Shanghai Chong Kee v Church of St Teresa: Unconscionability in Performance Bond Call

In Shanghai Chong Kee Furniture & Construction Pte Ltd v Church of St Teresa, the High Court of Singapore dismissed an application by Shanghai Chong Kee for a declaration that the Church of St Teresa acted unconscionably in calling on a performance bond for a restoration project. Shanghai Chong Kee sought an injunction to restrain the Church from receiving payment under the bond, or alternatively, for a reduction in the bond sum to account for retention sums already held by the Church. The court, presided over by Judicial Commissioner Wong Li Kok, found no strong prima facie case of unconscionability and dismissed the application. The claimant's application for an Erinford injunction was also dismissed.

1. Case Overview

1.1 Court

General Division of the High Court

1.2 Outcome

Claimant's application dismissed

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

The High Court dismissed Shanghai Chong Kee's application to restrain Church of St Teresa from receiving payment under a performance bond, finding no unconscionable conduct.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Shanghai Chong Kee Furniture & Construction Pte LtdClaimantCorporationApplication dismissedLostLim Chong Guang Charles, Ryan Mark Lopez, Nilesh Khetan
Church of St TeresaDefendantOtherJudgment for DefendantWonTan Spring, Farahna Alam

3. Judges

Judge NameTitleDelivered Judgment
Wong Li Kok, AlexJudicial CommissionerYes

4. Counsels

Counsel NameOrganization
Lim Chong Guang CharlesShook Lin & Bok LLP
Ryan Mark LopezShook Lin & Bok LLP
Nilesh KhetanShook Lin & Bok LLP
Tan SpringWithers KhattarWong LLP
Farahna AlamWithers KhattarWong LLP

4. Facts

  1. Claimant and defendant entered into a contract on 19 August 2019 for restoration works at the defendant's church.
  2. The contract incorporated the Articles and Conditions of Contract for Minor Works 2012.
  3. Clause 26 of the Conditions of Contract required the claimant to provide a performance bond of 10% of the contract sum.
  4. The claimant delivered a performance bond dated 9 October 2019 to the defendant for $629,998.70.
  5. The contract provided for Jiudong LLP to serve as the architect for the project.
  6. Restrictions related to the COVID-19 pandemic impacted the works and progress was delayed.
  7. On 20 July 2023, the defendant made a call on the Bond.

5. Formal Citations

  1. Shanghai Chong Kee Furniture & Construction Pte Ltd v Church of St Teresa, Originating Application No 876 of 2023, [2024] SGHC 5

6. Timeline

DateEvent
Claimant and defendant entered into a contract for the Project.
Contract commencement date.
Claimant delivered the Bond to the defendant.
Contract completion date.
Claimant submitted a Notification for Relief under s 9 of the Covid-19 (Temporary Measures) Act 2020 to the defendant.
Defendant expressed its wish to assert its entitlement to claim LDs in an email to the Architect.
Completion Certificate issued.
Claimant was placed under a moratorium pursuant to s 64 of the Insolvency, Restructuring and Dissolution Act 2018.
Defendant made a call on the Bond.
Claimant took out the present originating application seeking a declaration that the defendant’s call on the Bond was unconscionable.
Interim injunction granted restraining the defendant from receiving payment from Lonpac under the Bond.
Oral decision dismissing the claimant’s application for an injunction was delivered.
Claimant filed a notice of appeal and sought an order for an Erinford injunction.
Judgment date.
Judgment date.

7. Legal Issues

  1. Unconscionability
    • Outcome: The court found no strong prima facie case of unconscionability on the part of the defendant.
    • Category: Substantive
    • Sub-Issues:
      • Abuse
      • Unfairness
      • Dishonesty
    • Related Cases:
      • [2012] 3 SLR 352
  2. Entitlement to Liquidated Damages
    • Outcome: The court did not rule on the merits of whether the liquidated damages claim was contractually and legally justified.
    • Category: Substantive
  3. Erinford Injunction
    • Outcome: The court dismissed the claimant's application for an Erinford injunction.
    • Category: Procedural
    • Related Cases:
      • [1974] 2 WLR 749

