Thyssen Hynnebeck Singapore Pte Ltd v TTJ Civil Engineering Pte Ltd: Formwork Contract Dispute

In a dispute between Thyssen Hynnebeck Singapore Pte Ltd and TTJ Civil Engineering Pte Ltd, the High Court of Singapore, presided over by Judith Prakash J, addressed a claim by the plaintiff for outstanding payment, compensation for unreturned and damaged formwork, and the cost of additional materials. The defendant counterclaimed for overpayment and breach of contract. The court allowed the plaintiff's appeal in part, ordering interlocutory judgment for the plaintiff regarding the unreturned formwork, with damages to be assessed. The court found that the defendant was responsible for assembling the formwork and liable for the cost of formwork not redelivered.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Appeal allowed in part. Interlocutory judgment entered for the plaintiff regarding the formwork not returned by the defendant, with damages to be assessed.

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Dispute over a formwork contract. The court found the defendant liable for the cost of formwork not returned to the plaintiff.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
TTJ Civil Engineering Pte LtdDefendantCorporationInterlocutory judgment entered against defendantLost
Thyssen Hynnebeck Singapore Pte LtdPlaintiffCorporationAppeal allowed in partPartial

3. Judges

Judge NameTitleDelivered Judgment
Judith PrakashJudgeYes

4. Counsels

4. Facts

  1. The plaintiff and defendant entered into a contract for the sale and buy-back of a formwork system.
  2. The defendant obtained a sub-contract for the construction of a depot for the Singapore Mass Rapid Transit System.
  3. The contract included a buy-back guarantee for 40% of the standard sale equipment.
  4. The defendant admitted to cutting and consuming parts of the formwork during assembly.
  5. The defendant did not return all of the formwork to the plaintiff.

5. Formal Citations

  1. Thyssen Hynnebeck Singapore Pte Ltd v TTJ Civil Engineering Pte Ltd, Suit 766/2001/K, RA 200/2001, [2002] SGHC 21

6. Timeline

DateEvent
Parties entered into a contract for the plaintiff to sell formwork to the defendant.
Plaintiff filed action against the defendant.
High Court allowed the plaintiff's appeal in part.

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that the defendant had breached the contract by failing to redeliver the formwork as required.
    • Category: Substantive
    • Sub-Issues:
      • Failure to redeliver purchased goods
      • Cutting and consuming materials

8. Remedies Sought

  1. Monetary Damages
  2. Compensation for lost formwork
  3. Compensation for damaged formwork

9. Cause of Actions

  • Breach of Contract

10. Practice Areas

  • Commercial Litigation
  • Construction Law

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
No cited cases

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Formwork
  • Buy-back guarantee
  • Pre-assembly
  • Redelivery
  • Construction
  • KST Table Form
  • Manto Column Form

15.2 Keywords

  • Formwork
  • Construction
  • Contract
  • Singapore
  • Breach of Contract

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Contract Law