Shimizu Corp v Stargood Construction: Payment Claims & Termination under SOPA
In Shimizu Corporation v Stargood Construction Pte Ltd, the Singapore Court of Appeal addressed whether a payment claim can be served after the termination of a construction subcontract. Shimizu terminated Stargood's subcontract, and Stargood subsequently served payment claims. The court held that the Building and Construction Industry Security of Payment Act (SOPA) does not provide an independent right to serve payment claims for works completed, regardless of the provisions of the underlying contract. The court allowed Shimizu's appeal, setting aside the lower court's orders and clarifying the relationship between SOPA and contractual terms.
1. Case Overview
1.1 Court
Court of Appeal of the Republic of Singapore1.2 Outcome
Appeal Allowed
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
Singapore Court of Appeal addresses whether payment claims can be served after contract termination under the SOPA, clarifying its interaction with contract terms.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Shimizu Corporation | Appellant, Respondent | Corporation | Appeal Allowed | Won | |
Stargood Construction Pte Ltd | Respondent, Applicant | Corporation | Appeal Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Sundaresh Menon | Chief Justice | No |
Tay Yong Kwang | Judge of Appeal | No |
Steven Chong | Judge of Appeal | Yes |
4. Counsels
4. Facts
- Shimizu engaged Stargood as a subcontractor for a project at 79 Robinson Road, Singapore.
- The subcontract incorporated the Real Estate Developers’ Association of Singapore Design and Build Conditions of Contract.
- Shimizu appointed a project director to act on its behalf, including the certification of progress payments.
- Shimizu issued a notice of default to Stargood on 4 March 2019.
- Shimizu terminated the subcontract on 22 March 2019, citing breaches by Stargood.
- Stargood served Payment Claim No 12 on 30 April 2019, after the termination.
- Stargood served Payment Claim No 13 on 31 May 2019, also after the termination.
5. Formal Citations
- Shimizu Corporation v Stargood Construction Pte Ltd, Civil Appeal No 204 of 2019, [2020] SGCA 37
6. Timeline
Date | Event |
---|---|
Letter of acceptance issued to Stargood Construction Pte Ltd | |
Shimizu Corporation issued a notice of default to Stargood Construction Pte Ltd | |
Shimizu Corporation exercised its termination rights under cl 33.2 of the Subcontract | |
Stargood Construction Pte Ltd served Payment Claim No 12 on Shimizu Corporation | |
Stargood Construction Pte Ltd served Payment Claim No 13 on Shimizu Corporation | |
Stargood Construction Pte Ltd lodged Adjudication Determination No SOP/AA203/2019 | |
Shimizu Corporation served payment response to Payment Claim No 13 | |
Adjudication Determination No SOP/AA203/2019 was dismissed | |
Stargood Construction Pte Ltd lodged Adjudication Determination No SOP/AA245/2019 | |
Adjudication Determination No SOP/AA245/2019 was dismissed | |
Stargood Construction Pte Ltd filed OS 1099 of 2019 | |
Hearing date | |
Judgment reserved |
7. Legal Issues
- Payment Claims After Termination
- Outcome: The court held that the SOPA does not provide an independent right to continue serving payment claims for works completed regardless of the provisions of the underlying contract.
- Category: Substantive
- Sub-Issues:
- Validity of payment claims served after termination
- Effect of termination clauses on payment rights
- Interpretation of Contractual Termination Clauses
- Outcome: The court interpreted the termination clauses of the subcontract to determine whether Stargood was entitled to serve payment claims after termination.
- Category: Substantive
- Sub-Issues:
- Distinction between termination of employment and termination of contract
- Effect of termination on payment certification process
- Functus Officio of Project Director
- Outcome: The court made observations on whether the Project Director became functus officio but did not make a definitive ruling.
- Category: Procedural
- Sub-Issues:
- Whether the project director's role ceased upon termination
- Impact on the validity of payment claims
8. Remedies Sought
- Setting aside of adjudication determinations
- Declaration that Stargood was entitled to serve further payment claims
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Construction Law
- Commercial Litigation
- Arbitration
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Far East Square Pte Ltd v Yau Lee Construction (Singapore) Pte Ltd | Court of Appeal | Yes | [2019] 2 SLR 189 | Singapore | Cited as the basis for determining a contractor’s entitlement to submit payment claims under the SOPA, emphasizing the importance of the underlying construction contract. |
Tienrui Design & Construction Pte Ltd v G & Y Trading and Manufacturing Pte Ltd | High Court | Yes | [2015] 5 SLR 852 | Singapore | Cited by the respondent to support the position that a claimant has an independent right under the SOPA to serve a payment claim after termination of the underlying contract. |
CHL Construction Pte Ltd v Yangguang Group Pte Ltd | High Court | Yes | [2019] 4 SLR 1382 | Singapore | Cited by the respondent to support the position that a claimant has an independent right under the SOPA to serve a payment claim after termination of the underlying contract. |
Choi Kum Peng and another v Tan Poh Eng Construction Pte Ltd | High Court | Yes | [2014] 1 SLR 1210 | Singapore | Cited by the respondent to support the position that a claimant has an independent right under the SOPA to serve a payment claim after termination of the underlying contract. |
LW Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd | High Court | Yes | [2011] 4 SLR 477 | Singapore | Cited in relation to the distinction between termination of a contractor’s employment and termination of a contract. |
Engineering Construction Pte Ltd v Attorney General | N/A | Yes | Engineering Construction Pte Ltd v Attorney General (No. 2) (1994) | N/A | Cited in relation to the effect of contract termination on the powers of an architect or engineer to certify payments. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Payment Claim
- Termination
- Subcontract
- Project Director
- Functus Officio
- Progress Payment
- SOPA
- Adjudication
- Certification
- Notice of Default
15.2 Keywords
- construction
- payment claim
- SOPA
- termination
- adjudication
- Singapore
- contract law
17. Areas of Law
16. Subjects
- Construction Dispute
- Security of Payment
- Contract Law