DSL Integrated Solution v Triumph Electrical: Subcontract Termination Dispute
DSL Integrated Solution Pte Ltd ("DSL") sued Triumph Electrical System Engineering Pte Ltd ("Triumph Electrical") in the General Division of the High Court of Singapore, alleging breaches of a subcontract. DSL claimed Triumph Electrical wrongfully repudiated the agreement by stopping work in May 2021. Triumph Electrical counterclaimed for quantum meruit. The court, presided over by Justice Kwek Mean Luck, found that a binding agreement existed but that Triumph Electrical was justified in terminating the agreement due to DSL's failure to secure a performance bond, which resulted in non-payment for Triumph Electrical's work. The court dismissed DSL's claim for indemnity and loss of profit but allowed DSL's claim for the cost of engaging a full-time project manager and damages for inadequate manpower. The court allowed Triumph Electrical's claim for 92% of the value of the work done prior to termination.
1. Case Overview
1.1 Court
General Division of the High Court1.2 Outcome
Plaintiff's claim dismissed in part; Defendant's counterclaim allowed in part.
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
DSL Integrated Solution sued Triumph Electrical for breach of contract. The court found Triumph was justified in terminating the agreement.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
DSL Integrated Solution Pte Ltd | Plaintiff | Corporation | Claim dismissed in part | Partial | |
Triumph Electrical System Engineering Pte Ltd | Defendant | Corporation | Counterclaim allowed in part | Partial |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Kwek Mean Luck | Judge | Yes |
4. Counsels
4. Facts
- DSL was the subcontractor for electrical works at the Forett Condominium Project.
- DSL subcontracted the Electrical Works to Triumph Electrical.
- Triumph Electrical commenced work in late September 2020.
- DSL failed to provide a performance bond to CNQC.
- CNQC withheld payments due to the lack of a performance bond.
- Triumph Electrical ceased work in May 2021 due to non-payment.
- DSL terminated the purported sub-contract on 2 June 2021.
5. Formal Citations
- DSL Integrated Solution Pte Ltd v Triumph Electrical System Engineering Pte Ltd, Suit No 519 of 2021, [2022] SGHC 221
6. Timeline
Date | Event |
---|---|
Edward approached Lawrence to find out more about the Project. | |
Lawrence sent Edward documents including the Plaintiff’s quotation to the Main Contractor. | |
Lawrence met Edward at the Plaintiff’s office. | |
Edward, the Plaintiff’s Mr Allan Tan and the Main Contractor’s representative attended a meeting at the Plaintiff’s office. | |
Edward issued a quotation for the provision of electrical installation works to Lawrence. | |
Lawrence, Gary, the Plaintiff’s Mr Dan Ling, Mr Allan Tan, and Edward met at the Defendant’s office. | |
The Plaintiff sent an email enclosing a revised version of the Defendant’s quotation to the Defendant. | |
Lawrence had a telephone call with Edward about the Revised Quotation. | |
Lawrence sent a WA message to Edward regarding man-year entitlement. | |
Edward sent an email to the Plaintiff regarding man-year entitlement and site dormitory. | |
The Defendant commenced work. | |
Edward sent an email to the Main Contractor stating that documents were compiled under Triumph Electrical as DSL sub-con. | |
The Plaintiff sent a copy of the Main Contract to the Defendant and requested a meeting. | |
Gary, Mr Dan Ling, and Edward met at the Plaintiff’s office. | |
Edward sent a WA message to Gary enquiring about the bond. | |
Edward sent a WA message to Gary chasing for various things. | |
The Defendant assisted the Plaintiff to prepare its first progress claim to the Main Contractor. | |
The Main Contractor issued its first payment response. | |
The Plaintiff submitted its second progress claim to the Main Contractor. | |
The Plaintiff was engaged in negotiations with the Main Contractor in respect of the on-demand performance bond. | |
The Plaintiff submitted its third progress claim to the Main Contractor. | |
Gary informed Edward that payment could be collected next week. | |
Edward sent a WA message to Gary enquiring on the status of the performance bond. | |
The Main Contractor issued its second payment response. | |
Gary asked if the Defendant would be keen to take over the Main Contract from the Plaintiff. | |
The Main Contractor issued its third payment response. | |
Gary informed Edward that the payment for another project was ready for collection. | |
Edward sent a series of WA messages to Gary. | |
Gary emailed Edward that the Plaintiff would require the Defendant to furnish a performance bond. | |
Edward responded to Gary’s email stating that the Defendant is unable to accept the performance bonds. | |
Edward sent a WA message to Gary stating that all works will stop this week. | |
Edward sent WA messages to Gary regarding voiding the contract. | |
The Defendant’s solicitors served the Defendant’s “Notice to Cease Work”. | |
The Plaintiff terminated the purported sub-contract through its solicitors. | |
Trial began. | |
Judgment reserved. | |
Judgment issued. |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that the Defendant was justified in terminating the agreement due to the Plaintiff's failure to secure a performance bond, which resulted in non-payment for the Defendant's work.
- Category: Substantive
- Sub-Issues:
- Repudiation of contract
- Failure to perform obligations
- Related Cases:
- [2007] 4 SLR(R) 413
- [2021] 2 SLR 510
- [2001] SGHC 243
- [1994] 3 SLR(R) 1004
- Formation of Contract
- Outcome: The court found that a binding agreement existed between the parties based on the Revised Quotation and the Confirmation Email.
- Category: Substantive
- Sub-Issues:
- Acceptance
- Counter-offer
- Essential terms
- Related Cases:
- [2018] 1 SLR 50
- [2010] 3 SLR 956
- [2021] SGHC 220
- Quantum Meruit
- Outcome: The Defendant is entitled to claim for 92% of the value of the work done prior to its termination of the works on 22 May 2021.
