LBE Engineering v Double S Construction: Wrongful Termination in Construction Dispute
LBE Engineering Pte Ltd, the defendant, appealed against the District Court's decision that Double S Construction Pte Ltd, the plaintiff, was entitled to stop work and hold LBE Engineering in breach of contract for non-payment. The dispute arose from a construction project for the Jalan Besar Town Council. The High Court allowed the appeal, finding that Double S Construction wrongfully terminated the contract and allowed LBE Engineering's counterclaim for damages.
1. Case Overview
1.1 Court
General Division of the High Court1.2 Outcome
Appeal Allowed
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
LBE Engineering appealed against the decision that Double S Construction was entitled to stop work. The court allowed the appeal, finding Double S Construction wrongfully terminated the contract.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
LBE Engineering Pte Ltd | Appellant, Defendant | Corporation | Counterclaim Allowed | Won | |
Double S Construction Pte Ltd | Respondent, Plaintiff | Corporation | Claim Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Lee Seiu Kin | Judge of the High Court | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Oh Kim Heoh Mimi | Ethos Law Corporation |
Allagarsamy s/o Palaniyappan | Allagarsamy & Co |
4. Facts
- LBE Engineering engaged Double S Construction for construction work for the Jalan Besar Town Council.
- The Letter of Award outlined three sets of work for a lump sum of $243,811.
- Payment terms required Double S Construction to submit monthly progress claims.
- LBE Engineering certified and paid the first three claims.
- Disputes arose over the fourth and fifth progress payments.
- Double S Construction stopped work due to non-payment.
- LBE Engineering engaged another contractor to complete the works.
5. Formal Citations
- LBE Engineering Pte Ltd v Double S Construction Pte Ltd, DCA 31 of 2021, [2022] SGHC 92
- Jia Min Building Construction Pte Ltd v Ann Lee Pte Ltd, , [2004] SGHC 107
- Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd, , [2021] 2 SLR 510
- Republic Airconditioning (S) Pte Ltd v Shinsung Eng Co Ltd (Singapore Branch), , [2012] 2 SLR 601
- Chan Hong Seng Engrg & Const Pte Ltd v Vatten International Pte Ltd, , [2002] SGHC 124
- Far East Square Pte Ltd v Yau Lee Construction (Singapore) Pte Ltd, , [2019] 2 SLR 189
- Zhong Kai Construction Co Pte Ltd v Diamond Glass Enterprise Pte Ltd, , [2021] SGHC 277
- Double S Construction Pte Ltd v LBE Engineering Pte Ltd, , [2021] SGDC 242
6. Timeline
Date | Event |
---|---|
Building and Construction Industry Security of Payment Act 2004 enacted | |
Double S Construction submitted first claim for $32,445.00 | |
LBE Engineering certified first claim | |
Double S Construction filed second claim for $34,592.20 | |
LBE Engineering certified second claim | |
Double S Construction filed third claim for $20,589.84 | |
Double S Construction filed fourth progress payment for $82,487.10 | |
LBE Engineering certified third claim for a reduced sum of $15,604 | |
Double S Construction filed fifth progress payment for $68,640.67 | |
Double S Construction notified LBE Engineering of intention to stop work | |
Double S Construction stopped work | |
Double S Construction sent a final progress claim to LBE Engineering for $90,845.35 | |
District judge allowed the plaintiff’s claim purely on liability | |
District Court Appeal No 31 of 2021 | |
Appeal allowed as well as the defendant’s counterclaim | |
Grounds of Decision |
7. Legal Issues
- Wrongful Termination
- Outcome: The court held that the plaintiff wrongfully terminated the contract by stopping work.
- Category: Substantive
- Sub-Issues:
- Repudiation of contract
- Suspension of work
- Related Cases:
- [2004] SGHC 107
- [2021] 2 SLR 510
- Non-payment of progress claims
- Outcome: The court held that non-payment of progress claims did not justify the plaintiff's suspension of work.
- Category: Substantive
- Related Cases:
- [2004] SGHC 107
8. Remedies Sought
- Outstanding Payment
- Damages for wrongful termination
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Construction Disputes
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Jia Min Building Construction Pte Ltd v Ann Lee Pte Ltd | High Court | Yes | [2004] SGHC 107 | Singapore | Cited for the proposition that a contractor/sub-contractor has no general right at common law to suspend work unless this is expressly agreed upon. |
Lubenham Fidelities and Investments Co Ltd v South Pembrokeshire District Council | N/A | Yes | (1986) 33 BLR 46 | N/A | Cited to support the principle that the proper remedy for under-valuation is to request adjustment or take the dispute to arbitration. |
Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd | Court of Appeal | Yes | [2021] 2 SLR 510 | Singapore | Cited to support the principle that not every instance of non-payment amounts to repudiation of contract. |
Republic Airconditioning (S) Pte Ltd v Shinsung Eng Co Ltd (Singapore Branch) | N/A | Yes | [2012] 2 SLR 601 | Singapore | Cited to show an example where the subcontractor had the right to suspend work for non-payment because the contract provided for such a right. |
Chan Hong Seng Engrg & Const Pte Ltd v Vatten International Pte Ltd | High Court | Yes | [2002] SGHC 124 | Singapore | Cited to support the proposition that a sub-contractor generally has no right to suspend work at common law for non-payment. |
Far East Square Pte Ltd v Yau Lee Construction (Singapore) Pte Ltd | N/A | Yes | [2019] 2 SLR 189 | Singapore | Cited to explain the purpose of SOPA. |
Zhong Kai Construction Co Pte Ltd v Diamond Glass Enterprise Pte Ltd | High Court | Yes | [2021] SGHC 277 | Singapore | Cited to support the principle that there was no persistent course of delays or protracted delays in the payment of a substantial sum that could amount to repudiation of the contract. |
Double S Construction Pte Ltd v LBE Engineering Pte Ltd | District Court | Yes | [2021] SGDC 242 | Singapore | Reference to the trial at first instance. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
Building and Construction Industry Security of Payment Act 2004 | Singapore |
15. Key Terms and Keywords
15.1 Key Terms
- Progress claim
- Letter of Award
- Wrongful termination
- Repudiation
- Suspension of work
- SOPA
- Non-payment
15.2 Keywords
- construction
- wrongful termination
- payment dispute
- SOPA
- Singapore
17. Areas of Law
16. Subjects
- Construction Law
- Contract Law
- Termination