multistar to Geocon. Multistar also filed a counterclaim, which was rejected.

1. Case Overview

1.1 Court

High Court of the Republic of Singapore

1.2 Outcome

Judgment for Plaintiff in part.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Geocon Piling sued Multistar for outstanding sums under a construction subcontract for bored piling works. The court granted Geocon's claims in part.

1.7 Decision Date

2. Parties and Outcomes

3. Judges

Judge NameTitleDelivered Judgment
Vinodh CoomaraswamyJudgeYes

4. Counsels

4. Facts

  1. Multistar was the subcontractor for bored piling works at a section of the KPE.
  2. Geocon was the sub-subcontractor for those works.
  3. The Multistar/Geocon subcontract sum was agreed at a fixed lump sum of $26m.
  4. Resource Piling stopped all work at the ECP South Location by October 2002.
  5. Geocon ended up completing the works at the ECP South Location and at all the other locations under the Geocon/Resource Piling subcontract.
  6. The liquidator quantified Multistar’s debt to Geocon at $10,894,835.41.
  7. The Audited Accounts record that Multistar owes Geocon only $52,505.

5. Formal Citations

  1. Geocon Piling & Engineering Pte Ltd (in compulsory liquidation)vMultistar Holdings Ltd (formerly known as Multi-Con Systems Ltd) and another suit, Suit No 65 of 2011 consolidated with Suit No 500 of 2011, [2016] SGHC 240

6. Timeline

DateEvent
Land Transport Authority awarded contract C421 to Sembcorp Engineers and Constructors Pte Ltd
Sembcorp subcontracted bored piling works to Multistar
Multistar subcontracted work to Geocon
Geocon subcontracted work to Resource Piling Pte Ltd
Resource Piling stopped work at ECP South Location
Resource Piling ceased work at all locations
Multistar commenced proceedings against Resource Piling
Resource Piling commenced suit against Geocon and Multistar
Last entry for GC 1077
Geocon's latest available audited accounts dated
Resource Piling secured order winding up Geocon
Statement of Final Account signed
Action commenced by Geocon against Multistar
Trial began
Judgment issued

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that Multistar breached the subcontract with Geocon by failing to pay the full amount due.
    • Category: Substantive
  2. Limitation Act
    • Outcome: The court held that Geocon's claims were not time-barred under s 6 of the Limitation Act.
    • Category: Procedural
  3. Estoppel
    • Outcome: The court held that Geocon was not estopped from making claims against Multistar by virtue of the 2004 Litigation or from going behind its own Audited Accounts.
    • Category: Procedural

8. Remedies Sought

  1. Monetary Damages

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Geocon Piling & Engineering Pte Ltd (in compulsory liquidation) v Multistar Holdings Ltd (formerly known as Multi-Con Systems Ltd)High CourtYes[2015] 3 SLR 1213SingaporeCited for reasons for granting Geocon leave to amend its statement of claim.
Multistar Holdings Ltd v Geocon Piling & Engineering Pte LtdCourt of AppealYes[2016] 2 SLR 1SingaporeCited for dismissing Multistar’s appeal against the decision to grant Geocon leave to make its amendments.
Tay J’s judgmentHigh CourtYes[2006] SGHC 134SingaporeCited for holding that Resource Piling’s subcontract was with Geocon and not with Multistar and finding Geocon liable to Resource Piling to pay damages for breach of contract.
Dynasty Line Ltd (in liquidation) v Sukamto Sia and another and another appealCourt of AppealYes[2014] 3 SLR 277SingaporeCited for the principle that the fact that the action was commenced by Geocon’s liquidator on Geocon’s behalf does not prevent the time bar from running against Geocon.
Lee Tat Development Pte Ltd v Management Corporation of Strata Title Plan No 301Court of AppealYes[2005] 3 SLR(R) 157SingaporeCited for the requirements for an issue estoppel.
Fustar Chemicals Ltd (Hong Kong) v Liquidator of Fustar Chemicals Pte LtdCourt of AppealYes[2009] 4 SLR 458SingaporeCited for the principle that a liquidator of a company is not only entitled but obliged to go behind the audited accounts of the company in order to establish the true extent of its liabilities.
Westcoast Energy Inc v RN/AYes[1991] 1 CTC 471N/ACited for the definition of the term “reimburse”.

13. Applicable Rules

Rule Name
Rules of Court (Cap 322, R 5, 2014 Rev Ed)

14. Applicable Statutes

Statute NameJurisdiction
Limitation Act (Cap 163, 1996 Rev Ed)Singapore
Evidence Act (Cap 97, 1997 Rev Ed)Singapore
Companies Act (Cap 50, 2006 Rev Ed)Singapore
Legal Profession Act (Cap 161, 2009 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Bored piling
  • Subcontract
  • Lump sum contract
  • Variations
  • KPE
  • Project management fees
  • Reimbursement basis
  • Back charges
  • Liquidation

15.2 Keywords

  • Construction Law
  • Subcontract
  • Breach of Contract
  • Singapore
  • Building and Construction Law
  • Lump sum contract
  • Variations
  • Limitation Act
  • Estoppel

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Contract Law
  • Civil Litigation