Lam Hong Leong Aluminium v Lian Teck Huat: Guarantee, Construction Contract Dispute
Lam Hong Leong Aluminium Pte Ltd, specialist aluminium cladding contractors, sued Lian Teck Huat Construction Pte Ltd and Chew Joon Huat in the High Court of Singapore on March 10, 2003, for claims related to progress payments for work done under a subcontract. The court, presided over by Justice Lai Siu Chiu, found in favor of Lam Hong Leong Aluminium, awarding judgment against Lian Teck Huat Construction and holding Chew Joon Huat liable under a personal guarantee. The court dismissed the defendants' counterclaim.
1. Case Overview
1.1 Court
High Court1.2 Outcome
Judgment for Plaintiff
1.3 Case Type
Civil
1.4 Judgment Type
Grounds of Decision
1.5 Jurisdiction
Singapore
1.6 Description
Specialist aluminium cladding contractors sue building contractors for progress payments. Court considers guarantee and reasonable business meaning in construction contract.
1.7 Decision Date
2. Parties and Outcomes
Party Name | Role | Type | Outcome | Outcome Type | Counsels |
---|---|---|---|---|---|
Lam Hong Leong Aluminium Pte Ltd | Plaintiff | Corporation | Judgment for Plaintiff | Won | |
Lian Teck Huat Construction Pte Ltd | Defendant | Corporation | Counterclaim Dismissed | Lost | |
Chew Joon Huat | Defendant | Individual | Counterclaim Dismissed | Lost |
3. Judges
Judge Name | Title | Delivered Judgment |
---|---|---|
Lai Siu Chiu | Judge | Yes |
4. Counsels
Counsel Name | Organization |
---|---|
Lek Yi Siang | Drew & Napier LLC |
Michael Por | Tan Lee & Partners |
Angeline Toh | Tan Lee & Partners |
4. Facts
- Lam Hong Leong Aluminium was subcontracted by Lian Teck Huat Construction for aluminium cladding work.
- No formal subcontract was executed between the parties, despite a clause in the Letter of Award requiring it.
- The plaintiffs submitted two applications for extensions of time, which were not responded to by the defendants.
- The first defendants consistently underpaid the plaintiffs' progress claims.
- Chew Joon Huat provided two guarantees for the payment of the plaintiffs' progress claims.
- The first defendants alleged delays and defective workmanship on the part of the plaintiffs.
- The Architects imposed liquidated damages on the first defendants due to delays in the project.
5. Formal Citations
- Lam Hong Leong Aluminium Pte Ltd v Lian Teck Huat Construction Pte Ltd and Another, Suit 1497/2001, [2003] SGHC 53
6. Timeline
Date | Event |
---|---|
Plaintiffs' quotation submitted | |
Main contract commencement date | |
Letter of Award from first defendants to plaintiffs | |
Plaintiffs submitted colour chart | |
Plaintiffs commenced submission of shop drawings for the Genting block | |
Plaintiffs commenced submission of shop drawings for the Tannery block | |
First defendants' master programme faxed to the plaintiffs | |
Plaintiffs' installation programme starting date for the Genting block | |
Plaintiffs responded with their own installation programme | |
Architects selected four colours | |
Architects selected another two colours | |
Plaintiffs followed up with submission of colour samples | |
Architects confirmed the colour location of the panels on Genting block | |
Final submissions for the Genting block were made | |
Plaintiffs' progress payments totalled $246,522.15 | |
Completion date for the subcontract works | |
See Choon Howe Jeffrey met the second defendant | |
Plaintiffs wrote to the first defendants to request for payment of $150,000 by 9 March 2001 | |
Completion date for the main contract works | |
Outstanding progress claims totalled $529,875 | |
See met Chew and requested a personal guarantee from him | |
First guarantee provided by Chew | |
See met Chew again and procured a fresh guarantee | |
Second guarantee from Chew | |
Liquidated damages imposed on the first defendants retrospectively | |
Plaintiffs submitted first application for extensions of time | |
First defendants applied for EOT from the Architects | |
First defendants failed to make any payment after this date | |
Plaintiffs' 12th progress claim | |
Plaintiffs' 13th progress claim | |
Plaintiffs' 14th progress claim | |
Plaintiffs submitted subsequent letter for extensions of time | |
Defendants alleged that the plaintiffs stopped work | |
Architects' letter giving notice that liquidated damages would be imposed on the first defendants retrospectively, from 1 June 2001 | |
Plaintiffs commenced proceedings | |
Measurements for the Genting block were finally taken | |
Plaintiffs requested site measurements to be taken of the Tannery block | |
Summary judgment against the first defendants in the sum of $100,000 | |
Date of the defence | |
Architects made further deductions of $204,298.29 and $76,368 | |
Decision Date |
7. Legal Issues
- Breach of Contract
- Outcome: The court found that the first defendants had breached the contract by failing to make timely and full progress payments to the plaintiffs.
- Category: Substantive
- Sub-Issues:
- Failure to make progress payments
- Delay in completion of works
- Enforceability of Guarantee
- Outcome: The court held that the second guarantee was enforceable against Chew Joon Huat, finding that there was sufficient consideration and that the guarantee should be given a reasonable business meaning.
- Category: Substantive
- Sub-Issues:
- Consideration for guarantee
- Interpretation of guarantee terms
- Incorporation of Main Contract Terms into Subcontract
- Outcome: The court ruled that the terms of the main contract were not incorporated into the subcontract between the plaintiffs and the first defendants because the plaintiffs were never shown the main contract documents and did not sign a subcontract with similar terms.
- Category: Substantive
- Sub-Issues:
- Privity of contract
- Express incorporation
8. Remedies Sought
- Monetary Damages
9. Cause of Actions
- Breach of Contract
- Enforcement of Guarantee
10. Practice Areas
- Construction Disputes
- Commercial Litigation
11. Industries
- Construction
12. Cited Cases
Case Name | Court | Affirmed | Citation | Jurisdiction | Significance |
---|---|---|---|---|---|
Imperial Steel Drum Manufacturers Sdn Bhd v Wong Kin Heng | High Court | Yes | [1997] 2 SLR 695 | Singapore | Cited for the principle that guarantees should be given a reasonable, business meaning and should not be construed so as to render the guarantee ineffective or illusory. |
Hyundai Shipbuilding v Pournaras | N/A | No | Hyundai Shipbuilding v Pournaras [1978] 2 Lloyd's Rep 502 | N/A | Commercial purpose of the guarantee was that the plaintiffs get their money from the defendant if they cannot get it from Automatic. |
13. Applicable Rules
Rule Name |
---|
No applicable rules |
14. Applicable Statutes
Statute Name | Jurisdiction |
---|---|
No applicable statutes |
15. Key Terms and Keywords
15.1 Key Terms
- Guarantee
- Letter of Award
- Progress Payments
- Subcontract
- Liquidated Damages
- Shop Drawings
- Clerk-of-Works
- Extensions of Time
- Site Measurements
- Defective Works
15.2 Keywords
- construction contract
- guarantee
- progress payments
- aluminium cladding
- Singapore
- High Court
17. Areas of Law
16. Subjects
- Construction Dispute
- Contract Law
- Guarantee Law