Huatraco Singapore Pte Ltd v Hua Rong Engineering Pte Ltd: Breach of Contract in Equipment Rental Agreement

Huatraco Singapore Pte Ltd sued Hua Rong Engineering Pte Ltd in the High Court of Singapore, Suit No 1118 of 2017, for breach of contract. The case was heard before Choo Han Teck J on 4, 5, 6 February, 31 March 2020, with judgment reserved on 28 April 2020. Huatraco claimed that Hua Rong failed to return rented equipment or returned it in a damaged state, seeking $369,214.78 in replacement and repair costs. Hua Rong counterclaimed for the return of a deposit and outstanding labour costs. The court granted judgment for Huatraco in the amount of $358,214.78, after setting off the deposit.

1. Case Overview

1.1 Court

High Court of the Republic of Singapore

1.2 Outcome

Judgment for Plaintiff

1.3 Case Type

Civil

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

Huatraco sued Hua Rong for breach of contract for failing to return rented equipment. The court found Hua Rong liable for $358,214.78.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Huatraco Singapore Pte LtdPlaintiffCorporationJudgment for PlaintiffWonLee Bik Wei, Chong Xue Er Cheryl, Alisa Toh Qian Wen, Toh Jia Jing Vivian
Hua Rong Engineering Pte LtdDefendantCorporationJudgment against DefendantLostLim Kim Hong, Nadiah Li Feng Binte Mahmood

3. Judges

Judge NameTitleDelivered Judgment
Choo Han TeckJudgeYes

4. Counsels

Counsel NameOrganization
Lee Bik WeiAllen & Gledhill LLP
Chong Xue Er CherylAllen & Gledhill LLP
Alisa Toh Qian WenAllen & Gledhill LLP
Toh Jia Jing VivianAllen & Gledhill LLP
Lim Kim HongKim & Co
Nadiah Li Feng Binte MahmoodKim & Co

4. Facts

  1. Huatraco and Hua Rong entered into a contract for the rental of equipment.
  2. Hua Rong was to rent equipment from Huatraco for five months at $55,000.
  3. Huatraco delivered equipment to Hua Rong between June and November 2016.
  4. Hua Rong returned equipment to Huatraco between February and June 2017.
  5. Huatraco claimed Hua Rong failed to return some equipment and returned others damaged.
  6. Huatraco sought $369,214.78 for replacement and repair costs.
  7. Hua Rong counterclaimed for the return of a deposit and outstanding labour costs.

5. Formal Citations

  1. Huatraco Singapore Pte Ltd v Hua Rong Engineering Pte Ltd, Suit No 1118 of 2017, [2020] SGHC 85

6. Timeline

DateEvent
Contract signed
Quotation dated
Letter of contract for the hire of equipment
Plaintiff's standard terms and conditions
Parties entered into a written contract
Defendant's rental of various equipment from the plaintiff's C60 Table Forms and Shoring System
Defendant paid a deposit of $11,000
Plaintiff made 33 deliveries of various quantities of the Equipment to the defendant
Defendant returned various quantities of the Equipment to the plaintiff
Parties entered into an agreement under which the plaintiff hired labour from it
Plaintiff was granted summary judgment for its Rental Claim
Trial began
Trial concluded
Judgment reserved

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found the defendant liable for breach of contract for failing to return equipment or returning it in a damaged state.
    • Category: Substantive
    • Sub-Issues:
      • Failure to return equipment
      • Return of damaged equipment

8. Remedies Sought

  1. Monetary Damages
  2. Late payment interest

9. Cause of Actions

  • Breach of Contract
  • Conversion

10. Practice Areas

  • Commercial Litigation
  • Construction Law

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
No cited cases

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Civil Law Act (Cap 43, 1999 Rev Ed), s 12Singapore
Unfair Contract Terms Act (Cap 396, 1994 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Equipment
  • Rental
  • Delivery Order
  • Equipment Receipt Notes
  • Deposit
  • Standard Terms and Conditions
  • Liquidated Sum

15.2 Keywords

  • breach of contract
  • equipment rental
  • construction
  • singapore
  • high court

16. Subjects

  • Contract Dispute
  • Equipment Rental
  • Construction Dispute

17. Areas of Law

  • Contract Law
  • Construction Law