Seraya Energy Pte Ltd
Seraya Energy Pte Ltd is a corporation in Singapore's legal system. The party has been involved in 3 cases in Singapore's courts. Represented by 7 counsels. Through 1 law firm. They have been involved in 3 complex cases, representing 100.0% of their total caseload.
Legal Representation
Seraya Energy Pte Ltd has been represented by 1 law firm and 7 counsels.
Law Firm | Cases Handled |
---|---|
TSMP Law Corporation | 3 cases |
Case Complexity Analysis
Analysis of Seraya Energy Pte Ltd's case complexity based on the number of parties involved and case characteristics.
Complexity Overview
- Average Parties per Case
- 4.0
- Complex Cases
- 3 (100.0%)
- Cases with more than 3 parties
Complexity by Case Type
Type | Cases |
---|---|
Lost | 24.0 parties avg |
Partial | 14.0 parties avg |
Complexity Trends Over Time
Year | Cases |
---|---|
2019 | 34.0 parties avg |
Case Outcome Analytics
Analysis of Seraya Energy Pte Ltd's case outcomes, including distribution by type, yearly trends, and monetary outcomes where applicable.
Outcome Distribution
Outcome Type | Cases |
---|---|
Lost | 2(66.7%) |
Partial | 1(33.3%) |
Monetary Outcomes
Currency | Average |
---|---|
SGD | 390,000.002 cases |
Yearly Outcome Trends
Year | Total Cases |
---|---|
2019 | 2 21 |
Case History
Displaying all 3 cases
Case | Role | Outcome |
---|---|---|
17 Apr 2019 | Plaintiff, Defendant in Counterclaim | LostSeraya Energy Pte Ltd is to pay Denka Advantech Private Limited 90% of the costs of the action, on a standard basis, from the date the offer to settle was served. This is fixed at $390,000. Assumed SGD as the judgment originates from Singapore. |
28 Jan 2019 | Plaintiff, Defendant in Counterclaim | LostSeraya Energy is to pay Denka Advantech 90% of the costs of the action, on a standard basis, from the date the offer to settle was served. This is fixed at $390,000 (assumed SGD, as the judgment originates from Singapore). |
01 Jan 2019 | Plaintiff, Defendant in Counterclaim | PartialJudgment for Plaintiff in part; Liquidated damages provisions deemed unenforceable; Damages to be assessed based on common law principles. Currency assumed to be SGD, the currency of the jurisdiction. |