Pure Group v Siong Ann Engineering: Dispute over Ramp Works Contract and Payment Milestones

Pure Group (Singapore) Pte Ltd appealed a district court decision regarding a contract dispute with Siong Ann Engineering Pte Ltd over the design, supply, and installation of a temporary ramp. The High Court, presided over by Choo Han Teck J, dismissed the appeal, affirming the lower court's decision that Siong Ann Engineering was entitled to payment for fulfilling the first two milestones of the contract. The court found that Pure Group had confirmed the order and that Arup's approval was not a condition precedent for the second milestone.

1. Case Overview

1.1 Court

General Division of the High Court of the Republic of Singapore

1.2 Outcome

Appeal Dismissed

1.3 Case Type

Civil

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

Appeal regarding a contract dispute over ramp works. The court dismissed the appeal, affirming the lower court's decision in favor of Siong Ann Engineering.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Pure Group (Singapore) Pte LtdAppellantCorporationAppeal DismissedLostChia Swee Chye Kelvin
Siong Ann Engineering Pte LtdRespondentCorporationAppeal DismissedWonTan Jin Yong

3. Judges

Judge NameTitleDelivered Judgment
Choo Han TeckJudge of the High CourtYes

4. Counsels

Counsel NameOrganization
Chia Swee Chye KelvinLumen Law Corporation
Tan Jin YongLee & Lee

4. Facts

  1. Pure Group was in charge of a project converting a theatre into a restaurant and nightclub.
  2. Siong Ann Engineering was a sub-contractor for the project.
  3. The dispute concerns the design, supply, and installation of a temporary ramp.
  4. Siong Ann Engineering prepared construction materials and delivered them to the work site.
  5. Mr. Coney abruptly told Mr. Wong to stop work.
  6. The adjudicator determined that Pure Group has to pay Siong Ann Engineering $123,897.77 for work done.
  7. Pure Group engaged a lower-cost sub-contractor to complete the Ramp Works.

5. Formal Citations

  1. Pure Group (Singapore) Pte Ltd v Siong Ann Engineering Pte Ltd, District Court Appeal No 13 of 2023, [2023] SGHC 279

6. Timeline

DateEvent
Siong Ann Engineering submitted quotation
Pure Group accepted quotation
Mr. Coney instructed Mr. Wong to proceed with Ramp Works
Mr. Wong asked Mr. Coney if it was possible to receive Pure Group's purchase order
Pure Group emailed Siong Ann Engineering to stop further work
Siong Ann Engineering requested to resume Ramp Works
Siong Ann Engineering requested to resume Ramp Works
Adjudication Application No. SOP/AA435 of 2018 filed for payment
Siong Ann Engineering Pte Ltd v Pure Group (Singapore) Pte Ltd [2022] SGHC 73
Judgment reserved
Judgment issued

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that the respondent did not breach the contract.
    • Category: Substantive
    • Sub-Issues:
      • Failure to achieve milestones
      • Failure to deliver usable materials
      • Failure to complete installation
  2. Order Confirmation
    • Outcome: The court found that the first milestone of order confirmation was met upon the appellant’s acceptance of the 5 February quotation.
    • Category: Substantive
  3. Milestone Completion
    • Outcome: The court found that the lack of Arup’s approval is not a condition for the respondent’s completion of the second milestone.
    • Category: Substantive

8. Remedies Sought

  1. Recovery of payment

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Litigation
  • Construction Disputes

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Siong Ann Engineering Pte Ltd v Pure Group (Singapore) Pte LtdHigh CourtYes[2022] SGHC 73SingaporeThe case was remitted to the district court for the determination of two issues of fact.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Ramp Works
  • Order Confirmation
  • Milestone
  • Purchase Order
  • Arup Approval
  • Fabrication
  • Installation

15.2 Keywords

  • Contract
  • Breach
  • Ramp
  • Construction
  • Payment
  • Milestone

16. Subjects

  • Contract Dispute
  • Construction Law

17. Areas of Law

  • Contract Law
  • Construction Law