8. Remedies Sought

  1. Declaration that the defendant’s call on the Bond was unconscionable
  2. Injunction to restrain the defendant from receiving payment from Lonpac on the Bond
  3. Reduction in the Bond sum that the defendant is allowed to call on and receive in order to account for the retention sum

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Construction Law
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
BS Mount Sophia Pte Ltd v Join-Aim Pte LtdCourt of AppealYes[2012] 3 SLR 352SingaporeCited as the leading case summarizing the law on unconscionability in the context of calls on performance bonds in construction contracts.
JK Integrated (Pte Ltd) v 50 Robinson Pte Ltd and anotherHigh CourtYes[2015] SGHC 57SingaporeCited for the principle that a mistaken but bona fide call on a performance bond would not fall foul of the doctrine of unconscionability.
Dauphin Offshore Engineering & Trading Pte Ltd v The Private Office of HRH Sheikh Sultan bin Khalifa bin Zayed Al NahyanHigh CourtYes[2000] 1 SLR(R) 117SingaporeCited for the principle that a high degree of strictness must be applied to the claimant’s case, with the claimant required to establish a clear case of fraud or unconscionability, and mere allegations are insufficient.
Bocotra Construction Pte Ltd and others v Attorney-GeneralCourt of AppealYes[1995] 2 SLR(R) 262SingaporeCited for the principle that a high degree of strictness must be applied to the claimant’s case, with the claimant required to establish a clear case of fraud or unconscionability, and mere allegations are insufficient.
Anwar Siraj and another v Teo Hee Lai Building Construction Pte LtdCourt of AppealYes[2003] 1 SLR(R) 394SingaporeCited for the principle that the court does not engage in a detailed merits review when hearing an application to injunct the call on a performance bond.
CEX v CEY and anotherHigh CourtYes[2021] 3 SLR 571SingaporeCited for the principle that when the architect is called on to exercise his independent judgment and issue certificates, he cannot be the agent of the employer.
Hiap Hong & Co Pte Ltd v Hong Huat Development Co (Pte) LtdHigh CourtYes[2001] 1 SLR(R) 458SingaporeCited for the principle that when executing duties, the Architect was not acting as the defendant’s agent.
Eltraco International Pte Ltd v CGH Development Pte LtdCourt of AppealYes[2000] 3 SLR(R) 198SingaporeCited for the principle that the court should take a broad approach and decide whether the present call on the Bond gave the defendant ample security, without being that inordinate as to be unconscionable.
SH Design & Build Pte Ltd v BD Cranetech Pte LtdHigh CourtYes[2018] SGHC 133SingaporeCited regarding the form of application for the Erinford injunction.
Sin Herh Construction Pte Ltd v Hyundai Engineering & Construction Co Ltd and anotherHigh CourtYes[2017] SGHC 3SingaporeCited regarding the form of application for the Erinford injunction.
Erinford Properties Ltd and Another v Cheshire County CouncilUnknownYes[1974] 2 WLR 749England and WalesCited for the grounds on which an Erinford injunction should be granted.

13. Applicable Rules

Rule Name
Rules of Court 2021
Architects Rules, The Schedule (Code of Professional Conduct and Ethics), Part I, Rule 3.-(1)

14. Applicable Statutes

Statute NameJurisdiction
Covid-19 (Temporary Measures) Act 2020Singapore
Insolvency, Restructuring and Dissolution Act 2018Singapore

15. Key Terms and Keywords

15.1 Key Terms

  • Performance Bond
  • Unconscionability
  • Liquidated Damages
  • COVID-19 (Temporary Measures) Act 2020
  • COTMA
  • Architect's Certificate
  • Retention Sum
  • Erinford Injunction

15.2 Keywords

  • Performance bond
  • Unconscionability
  • Construction contract
  • Injunction
  • Singapore
  • COVID-19
  • Building and Construction Law

16. Subjects

  • Construction Law
  • Contract Law
  • Injunctions
  • Performance Bonds

17. Areas of Law

  • Building and Construction Law
  • Injunctions
  • Contract Law