Teo Hee Lai v Anwar Siraj: Interim Injunction Against Performance Bond Call Due to Unconscionability

In Teo Hee Lai Building Construction Pte Ltd v Anwar Siraj and Another, the High Court of Singapore heard an appeal regarding an interim injunction to restrain the respondents from receiving payment under a performance bond. The appellant, Teo Hee Lai Building Construction Pte Ltd, sought the injunction based on allegations of unconscionability. The High Court allowed the appeal, restoring the interim injunction, finding sufficient evidence of unconscionability on the part of the respondents.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Appeal Allowed

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

The High Court granted an interim injunction restraining Anwar Siraj from receiving payment under a performance bond due to potential unconscionability.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Teo Hee Lai Building Construction Pte LtdAppellantCorporationAppeal AllowedWonS Thulasidass
Anwar SirajRespondentIndividualAppeal DismissedLostAlvin Chang
Khoo Cheng Neo, NormaRespondentIndividualAppeal DismissedLostAlvin Chang

3. Judges

Judge NameTitleDelivered Judgment
Lee Seiu KinJudicial CommissionerYes

4. Counsels

Counsel NameOrganization
S ThulasidassLing Das & Partners
Alvin ChangKhattar Wong & Partners

4. Facts

  1. Appellant contracted to build a house for the Respondents for $1.2 million.
  2. Appellant procured a performance bond for $120,000 from The Tai Ping Insurance Company Ltd.
  3. Respondents made a demand to the Insurer for payment under the performance bond.
  4. Appellant alleged substantial completion of works with only basement painting remaining.
  5. Appellant claimed the Respondents were holding about $290,000 of the Appellant's monies.
  6. Appellant alleged denial of opportunity to carry out remedial works during the maintenance period.
  7. Appellant gave notice of arbitration.

5. Formal Citations

  1. Teo Hee Lai Building Construction Pte Ltd v Anwar Siraj and Another, DC Suit 4023/2001, RAS 6/2002, [2002] SGHC 139

6. Timeline

DateEvent
Contract signed
Performance bond procured
Appellant asserted substantial completion of works
List of defects forwarded to architect
Handover inspection arranged
Respondents moved in
Appellant proposed dates for inspection of defects
Notice of Arbitration given
Demand made for payment under the performance bond
Writ taken out in this action
Interim injunction granted
Respondents applied to discharge the injunction
Injunction set aside
Appeal heard and allowed, interim injunction restored
Notice of appeal lodged against decision of 31 January 2002
Grounds of Decision

7. Legal Issues

  1. Unconscionability
    • Outcome: The court found sufficient evidence of unconscionability to restrain the respondents from making a demand or receiving payment under the performance bond until the matter can be determined in arbitration.
    • Category: Substantive
    • Sub-Issues:
      • Oppressive conduct
      • Denial of contractual rights
    • Related Cases:
      • [1999] 4 SLR 604
      • Suit No. 1715 of 1995, 11 July 1996
  2. Interim Injunction
    • Outcome: The court restored the interim injunction, finding that despite some material non-disclosure, the balance of convenience favored maintaining the injunction due to potential unconscionability.
    • Category: Procedural
    • Sub-Issues:
      • Material non-disclosure
      • Balance of convenience
    • Related Cases:
      • [2000] 2 SLR 750
      • [2000] 1 SLR 657

8. Remedies Sought

  1. Injunctive Relief
  2. Access to property for rectification works

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Litigation
  • Construction Law
  • Arbitration
  • Performance Bonds

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
GHL v Unitrack Building ConstructionCourt of AppealYes[1999] 4 SLR 604SingaporeCited for the principle that unconscionability is a ground for granting an injunction against a call on a performance bond.
Tay Long Kee Impex Pte Ltd v. Tan Beng Huwah (t/a Sin Kwang Wah)N/AYes[2000] 2 SLR 750SingaporeCited for the principle that the court retains discretion to continue an injunction despite material non-disclosure.
Raymond Construction Pte Ltd v Low Yang Tong & AnorN/AYesSuit No. 1715 of 1995, 11 July 1996SingaporeCited for elaborating on the concept of unconscionability in relation to performance bonds.
Dauphin Offshore Engineering & Trading Pte Ltd v The Private Office of HRH Skeikh Sultan bin Khalifa bin Zayed Al NahyanCourt of AppealYes[2000] 1 SLR 657SingaporeCited for the standard of proof required to show unconscionability in interlocutory proceedings.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Performance bond
  • Interim injunction
  • Unconscionability
  • Completion Certificate
  • Rectification works
  • Maintenance period
  • Arbitration
  • Defects
  • Architect
  • Claims consultant

15.2 Keywords

  • construction
  • performance bond
  • injunction
  • unconscionability
  • arbitration

16. Subjects

  • Construction Dispute
  • Contract Law
  • Arbitration
  • Performance Bonds
  • Injunctions

17. Areas of Law

  • Contract Law
  • Construction Law
  • Injunctions
  • Arbitration Law