CWP v CWQ: Setting Aside Arbitral Award for Dredging Work Stoppages

In CWP v CWQ, the General Division of the High Court of Singapore dismissed CWP's application to set aside a partial final arbitral award dated 4 May 2022. The dispute arose from CWQ's claim for compensation for stoppages and delays in dredging works under a contract with CWP. CWP argued that the arbitral tribunal exceeded its scope and breached natural justice. The court, presided over by Justice S Mohan, found no basis to set aside the award, upholding the tribunal's decision.

1. Case Overview

1.1 Court

General Division of the High Court of the Republic of Singapore

1.2 Outcome

Claimant's application dismissed.

1.3 Case Type

Arbitration

1.4 Judgment Type

Judgment

1.5 Jurisdiction

Singapore

1.6 Description

Singapore court dismisses CWP's application to set aside an arbitral award favoring CWQ for dredging work stoppages, upholding party autonomy.

1.7 Decision Date

2. Parties and Outcomes

3. Judges

Judge NameTitleDelivered Judgment
S MohanJudgeYes

4. Counsels

4. Facts

  1. CWP engaged to carry out dredging and land reclamation works in Ruritania City Port.
  2. CWP sub-contracted the dredging works to CWQ via an agreement dated 12 May 2017.
  3. The contract was governed by English law and provided for arbitration in Singapore.
  4. CWQ was to deploy four vessels to carry out the dredging works.
  5. The works were to be completed within a 90-day period from the commencement date of 26 May 2017.
  6. CWQ sought compensation from CWP under Art 3.9 for stoppages to the operation of the Vessels.
  7. CWP completely denied any liability under Art 3.9.

5. Formal Citations

  1. CWP v CWQ, Originating Application No 419 of 2022, [2023] SGHC 61

6. Timeline

DateEvent
Contract signed
Commencement date of works
Works completed
Arbitration proceedings commenced
Award issued
Affidavit of SSJ dated
Affidavit of KFB dated
Hearing date
Judgment reserved

7. Legal Issues

  1. Scope of Submission to Arbitration
    • Outcome: The court held that the arbitral tribunal's decision was within the scope of submission to arbitration.
    • Category: Procedural
    • Sub-Issues:
      • Acceptance of unpleaded arguments
    • Related Cases:
      • [2015] 3 SLR 488
      • [2021] 2 SLR 1279
      • [2020] 5 SLR 894
      • [2021] 2 SLR 235
      • [2022] 1 SLR 505
      • [2022] 2 SLR 557
      • [2023] SGHC(I) 1
  2. Breach of Natural Justice
    • Outcome: The court held that there was no breach of natural justice by the arbitral tribunal.
    • Category: Procedural
    • Sub-Issues:
      • Failure to consider evidence
      • Failure to consider arguments
      • Denial of opportunity to present case
    • Related Cases:
      • [2007] 3 SLR(R) 86
      • [2020] 1 SLR 695
      • [2013] 4 SLR 972
      • [2022] 1 SLR 1080
  3. Interpretation of Contractual Clauses
    • Outcome: The court upheld the arbitral tribunal's interpretation of the contractual clauses.
    • Category: Substantive
    • Sub-Issues:
      • Interpretation of Article 3.9
      • Interpretation of Article 22
    • Related Cases:
      • [2015] 2 WLR 1593

8. Remedies Sought

  1. Setting aside of arbitral award

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Arbitration
  • Commercial Litigation
  • Construction Disputes

11. Industries

  • Construction
  • Marine Engineering

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
AKN and another v ALC and others and other appealsCourt of AppealYes[2015] 3 SLR 488SingaporeCited for the principle that the inference of an arbitrator's failure to consider an important pleaded issue must be clear and virtually inescapable.
Bloomberry Resorts and Hotels Inc and another v Global Gaming Philippines LLC and anotherCourt of AppealYes[2021] 2 SLR 1279SingaporeCited as a warning that courts must be wary of attempts by an aggrieved party to mount what is, in effect, an appeal in disguise.
TYN Investment Group Pte Ltd v ERC Holdings Pte Ltd and anotherN/AYes[2020] 5 SLR 894SingaporeCited for the proposition that the notice of arbitration exhaustively defines the parameters within which the arbitration must operate, but the court found the reliance misplaced.
CDM and another v CDPCourt of AppealYes[2021] 2 SLR 235SingaporeCited for the principle that in determining the scope of the parties’ submission to arbitration, the court may have regard to five sources.
CAJ and another v CAI and another appealCourt of AppealYes[2022] 1 SLR 505SingaporeCited for the principle that the five sources for determining the scope of the parties’ submission to arbitration are not discrete or independent sources.
CJA v CIZCourt of AppealYes[2022] 2 SLR 557SingaporeCited for the principle that the court must look at matters in the round to determine whether the issues in question were live issues in the arbitration.
CFJ and another v CFL and another and other mattersSingapore International Commercial CourtYes[2023] SGHC(I) 1SingaporeCited for the principle that a practical view must be taken regarding the substance of the dispute being referred to arbitration.
Soh Beng Tee & Co Pte Ltd v Fairmount Development Pte LtdN/AYes[2007] 3 SLR(R) 86SingaporeCited for the principle that a party challenging an award on the basis of a breach of natural justice must establish the breach, its connection to the award, and prejudice to its rights.
China Machine New Energy Corp v Jaguar Energy Guatemala LLC and anotherN/AYes[2020] 1 SLR 695SingaporeCited for the principle that a party challenging an award on the basis of a breach of natural justice must establish the breach, its connection to the award, and prejudice to its rights.
TMM Division Maritima SA de CV v Pacific Richfield Marine Pte LtdN/AYes[2013] 4 SLR 972SingaporeCited for the principle that a tribunal must ensure that all essential issues are dealt with, but need not address each and every argument raised by a party.
Ng Koon Yee Mickey v Mah Sau CheongN/AYes[2022] 2 SLR 1296SingaporeCited for the principle that a promisee cannot insist upon the performance of an obligation which it has prevented the promisor from performing.
Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No. 2)N/AYes(2007) 111 ConLR 78United KingdomCited for the principle that the employer cannot hold the contractor to a specified completion date, if the employer has by act or omission prevented the contractor from completing by that date.
Adyard Abu Dhabi v SD Marine ServicesN/AYes(2011) 136 ConLR 190N/ACited for the explanation that the rationale behind the prevention principle necessarily meant a delay in fact and not a notional or hypothetical delay.
Arnold v Britton and othersUK Supreme CourtYes[2015] 2 WLR 1593United KingdomCited for English law principles on contractual interpretation, stating that the language of the provision itself was clear and unambiguous in its meaning.
L W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd and another appealN/AYes[2013] 1 SLR 125SingaporeCited for the principle that to establish actual or real prejudice, the aggrieved party must be able demonstrate that the breach could reasonably have made a difference to the outcome of the arbitration.
BZW and another v BZVN/AYes[2022] 1 SLR 1080SingaporeDistinguished for its exceptional facts, where the tribunal had completely failed to even mention most of the defenses raised by the arbitration respondent.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
International Arbitration Act 1994Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Arbitration
  • Arbitral Award
  • Setting Aside
  • Party Autonomy
  • Natural Justice
  • Stoppage
  • Dredging Works
  • Time for Completion
  • Force Majeure
  • National Security Clearance
  • Import Permit
  • Demurrage

15.2 Keywords

  • arbitration
  • construction
  • contract
  • dredging
  • stoppage
  • award
  • setting aside

17. Areas of Law

16. Subjects

  • Arbitration
  • Contract Law
  • Construction Dispute