- Category: Substantive
8. Remedies Sought
- Damages
- Indemnity
- Costs
- Interest
9. Cause of Actions
- Breach of Contract
- Quantum Meruit
10. Practice Areas
- Construction Law
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
OMG Holdings Pte Ltd v Pos Ad Sdn Bhd | High Court | Yes | [2012] 4 SLR 231 | Singapore | Cited for the principle that the court may permit an unpleaded point to be raised, provided that the other party is not taken by surprise or irreparably prejudiced. |
Lu Bang Song v Teambuild Construction Pte Ltd | High Court | Yes | [2009] SGHC 49 | Singapore | Cited for the principle that the court may permit an unpleaded point to be raised, provided that the other party is not taken by surprise or irreparably prejudiced. |
GIB Automation Pte Ltd v Deluge Fire Protection (SEA) Pte Ltd | Court of Appeal | Yes | [2007] 2 SLR(R) 918 | Singapore | Cited for the definition of a 'back-to-back' contract and the factors to consider when determining what is incorporated into a subcontract. |
Comfort Management Pte Ltd v OGSP Engineering Pte Ltd and another | High Court | Yes | [2020] SGHC 165 | Singapore | Cited for the principle that despite words of incorporation appearing in a subcontract, the subcontract and the head contract remain distinct contracts. |
Hi-Amp Engineering Pte Ltd v Technicdelta Electrical Engineering Pte Ltd | High Court | Yes | [2003] SGHC 316 | Singapore | Cited to show that there was no back-to-back contract because the defendants did not furnish the main contract documents to the plaintiff when the parties signed the sub-contract, and the plaintiff was unaware of the terms of the main contract. |
Toptip Holding Pte Ltd v Mercuria Energy Trading Pte Ltd and another appeal | Court of Appeal | Yes | [2018] 1 SLR 50 | Singapore | Cited for the principle that a contract may be formed despite the fact that some terms have not yet been finalised. |
Norwest Holdings Pte Ltd (in liquidation) v Newport Mining Ltd | High Court | Yes | [2010] 3 SLR 956 | Singapore | Cited for the principle that the determination of the essential terms in a contract is a factual inquiry that depends on the circumstances of the parties’ dealings with each other, including the nature of the transaction envisaged by the parties. |
Tan Ngiap Tong v Tan Ngep Hong | High Court | Yes | [2021] SGHC 220 | Singapore | Cited for the principle that typically, the essential terms of a contract would include the parties, the price, and the subject matter. |
Drake and Scull Engineering Limited v Higgs and Hill Northern Limited | Official Referee | Yes | (1995) 11 Const LJ 214 | England and Wales | Cited for the principle that a binding contract can exist even if some terms are not agreed upon. |
Hock Chuan Ann Construction Pte Ltd v Kimta Electric Pte Ltd | High Court | Yes | [1999] 2 SLR (R) 237 | Singapore | Cited for the principle that in some cases, the battle is won by the man who fires the last shot, the other party being taken to have agreed to his terms by conduct in proceeding to perform the agreement without objection. |
L & M Equipment Pte Ltd (formerly known as L & M Engineering Logistic Pte Ltd) v Hyundai Engineering & Construction Co Ltd and Others | High Court | Yes | [1999] SGHC 182 | Singapore | Cited as an example where the court found that there was no contract between the sub-contractor and the sub-sub-contractor, notwithstanding the fact that latter had already commenced work at the former’s request. |
RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd and another appeal | Court of Appeal | Yes | [2007] 4 SLR(R) 413 | Singapore | Cited for the situations where an innocent party is entitled to terminate a contract. |
Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd | Court of Appeal | Yes | [2021] 2 SLR 510 | Singapore | Cited for the principle that a persistent course of payment delays, or a protracted delay in the payment of a very substantial sum amounts to a repudiation of the contract. |
AL Stainless Industries Pte Ltd v Wei Sin Construction Pte Ltd | High Court | Yes | [2001] SGHC 243 | Singapore | Cited for the principle that non-payment can amount to a repudiatory breach if prolonged and substantial. |
Jia Min Building Construction Pte Ltd v Ann Lee Pte Ltd | High Court | Yes | [2004] 3 SLR(R) 288 | Singapore | Cited for the principle that a contractor/subcontractor has no general right at common law to suspend work unless this is expressly agreed upon, even if payment is wrongly withheld. |
Brani Readymixed Pte Ltd v Yee Hong Pte Ltd and another appeal | Court of Appeal | Yes | [1994] 3 SLR(R) 1004 | Singapore | Cited for the principle that a delay in payment can amount to a repudiation of the contract if the circumstances suggest that the non-paying party did not intend to pay the other party at all. |
Zhong Kai Construction Co Pte Ltd v Diamond Glass Enterprise Pte Ltd | High Court | Yes | [2021] SGHC 277 | Singapore | Cited for the principle that there was no persistent course of payments delays which justified the defendant’s repudiation of the contract because prior progress claims were not fully rejected but certified for lower sums, and the plaintiff had substantially paid the amounts that were certified. |
W Y Steel Construction Pte Ltd v Osko Pte Ltd | Court of Appeal | Yes | [2013] 3 SLR 380 | Singapore | Cited for the principle that cash flow is the life blood of those in the building and construction industry. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building and Construction Industry Security of Payment Act 2004 | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Sub-contract
- Electrical Works
- Performance Bond
- Man-Year Entitlement
- Repudiation
- Termination
- Quantum Meruit
- Main Contract
- Revised Quotation
- Confirmation Email
15.2 Keywords
- construction
- contract
- termination
- subcontract
- electrical works
- performance bond
17. Areas of Law
16. Subjects
- Construction Dispute
- Contract Law
- Termination of Contract