Lam Hong Leong Aluminium v Lian Teck Huat: Guarantee, Construction Contract Dispute

Lam Hong Leong Aluminium Pte Ltd, specialist aluminium cladding contractors, sued Lian Teck Huat Construction Pte Ltd and Chew Joon Huat in the High Court of Singapore on March 10, 2003, for claims related to progress payments for work done under a subcontract. The court, presided over by Justice Lai Siu Chiu, found in favor of Lam Hong Leong Aluminium, awarding judgment against Lian Teck Huat Construction and holding Chew Joon Huat liable under a personal guarantee. The court dismissed the defendants' counterclaim.

1. Case Overview

1.1 Court

High Court

1.2 Outcome

Judgment for Plaintiff

1.3 Case Type

Civil

1.4 Judgment Type

Grounds of Decision

1.5 Jurisdiction

Singapore

1.6 Description

Specialist aluminium cladding contractors sue building contractors for progress payments. Court considers guarantee and reasonable business meaning in construction contract.

1.7 Decision Date

2. Parties and Outcomes

Party NameRoleTypeOutcomeOutcome TypeCounsels
Lam Hong Leong Aluminium Pte LtdPlaintiffCorporationJudgment for PlaintiffWon
Lian Teck Huat Construction Pte LtdDefendantCorporationCounterclaim DismissedLost
Chew Joon HuatDefendantIndividualCounterclaim DismissedLost

3. Judges

Judge NameTitleDelivered Judgment
Lai Siu ChiuJudgeYes

4. Counsels

4. Facts

  1. Lam Hong Leong Aluminium was subcontracted by Lian Teck Huat Construction for aluminium cladding work.
  2. No formal subcontract was executed between the parties, despite a clause in the Letter of Award requiring it.
  3. The plaintiffs submitted two applications for extensions of time, which were not responded to by the defendants.
  4. The first defendants consistently underpaid the plaintiffs' progress claims.
  5. Chew Joon Huat provided two guarantees for the payment of the plaintiffs' progress claims.
  6. The first defendants alleged delays and defective workmanship on the part of the plaintiffs.
  7. The Architects imposed liquidated damages on the first defendants due to delays in the project.

5. Formal Citations

  1. Lam Hong Leong Aluminium Pte Ltd v Lian Teck Huat Construction Pte Ltd and Another, Suit 1497/2001, [2003] SGHC 53

6. Timeline

DateEvent
Plaintiffs' quotation submitted
Main contract commencement date
Letter of Award from first defendants to plaintiffs
Plaintiffs submitted colour chart
Plaintiffs commenced submission of shop drawings for the Genting block
Plaintiffs commenced submission of shop drawings for the Tannery block
First defendants' master programme faxed to the plaintiffs
Plaintiffs' installation programme starting date for the Genting block
Plaintiffs responded with their own installation programme
Architects selected four colours
Architects selected another two colours
Plaintiffs followed up with submission of colour samples
Architects confirmed the colour location of the panels on Genting block
Final submissions for the Genting block were made
Plaintiffs' progress payments totalled $246,522.15
Completion date for the subcontract works
See Choon Howe Jeffrey met the second defendant
Plaintiffs wrote to the first defendants to request for payment of $150,000 by 9 March 2001
Completion date for the main contract works
Outstanding progress claims totalled $529,875
See met Chew and requested a personal guarantee from him
First guarantee provided by Chew
See met Chew again and procured a fresh guarantee
Second guarantee from Chew
Liquidated damages imposed on the first defendants retrospectively
Plaintiffs submitted first application for extensions of time
First defendants applied for EOT from the Architects
First defendants failed to make any payment after this date
Plaintiffs' 12th progress claim
Plaintiffs' 13th progress claim
Plaintiffs' 14th progress claim
Plaintiffs submitted subsequent letter for extensions of time
Defendants alleged that the plaintiffs stopped work
Architects' letter giving notice that liquidated damages would be imposed on the first defendants retrospectively, from 1 June 2001
Plaintiffs commenced proceedings
Measurements for the Genting block were finally taken
Plaintiffs requested site measurements to be taken of the Tannery block
Summary judgment against the first defendants in the sum of $100,000
Date of the defence
Architects made further deductions of $204,298.29 and $76,368
Decision Date

7. Legal Issues

  1. Breach of Contract
    • Outcome: The court found that the first defendants had breached the contract by failing to make timely and full progress payments to the plaintiffs.
    • Category: Substantive
    • Sub-Issues:
      • Failure to make progress payments
      • Delay in completion of works
  2. Enforceability of Guarantee
    • Outcome: The court held that the second guarantee was enforceable against Chew Joon Huat, finding that there was sufficient consideration and that the guarantee should be given a reasonable business meaning.
    • Category: Substantive
    • Sub-Issues:
      • Consideration for guarantee
      • Interpretation of guarantee terms
  3. Incorporation of Main Contract Terms into Subcontract
    • Outcome: The court ruled that the terms of the main contract were not incorporated into the subcontract between the plaintiffs and the first defendants because the plaintiffs were never shown the main contract documents and did not sign a subcontract with similar terms.
    • Category: Substantive
    • Sub-Issues:
      • Privity of contract
      • Express incorporation

8. Remedies Sought

  1. Monetary Damages

9. Cause of Actions

  • Breach of Contract
  • Enforcement of Guarantee

10. Practice Areas

  • Construction Disputes
  • Commercial Litigation

11. Industries

  • Construction

12. Cited Cases

Case NameCourtAffirmedCitationJurisdictionSignificance
Imperial Steel Drum Manufacturers Sdn Bhd v Wong Kin HengHigh CourtYes[1997] 2 SLR 695SingaporeCited for the principle that guarantees should be given a reasonable, business meaning and should not be construed so as to render the guarantee ineffective or illusory.
Hyundai Shipbuilding v PournarasN/ANoHyundai Shipbuilding v Pournaras [1978] 2 Lloyd's Rep 502N/ACommercial purpose of the guarantee was that the plaintiffs get their money from the defendant if they cannot get it from Automatic.

13. Applicable Rules

Rule Name
No applicable rules

14. Applicable Statutes

Statute NameJurisdiction
No applicable statutes

15. Key Terms and Keywords

15.1 Key Terms

  • Guarantee
  • Letter of Award
  • Progress Payments
  • Subcontract
  • Liquidated Damages
  • Shop Drawings
  • Clerk-of-Works
  • Extensions of Time
  • Site Measurements
  • Defective Works

15.2 Keywords

  • construction contract
  • guarantee
  • progress payments
  • aluminium cladding
  • Singapore
  • High Court

17. Areas of Law

16. Subjects

  • Construction Dispute
  • Contract Law
  • Guarantee Law