Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd: Liquidated Damages, Variations & SOPA

In Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd, the Appellate Division of the High Court of Singapore heard cross-appeals arising from a dispute over a subcontract for aluminium cladding works at Changi Airport. Zhong Kai Construction Co Pte Ltd claimed liquidated damages and replacement costs against Diamond Glass Enterprise Pte Ltd, who counterclaimed for payments under variation orders and the retention sum. The court allowed both appeals in part, adjusting the liquidated damages, replacement costs, and awarding payments for certain variation orders and the retention sum to Diamond Glass. The question of Diamond Glass's entitlement to its legal costs for the adjudication was remitted back to the Judge for his determination.

1. Case Overview

1.1 Court

Appellate Division of the High Court

1.2 Outcome

DG's appeal in CA 125 allowed in part and ZK's appeal in CA 129 allowed in part.

1.3 Case Type

Civil

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

Singapore court case involving Diamond Glass and Zhong Kai over liquidated damages, variation orders, and SOPA claims. Appeals allowed in part.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Diamond Glass Enterprise Pte LtdAppellant, Plaintiff in counterclaim, RespondentCorporationAppeal allowed in partPartial
Zhong Kai Construction Co Pte LtdRespondent, Plaintiff, Defendant in counterclaim, AppellantCorporationAppeal allowed in partPartial

3. Judges

Judge NameTitleDelivered Judgment
Woo Bih LiJudge of the Appellate DivisionNo
Quentin LohJudge of the Appellate DivisionYes
Hoo Sheau PengJudge of the High CourtNo

4. Counsels

4. Facts

  1. ZK engaged DG as a subcontractor for aluminium cladding works at Changi Airport.
  2. The Subcontract was divided into Phase 1 and Phase 2A works.
  3. ZK claimed liquidated damages from DG for delays in completing the works.
  4. DG counterclaimed for payments due under variation orders and the retention sum.
  5. DG abandoned the worksite on 6 June 2018.
  6. ZK engaged third parties to complete the remaining works and remedy defects.
  7. DG commenced Adjudication Application No 339 of 2019 under the SOPA.

5. Formal Citations

  1. Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd, Civil Appeal Nos 125 and 129 of 2021, [2022] SGHC(A) 44

6. Timeline

DateEvent
Letter of Award issued for the Subcontract.
ZK claims DG began to show signs of delay.
SCB states DG has not placed order for cabin glass.
DG sends letter cancelling purchase order for cabin glass.
DG states there was no delay by DG and demands payment.
DG demands payment of $149,436.99 by 12.00pm.
DG abandons the work site.
DG states it had no choice but to accept ZK’s repudiatory breach.
ZK states figures in DG's letter are untrue and misleading.
DG serves a progress claim on ZK.
ZK commences Suit No 917 of 2019.
ZK responds to DG’s progress claim.
DG commences Adjudication Application No 339 of 2019.
Adjudication Determination issued.
ZK commences Suit No 1282 of 2019.
DG obtains court order to enforce the AD as a judgment debt.
DG serves a statutory demand on ZK.
ZK files Originating Summons No 223 of 2020.
DG commences CWU 95 to wind up ZK.
ZK files HC/SUM 1577/2020 to dismiss CWU 95.
OS 223 and SUM 1577 heard in the High Court.
Court of Appeal upholds decision to stay CWU 95.
Judgment reserved.
Judgment date.

7. Legal Issues

  1. Liquidated Damages
    • Outcome: The court adjusted the liquidated damages awarded to ZK for Phase 1 works, reducing the amount by $165,600.
    • Category: Substantive
  2. Variations
    • Outcome: The court allowed DG's counterclaims for payments in respect of VO 6 and VO 8.
    • Category: Substantive
  3. Building and Construction Industry Security of Payment Act
    • Outcome: The court dismissed ZK's claim for overturning the main works allowed by the adjudicator in the AD.
    • Category: Substantive
  4. Repudiation of Contract
    • Outcome: The court found that DG wrongfully terminated the Subcontract.
    • Category: Substantive

8. Remedies Sought

  1. Monetary Damages
  2. Overturning of Adjudicated Amount

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte LtdCourt of AppealYes[2021] 2 SLR 510SingaporeUpheld the decision to stay CWU 95 until the determination of the Consolidated Suit and any appeal thereof.
Zhong Kai Construction Co Pte Ltd v Diamond Glass Enterprise Pte LtdHigh CourtNo[2021] SGHC 277SingaporeThe present dispute concerns two cross-appeals arising out of the decision of the High Court judge in this case.
LW Infrastructure Pte Ltd v Lim Chin San Contractors Pte LtdHigh CourtYes[2011] 4 SLR 477SingaporeCited for the principle that no liquidated damages accrue once a contract has been terminated, in the absence of express contractual provision to the contrary.
Triple Point Technology Inc v PTT Public Co LtdUK Supreme CourtYes[2021] AC 1148United KingdomAffirmed the proposition that the accrual of liquidated damages comes to an end on the termination of the contract.
Ho Pak Kim Realty Co Pte Ltd v Revitech Pte LtdHigh CourtNo[2010] SGHC 106SingaporeCited regarding the condition precedent for an extension of time.
Gaymark Investments Pty Ltd v Walter Construction Group Ltd (formerly Concrete Constructions Group Ltd)Northern Territory Supreme CourtNo[1999] NTSC 143AustraliaCited regarding liquidated damages and extension of time clauses.
Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No 2)Technology and Construction CourtYes[2007] EHWC 447 (TCC)England and WalesConsidered Gaymark and cast significant doubt on its correctness.
Tat Seng Machine Movers Pte Ltd v Orix Leasing Singapore LtdHigh CourtNo[2009] 4 SLR(R) 1101SingaporeCited regarding appellate intervention.
Wei Ho-Hung v Lyu JunHigh CourtNo[2022] SGHC(A) 30SingaporeCited regarding a new case on appeal.
GA Engineering Pte Ltd v Sun Moon Construction Pte LtdHigh CourtNo[2020] SGHC 167SingaporeAccepted that the operation of s 30(4) of the SOPA allows a party to an adjudication to claim for legal costs incurred by them as damages.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Liquidated Damages
  • Variation Orders
  • Retention Sum
  • Subcontract
  • Adjudication Determination
  • Phase 1 Works
  • Phase 2A Works
  • Aluminium Cladding
  • Repudiatory Breach
  • Security of Payment Act

15.2 Keywords

  • construction law
  • liquidated damages
  • variation orders
  • SOPA
  • Singapore
  • Changi Airport
  • aluminium cladding

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Contract Law
  • Arbitration Law