Samwoh Asphalt v Sum Cheong: Performance Bond Dispute & Interlocutory Restraint
In Samwoh Asphalt Premix Pte Ltd v Sum Cheong Piling Pte Ltd, the High Court of Singapore, on 2001-07-05, heard an application by Samwoh Asphalt Premix Pte Ltd for an interlocutory restraint order against Sum Cheong Piling Pte Ltd to prevent them from receiving funds under a performance guarantee. The court, presided over by Justice G P Selvam, denied the application, holding that the performance guarantee was in effect a demand guarantee and that the demand was justified. The court emphasized that applications for interlocutory restraint are improper in such cases.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Application for interlocutory restraint order denied.
1.3 Case Type
Civil
1.4 Judgment Type
Judgment
1.5 Jurisdiction
Singapore
1.6 Description
Samwoh Asphalt sought to restrain Sum Cheong from receiving funds under a performance guarantee. The court denied the order, emphasizing the nature of demand guarantees.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Samwoh Asphalt Premix Pte Ltd | Plaintiff | Corporation | Application for interlocutory restraint order denied | Lost | |
Sum Cheong Piling Pte Ltd | Defendant | Corporation | Application for interlocutory restraint order denied | Won | |
ECICS-COFACE Guarantee Company (Singapore) Ltd | Defendant | Corporation | Neutral | Neutral |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
G P Selvam | Judge | Yes |
4. Counsels
4. Facts
- Samwoh Asphalt Premix Pte Ltd sought to restrain Sum Cheong Piling Pte Ltd from receiving moneys under a performance guarantee.
- SC Piling had a principal contract with the Ministry of Defence for construction of a runway.
- SC Piling subcontracted part of the works to Gim Chuan Contractor Pte Ltd.
- Gim Chuan made a sub-subcontract with Samwoh Asphalt Premix Pte Ltd.
- The performance guarantee was issued by Ecics-Coface Guarantee Company (Singapore) Ltd.
- The performance guarantee was given in substitution of a cash deposit.
- The performance guarantee was for S$500,000.00.
5. Formal Citations
- Samwoh Asphalt Premix Pte Ltd v Sum Cheong Piling Pte Ltd and Another, Suit 245/2000, SIC 587/2001, [2001] SGHC 170
6. Timeline
Date | Event |
---|---|
Performance guarantee given | |
Subcontract dated between Samwoh Asphalt Premix Pte Ltd and Gim Chuan Contractor Pte Ltd | |
Suit filed | |
Judgment issued |
7. Legal Issues
- Whether demand under performance guarantee was justified
- Outcome: The court held that the demand was justified because it was made to achieve the very purpose for which it was procured by Sum Cheong Piling Pte Ltd.
- Category: Substantive
- Whether application for interlocutory restraint order was proper
- Outcome: The court held that an application for interlocutory restraint is improper.
- Category: Procedural
8. Remedies Sought
- Interlocutory Restraint Order
9. Cause of Actions
- Breach of Contract
10. Practice Areas
- Commercial Litigation
- Construction Law
11. Industries
- Construction
- Banking
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
No cited cases |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Performance Guarantee
- Demand Guarantee
- Interlocutory Restraint Order
- Unconscionable Conduct
15.2 Keywords
- performance bond
- demand guarantee
- interlocutory restraint
- construction
- Singapore
17. Areas of Law
Area Name | Relevance Score |
---|---|
Performance Bond | 85 |
Contract Law | 70 |
Injunctions | 60 |
Unconscionability | 50 |
16. Subjects
- Construction Dispute
- Banking
- Performance Bonds
- Demand Guarantees